Chippewa & Flambeau Improvement Co. v. Federal Energy Regulatory Commission

325 F.3d 353, 355 U.S. App. D.C. 453, 2003 U.S. App. LEXIS 7314, 2003 WL 1893253
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 18, 2003
Docket01-1329
StatusPublished
Cited by10 cases

This text of 325 F.3d 353 (Chippewa & Flambeau Improvement Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chippewa & Flambeau Improvement Co. v. Federal Energy Regulatory Commission, 325 F.3d 353, 355 U.S. App. D.C. 453, 2003 U.S. App. LEXIS 7314, 2003 WL 1893253 (D.C. Cir. 2003).

Opinion

Opinion for the Court filed by Chief Judge GINSBURG.

GINSBURG, Chief Judge:

The Chippewa and Flambeau Improvement Company petitions for review of a series of orders in which the Federal Energy Regulatory Commission concluded that the Company must obtain a license under the Federal Power Act for its Turtle-Flambeau reservoir on the Flambeau River in northern Wisconsin. We reject the Company’s arguments that the reservoir is not subject to the Commission’s jurisdiction and hence we deny the petition.

I. Background

In 1924 the predecessor of the Company filed with the predecessor of the Commission a declaration of its intention to create a reservoir for the purpose of developing power by damming the headwaters of the Flambeau River. The Agency, finding both that the North Fork of the Flambeau River was not “navigable” as defined in the Federal Power Act and that the reservoir would not otherwise affect interstate commerce, declined to assert jurisdiction over the project. The Company’s predecessor completed construction of the Turtle-Flambeau storage reservoir in 1926.

Although the reservoir remained free from federal oversight until the issuance of the orders under review, the Company has long been required to operate it in accordance with the rules of the Public Service Commission of Wisconsin and, more recently, pursuant to a 1990 Memorandum of Understanding with the Wisconsin Department of Natural Resources. Those authorities have required the Company to make seasonal releases of water in order to control the risk of flooding and to preserve natural resources. There is no electricity-generating equipment at the reservoir, but the required seasonal releases increase the generation of power at downstream hydroelectric plants, eight of which are owned by the principal shareholders in the Company.

The current dispute has its genesis in the relicensing proceedings of six downstream plants. In the course of those proceedings the Commission staff determined that operation of the Turtle-Flam-beau reservoir increased total generation at plants on the Flambeau River by 8.9 gigawatt-hours per year, or between five and six percent of the total average annual generation at those plants.

In light of this information, the Commission opened a separate docket to consider *356 whether the reservoir should be licensed on the ground that the reservoir is “necessary or appropriate in the maintenance and operation” of the licensed power plants downstream. See 16 U.S.C. § 796(11). In the orders under review, the Commission concluded that the reservoir, because of the benefit it provides to plants downstream, is indeed “part of the complete unit of development that includes those projects,” Chippewa & Flambeau Improvement Co., 95 F.E.R.C. ¶ 61,327 at 62,159, 2001 WL 34076867, 2001 FERC LEXIS 1278 (June 1, 2001) (Order Denying Rehearing), and therefore is subject to licensing under the Federal Power Act. The Company petitioned for review.

II. Analysis

The Company contends first that the Commission’s assertion of jurisdiction over the Turtle-Flambeau reservoir is precluded by the Commission’s pre-construction determination that it would lack jurisdiction over the same reservoir. Second, the Company argues that the Commission failed adequately to explain why the reservoir is “necessary or appropriate” to the maintenance and operation of downstream plants. Finally, the Company argues that the Commission arbitrarily limited its analysis to the four projects closest to the reservoir, and thereby inflated the effect that operation of the reservoir has upon downstream power generation, measured as a percentage increase in power output.

A. Issue preclusion

In response to the Company’s suggestion that the Commission is bound by its previous determination that the reservoir is not subject to federal licensing requirements, the Commission maintains it is free to reexamine its findings in order to take account of changes in the relevant facts and the governing law. See Nant-ahala Power & Light Co. v. FPC, 384 F.2d 200, 206 (4th Cir.1967). The Commission points out that its initial determination rested upon a more restrictive definition of “navigable waters” than that subsequently adopted by the Supreme Court in United States v. Appalachian Elec. Power Co., 311 U.S. 377, 61 S.Ct. 291, 85 L.Ed. 243 (1940). Under the Commission’s earlier approach a river that could be made navigable by improvements was not considered a navigable waterway. As a consequence, neither the Turtle-Flambeau reservoir nor the downstream power plants were subject to licensing, and the Commission therefore had no occasion to determine whether the reservoir might be “necessary or appropriate” to the operation of a licensed plant.

Now, by contrast, it is undisputed that the Flambeau River is “navigable,” and the Commission has licensed all the downstream plants (with the exception of one that is exempt). Therefore, the Commission argues, the precise question at issue — namely, whether the Turtle-Flam-beau reservoir should be licensed because it is necessary or appropriate to the operation of a licensed plant — arose for the first time in this proceeding, and the Commission is not bound by the answer it gave to the jurisdictional question at an earlier time. See, e.g., Clark-Cowlitz Joint Operating Agency v. FERC, 826 F.2d 1074, 1079 (D.C.Cir.1987) (en banc) (“[a] fundamental requisite of issue preclusion is an identity of the issue decided in the earlier action and that sought to be precluded in a later action”).

In reply the Company relies upon an unrelated 1922 decision in which the Commission’s predecessor disclaimed jurisdiction over hydroelectric projects — notwithstanding the presence upstream of a federally-licensed storage reservoir — on the ground that the Chippewa River was not navigable. See Federal Power *357 Comm’n, Second Annual Report 61-62, 150-51 (1922). According to the Company, the Commission’s action

clearly demonstrate[s] that, even if the Commission had jurisdiction over one component (i.e., over the upstream storage reservoir or over the downstream hydro projects benefitted by the storage reservoir) it was not in the 1920s asserting jurisdiction over the other component under a “complete unit” or any other theory. Thus, even if Appalachian Power had been the law in 1925 and the [Commission] had at that time asserted jurisdiction over the downstream hydroelectric projects on the Flambeau River based on their location on “navigable waters,” the [Commission] would not have asserted jurisdiction over Turtle-Flambeau.

The Company’s argument asks too much of preclusion doctrine.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Widakuswara v. Lake
District of Columbia, 2026
Kentucky Municipal Energy Agency v. FERC
45 F.4th 162 (D.C. Circuit, 2022)
Huawei Tech USA v. FCC
2 F.4th 421 (Fifth Circuit, 2021)
Gulf South Pipeline Company v. FERC
955 F.3d 1001 (D.C. Circuit, 2020)
Herrera v. Wyoming
587 U.S. 329 (Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
325 F.3d 353, 355 U.S. App. D.C. 453, 2003 U.S. App. LEXIS 7314, 2003 WL 1893253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chippewa-flambeau-improvement-co-v-federal-energy-regulatory-commission-cadc-2003.