Antero Resources Corporation v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 30, 2025
Docket24-1076
StatusPublished

This text of Antero Resources Corporation v. FERC (Antero Resources Corporation v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Antero Resources Corporation v. FERC, (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 10, 2025 Decided September 30, 2025

No. 24-1076

ANTERO RESOURCES CORPORATION AND MU MARKETING LLC, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

NATIONAL FUEL GAS DISTRIBUTION CORPORATION AND TENNESSEE GAS PIPELINE COMPANY, L.L.C., INTERVENORS

On Petition for Review of an Order of the Federal Energy Regulatory Commission

Charlotte H. Taylor argued the cause for petitioners. With her on the briefs was James E. Olson.

Angela X. Gao, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, at the time the brief was filed, and Robert H. Solomon, Solicitor. 2 Paul Korman argued the cause for intervenors in support of respondent. With him on the brief were Michael Diamond and Christopher J. Barr.

Before: MILLETT and RAO, Circuit Judges, and ROGERS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge RAO.

RAO, Circuit Judge: To secure additional pipeline capacity for its natural gas, Antero Resources contracted with Tennessee Gas Pipeline Company for an expansion project. In this petition, Antero challenges the fuel rates it must pay to move its gas through the post-expansion pipeline. Moving natural gas through a pipeline is an energy intensive process, and the cost increases exponentially as more gas flows through the system. Under the tariff approved by the Federal Energy Regulatory Commission, Antero is always treated as if its gas were the last, and therefore marginally most expensive, to be shipped in the pipeline. The other shippers are charged the average cost of all non-Antero shipments. As a practical matter, this allocation has resulted in Antero paying two to three times the fuel rate of other shippers on the same pipeline.

We hold that FERC’s order approving this two-tier fuel rate is arbitrary and capricious. The tariff requires Antero to always pay the highest marginal fuel rate, irrespective of whether the expansion capacity is being used. This results in fuel rates for Antero that are substantially disconnected from the actual costs of shipping Antero’s gas. The rates are not just and reasonable because they violate cost causation, and the Commission has failed to justify its departure from this fundamental principle. We therefore grant Antero’s petition for review and vacate the Commission’s order. 3 I.

Tennessee Gas operates an 11,800-mile network of natural gas pipelines spanning most of the eastern United States. One of Tennessee Gas’s clients is Antero, an independent natural gas producer in the Marcellus Shale, a rich gas field in the Appalachian Basin. This petition concerns Antero’s challenge to the fuel rates Tennessee Gas charges for transporting gas on the Broad Run Pathway, a segment of its pipeline system.

A.

In the early 2010s, a surge in natural gas production in the Marcellus created transportation bottlenecks. Antero wanted guaranteed—or “firm”—pipeline capacity to ensure it could reliably transport its gas to markets on the Gulf Coast, but sufficient firm capacity was not available on existing pipelines. To secure this capacity, Antero and Tennessee Gas agreed to the Broad Run Expansion Project, which would add 200,000 dekatherms per day of new capacity. As the sole shipper for whom the project was to be built, Antero executed a 15-year precedent agreement for all the newly created firm capacity. In exchange, Antero agreed to pay for the construction of the new facilities as well as any applicable “tariff fuel and electric power cost charges.”

The Project expanded capacity by adding new compressor stations along the existing pipeline. Compressors create pressure differentials that move natural gas through pipelines. Powering these compressors requires substantial energy. The relationship between the amount of gas transported through a pipeline and the amount of fuel required to run the compressors is exponential, not linear. As more gas is transported through a fixed-diameter pipe, exponentially more energy—and thus more fuel—is required to move successive units of gas. 4 Tennessee Gas recoups these energy expenses through “fuel rates” paid by shippers. These rates are expressed as a percentage of a shipper’s gas that is required to power the compressors. Because the “fuel curve” is exponential, the marginal cost of shipping gas increases as more gas enters the pipeline. The “last” unit of gas to flow is always the most energy intensive and therefore the most expensive to ship.

B.

Under the Natural Gas Act, a pipeline operator like Tennessee Gas must secure a certificate of public convenience and necessity from FERC before constructing new facilities. Natural Gas Act, Pub. L. No. 75-688, § 7(c), 52 Stat. 821, 825 (1938) (codified as amended at 15 U.S.C. § 717f(c)). In its 2015 certificate application for the Expansion Project, Tennessee Gas distinguished between construction costs and operational costs. Antero is paying, and does not here challenge, the charges proposed by Tennessee Gas to cover the cost of building the new compressors. For the ongoing fuel costs required to operate the new compressors, however, Tennessee Gas initially proposed to “roll in” any fuel costs from running the new compressors, spreading the expense across all shippers on its system. Tennessee Gas explained that the new compressors would be operated on an integrated basis with existing facilities, which would allow Tennessee Gas “to optimize fuel efficiency for all shippers.”

The Commission approved the construction of the Project but rejected the proposal for rolled-in fuel rates. In a 1999 Policy Statement, the Commission had announced a shift away from rolled-in rates, explaining that its primary goal was to prevent existing customers from subsidizing the construction costs of new projects. Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227, 61,745–46 (Sept. 5 15, 1999) (“1999 Policy Statement”), clarified, 90 FERC ¶ 61,128 (Feb. 9, 2000), further clarified, 92 FERC ¶ 61,094 (July 28, 2000). This “no-subsidy” policy was intended to foster competition between pipelines and prevent the “overbuilding of capacity” that can occur when rolled-in rates “mask[] the real cost” of an expansion. 1999 Policy Statement, 88 FERC at 61,745. Applying that policy to Tennessee Gas’s proposed fuel rates, FERC found that rolled-in rates could force existing shippers to subsidize an expansion built for Antero’s benefit. See Tennessee Gas Pipeline Co., LLC, 156 FERC ¶ 61,157, slip decision at ¶ 33 (Sept. 6, 2016). The Commission therefore directed Tennessee Gas to propose incremental fuel rates in future tariff filings to ensure operational costs associated with the new capacity were assigned to Antero.

C.

In its initial 2018 tariff filing under Section 4 of the Natural Gas Act, Tennessee Gas proposed a fuel curve for calculating fuel rates that reflected the exponential nature of fuel costs.

J.A. 342 (depicting results of a 2020 study conducted by Tennessee Gas, comparing the relationship between fuel 6 consumption and throughput for pre-expansion and post- expansion facilities). The curve proposed by Tennessee Gas reflects how fuel costs rise exponentially based on the volume of gas transported through the pipeline. See id.; J.A. 1185.

The tariff also proposed a two-tier system of fuel rates. One rate applied to all shippers except Antero. These shippers would pay a fuel rate based on the average cost, across the fuel curve, of shipping their gas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Antero Resources Corporation v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/antero-resources-corporation-v-ferc-cadc-2025.