Gulf South Pipeline Company v. FERC

955 F.3d 1001
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 10, 2020
Docket19-1074
StatusPublished
Cited by2 cases

This text of 955 F.3d 1001 (Gulf South Pipeline Company v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf South Pipeline Company v. FERC, 955 F.3d 1001 (D.C. Cir. 2020).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued January 14, 2020 Decided April 10, 2020

No. 19-1074

GULF SOUTH PIPELINE COMPANY, LP, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Michael E. McMahon argued the cause for petitioner. With him on the briefs were A. Gregory Junge, Sean Marotta, and Matthew J. Higgins.

Beth G. Pacella, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Robert H. Solomon, Solicitor, and Carol J. Banta, Senior Attorney. Robert M. Kennedy Jr., Attorney, entered an appearance.

Before: HENDERSON and RAO, Circuit Judges, and RANDOLPH, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge RAO. 2

RAO, Circuit Judge: Gulf South Pipeline Company filed an application with the Federal Energy Regulatory Commission (“FERC”) in order to build an expansion to its existing pipeline network. Because the expansion facilities will be dramatically more expensive to construct than the surrounding facilities were, Gulf South requested “incremental-plus rates”—also called “additive rates”—under which all natural gas shippers who use the new facilities will be charged a higher rate reflecting the cost of construction. FERC denied the proposed shipping rates. Instead, FERC effectively approved two separate rates for using the expansion facilities. Only Entergy Louisiana, a new shipper that entered into a long-term contract primarily to use the expansion facilities, will pay a higher rate reflecting the cost of the expansion. Gulf South’s existing shippers will pay a fraction of this cost to use the new facilities.

We hold that FERC’s rejection of incremental-plus rates was arbitrary and capricious. Under FERC’s order, materially identical shippers will pay dramatically different rates for the use of the same facilities. FERC failed to justify that disparity, and its decision violated fundamental ratemaking principles— namely, that rates should generally reflect the burdens imposed and benefits drawn by a given shipper. We therefore vacate the part of FERC’s order denying incremental-plus rates and remand for further proceedings consistent with this opinion. We deny Gulf South’s petition for review in all other respects, including the company’s objections related to its initial rate of return and depreciation rate.

I.

Gulf South operates an extensive network of natural gas pipelines in the southeastern United States. This case is about an application filed by Gulf South under Section 7 of the 3

Natural Gas Act, 15 U.S.C. § 717f, which governs the construction or expansion of pipeline facilities. To build an expansion, a company must first receive a “certificate of public convenience and necessity issued by the Commission.” Id. § 717f(c). FERC will grant such a certificate only if it finds the project “is or will be required by the present or future public convenience and necessity.” Id. § 717f(e). FERC may “attach to the issuance of the certificate and to the exercise of the rights granted thereunder such reasonable terms and conditions as the public convenience and necessity may require.” Id. FERC also reviews initial shipping rates proposed by pipeline companies for new facilities in Section 7 proceedings, but the Commission’s orders are meant only “to hold the line” pending more extensive ratemaking proceedings under Section 4 of the Natural Gas Act. Atl. Ref. Co. v. Pub. Serv. Comm’n of State of N.Y., 360 U.S. 378, 391–92 (1959); see also 15 U.S.C. § 717c.

In the Section 7 filing at issue, Gulf South proposed an expansion within its existing Lake Charles Zone in Louisiana. The Westlake Expansion Project will consist of a compressor station, 0.3 miles of pipeline, and a handful of other facilities, all of which will serve a new power plant owned and operated by Entergy Louisiana. Gas cannot be delivered to the new power plant unless a shipper uses the new compressor station, which in turn will be used only if a shipper is delivering gas to the plant. To deliver gas to Entergy’s power plant, a shipper must also use existing Lake Charles facilities—namely, several miles of an existing pipeline known as the Index 198-3 loop. However, after natural gas passes through the new compressor station, it “will, due to pressure differentials, be physically isolated from the rest of the Lake Charles Zone.” Request for Rehearing of Gulf South Pipeline Co., LP, at 6 (June 18, 2019) (“Rehearing Request”). 4

Entergy, which both operates the new power plant and ships natural gas, entered a precedent agreement with Gulf South—i.e., a long-term contract—agreeing to purchase the entire shipment capacity of the expansion facilities for 20 years. Despite that agreement, Gulf South claims existing shippers in the Lake Charles Zone will at times be able to secure access to the expansion facilities and deliver gas to Entergy’s power plant on what is known as a “secondary-firm” basis. Gulf South Br. 7–11. FERC does not dispute that this could occur on at least some occasions. See, e.g., Gulf South Pipeline Co., LP, 166 FERC ¶ 61,089, ¶ 24 (Feb. 1, 2019) (“Rehearing Order”) (noting that existing shippers will have “limited” access). 1

FERC approved Gulf South’s application to construct the expansion facilities but denied three of the company’s requested rates. See Gulf South Pipeline Co., LP, 163 FERC ¶ 61,124 (May 17, 2018) (“Certificate Order”). First, FERC rejected Gulf South’s proposed incremental-plus rates. Under 1 More specifically, Gulf South claims that existing shippers will occasionally be able to “bump” Entergy by taking advantage of FERC’s open-access policy and priority rules. See Transwestern Pipeline Co., 99 FERC ¶ 61,356, ¶ 11–12 (June 27, 2002) (holding that a secondary-firm shipper’s deliveries have priority over primary- firm shippers like Entergy if the latter fails to schedule a delivery early enough). Of course, the expansion facilities will be used exclusively to deliver gas to Entergy’s power plant, so it is not clear why or when secondary-firm shippers would bump Entergy in order to sell to Entergy. See Oral Argument at 8:48–9:45 (discussion in which Gulf South suggested that Entergy might be forced to buy gas from secondary-firm shippers who secure capacity through FERC’s priority rules). In any event, all parties agree that on some occasions shippers other than Entergy might obtain access to the facilities on a secondary-firm basis, so we assume for the purposes of this appeal that it can occur. 5

Gulf South’s proposal, all shippers using the expansion facilities would pay “both the Lake Charles Zone Rates and the Westlake Expansion Rates.” Id. at ¶ 16. In other words, all shippers would pay their normal rates for use of the Lake Charles Zone facilities, but any shipper who uses the expansion facilities would pay an additional rate reflecting the cost of construction. FERC rejected this proposal in favor of a scheme in which only the expansion shipper—i.e., Entergy—would pay an incremental rate, while the zone’s existing shippers would pay only their normal Lake Charles Zone rates, even when they use the expansion facilities. Id. at ¶¶ 21–22. Because the expansion facilities will be far more expensive to construct than the existing facilities, the rate disparity is significant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. FERC
38 F.4th 220 (D.C. Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
955 F.3d 1001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-south-pipeline-company-v-ferc-cadc-2020.