Transcontinental Gas Pipe Line Corporation v. FEDERAL ENERGY REGULATORY COMMISSION

518 F.3d 916, 380 U.S. App. D.C. 199, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20065, 2008 U.S. App. LEXIS 4923
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 7, 2008
Docket06-1286
StatusPublished
Cited by14 cases

This text of 518 F.3d 916 (Transcontinental Gas Pipe Line Corporation v. FEDERAL ENERGY REGULATORY COMMISSION) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Corporation v. FEDERAL ENERGY REGULATORY COMMISSION, 518 F.3d 916, 380 U.S. App. D.C. 199, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20065, 2008 U.S. App. LEXIS 4923 (D.C. Cir. 2008).

Opinions

Opinion for the Court filed by Circuit Judge TATEL.

Opinion concurring in part and dissenting in part filed by Circuit Judge BROWN.

TATEL, Circuit Judge:

Its existing pipeline too small to carry gas shipped by several new customers, petitioner Transcontinental Gas Pipe Line Corp. (Transco) expanded its pipeline and installed new compressors to push the added gas through the larger pipeline. In keeping with its normal practice, Transco sought to distribute the additional electricity costs of running the new compressors among all its customers. The Federal Energy Regulatory Commission, no longer supportive of that approach, instead directed the company to allocate the costs only to the customers for whom the pipeline expansion was undertaken. Transco petitions for review, arguing that FERC: (1) acted arbitrarily and capriciously, and (2) failed to show that Transco’s proposal was unjust and unreasonable and that FERC’s alternative was just and reasonable. We disagree on both counts and deny the petition.

[918]*918I.

Transco operates a natural gas pipeline system that connects Gulf of Mexico production sites with customers along the Eastern seaboard. Its system consists of large pipelines and nearly 350 compressors that move gas through the pipelines. This case arises out of Transco’s “Cherokee” project, which, in order to accommodate several new shippers, expanded Transco’s main pipeline in Alabama and added new compressors to push the additional gas through the expanded system.

After completing the Cherokee project, Transco filed new proposed rates with FERC pursuant to the Natural Gas Act (NGA), 15 U.S.C. § 717 et seq., which gives FERC authority to review proposed rates and assure that they are “just and reasonable.” Id. § 717c(a). Under NGA section 4, a pipeline proposing new rates must “prove [to FERC] that its proposed rates are just and reasonable.” Consol. Edison Co. of N.Y., Inc. v. FERC, 165 F.3d 992, 1007 (D.C.Cir.1999) (citing 15 U.S.C. § 717c). By contrast, “when the Commission or an intervenor seeks to impose on the pipeline rates different from either present rates or rates proposed by the pipeline,” NGA section 5 applies and “the Commission or the intervenor must prove that the pipeline’s present rates are not just and reasonable and that the new rates proposed by the Commission or the inter-venor are just and reasonable.” Id. (citing 15 U.S.C. § 717d). Also relevant here, under longstanding FERC policy, “[t]he cost of [new facilities] may be recovered in either of two ways: through ‘incremental’ pricing, which imposes an additional charge payable solely by customers who are directly served by the expansion facilities ...; or ‘rolled-in’ pricing, in which the cost[s] of the new facilities are added to the pipeline’s total rate base and reflected in rates charged to all customers system-wide.” Midcoast Interstate Transmission, Inc. v. FERC, 198 F.3d 960, 964 (D.C.Cir.2000) (citing TransCanada PipeLines Ltd. v. FERC, 24 F.3d 305, 307 n. 1 (D.C.Cir.1994)).

Transco had always rolled in compressor energy costs, and in its rate filing with FERC, it sought to do the same with the costs of running the Cherokee compressors. Under this approach, all customers paid a pro rata share of all compression power costs, and would for the Cherokee compressors as well. Several Transco customers objected, arguing that because Transco had undertaken the Cherokee project to benefit new customers and needed the added compression only for their benefit, the new customers should pay the full power costs of the additional compressors.

Following a hearing, an administrative law judge found that the parties challenging Transco’s proposed rate had demonstrated that it was unjust and unreasonable because it Conflicted with a 1999 FERC policy statement expressing the Commission’s goal of charging only those customers who benefit from a project for the costs of that project. Transcontinental Gas Pipe Line Corp., 101 F.E.R.C. ¶ 63,022 at 65, 095-96 (2002) (citing Certification of New Interstate Natural Gas Pipeline Facilities, 88 F.E.R.C. ¶ 61,227 (1999) (“1999 Policy Statement”)). The ALJ also found that the challenging parties had shown that their alternative pricing approach was just and reasonable. Id. Under that approach, the new customers for whose benefit the expansion was undertaken would pay all the power costs of the project’s compressors, as well as paying their pro rata share of the power costs of the rest of Transco’s system. The Commission affirmed the ALJ’s order. Transcontinental Gas Pipe Line Corp., 106 F.E.R.C. ¶ 61,299 at 62, 125-26 (2004). [919]*919Transco now petitions for review, arguing first that FERC acted arbitrarily and capriciously, and second that FERC failed to demonstrate that Transco’s proposed rate was unjust and unreasonable and that FERC’s alternative was just and reasonable.

II.

We “review FERC orders under the Administrative Procedure Act’s ... arbitrary and capricious standard,” Sithe/Independence Power Partners, L.P. v. FERC, 165 F.3d 944, 948 (D.C.Cir.1999), under which “[w]e must uphold an agency’s action where it ‘has considered the relevant factors and articulated a rational connection between the facts found and the choice made,’ ” Nat’l Ass’n of Clean Air Agencies v. EPA, 489 F.3d 1221, 1228 (D.C.Cir.2007) (quoting Allied Local & Reg’l Mfrs. Caucus v. EPA, 215 F.3d 61, 68 (D.C.Cir.2000)). Our review is “ ‘particularly deferential’ when FERC is involved in the highly technical process of ratemaking,” E. Ky. Power Co-op, Inc. v. FERC, 489 F.3d 1299, 1306 (D.C.Cir.2007) (quoting Ass’n of Oil Pipe Lines v. FERC, 83 F.3d 1424, 1431 (D.C.Cir.1996)), and we “accept the Commission’s factual findings if they are supported by substantial evidence,” id. (citing 16 U.S.C. § 825l(b)).

Transco offers several reasons why it thinks FERC acted arbitrarily and capriciously when it directed that the Cherokee electricity costs be priced incrementally. All lack merit.

First, Transco argues that FERC erred in relying on its 1999 Policy Statement because that statement dealt only with capital costs, not power costs. The 1999 Policy Statement, however, is far broader than Transco admits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
518 F.3d 916, 380 U.S. App. D.C. 199, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20065, 2008 U.S. App. LEXIS 4923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-corporation-v-federal-energy-regulatory-cadc-2008.