Domtar Maine Corp. v. Federal Energy Regulatory Commission

347 F.3d 304, 358 U.S. App. D.C. 193, 2003 U.S. App. LEXIS 21973, 2003 WL 22432854
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 28, 2003
Docket97-1300 & 02-1178
StatusPublished
Cited by10 cases

This text of 347 F.3d 304 (Domtar Maine Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Domtar Maine Corp. v. Federal Energy Regulatory Commission, 347 F.3d 304, 358 U.S. App. D.C. 193, 2003 U.S. App. LEXIS 21973, 2003 WL 22432854 (D.C. Cir. 2003).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

The Federal Power Act of 1920, 16 U.S.C. § 791a et seq., requires licensing of all dams operated on navigable waters for the purpose of generating electric power, except those authorized by a valid pre-Act permit. In this case, we must decide whether two dams are exempt from licensing because their owner operates other dams downstream pursuant to such a permit. The Federal Energy Regulatory Commission found them not exempt. Because we agree, and because we find no error in FERC’s challenged orders, we deny the petitions for review.

*306 I.

Section 4(e) of the Federal Power Act (FPA) authorizes the Federal Energy-Regulatory Commission to “issue licenses ... for the purpose of constructing, operating, and maintaining dams, ... reservoirs, ... or other project works necessary or convenient for the ... development, transmission, and utilization of power across, along, from, or in any ... bodies of water over which Congress has jurisdiction. ...” 16 U.S.C. § 797(e) (2000). Section 23(b)(1) makes it “unlawful ..., for the purpose of generating electric power, to construct, operate, or maintain any dam, ... reservoir, ... or other works incidental thereto across, along, or in any of the navigable waters of the United States,” unless FERC has issued a proper license. Id. § 817(1). That section, however, exempts any facility operating “under and in accordance with the terms of a permit or valid existing right-of-way granted prior to June 10, 1920,” the date the FPA became law. Id.

Petitioner, Domtar Maine Corporation, owns several hydroelectric facilities in eastern Maine. Its Forest City facility, located along the U.S.-Canadian border on the east branch of the St. Croix River, includes “a 16-foot-high, 500-foot-long dam, and a 16,070-acre reservoir.” Ga.-Pac. Corp., 78 F.E.R.C. ¶ 61,223, 61,953 (1997). Domtar’s West Branch facility, located on the west branch of the St. Croix, comprises two developments, each of which also includes a dam and a reservoir. Id. Both of Domtar’s facilities enhance the power-generating capabilities of two downstream projects that Domtar also operates, Woodland and Grand Falls. Forest City is thirty-five miles upstream from Grand Falls and forty-seven from Woodland; West Branch is ten miles upstream from Grand Falls and twenty-two from Woodland. Id. Although FERC licensed the two upstream facilities in 1980, it never licensed the downstream projects because they operate pursuant to a 1916 Act of Congress, see Pub.L. No. 64-234, 39 Stat. 534 (1916), and thus qualify for the exception to the FPA’s licensing requirement. (Domtar actually acquired the licenses to the upstream facilities in 2001, well after the previous licensee, Georgia-Pacific Corporation, initiated the proceedings in this case. See Ga.-Pac. Corp., Domtar Me. Corp., 97 F.E.R.C. ¶ 62,078, 64,114-15 (2001). For simplicity, we will refer to the petitioner as Domtar regardless of the time period under discussion.)

In 1995, Domtar started down what would prove to be a long and complex procedural path culminating in the proceedings now before us. The company petitioned FERC to declare that the two upstream facilities, though already licensed, actually fell outside FERC’s jurisdiction because the downstream projects that they benefited were themselves exempt from the licensing requirement. FERC declined to do so, holding that the downstream projects’ exemption had no effect on the jurisdictional status of the upstream dams. See Ga.-Pac. Corp., 77 F.E.R.C. ¶ 62,189 (1996) (Ruling 1), reh’g denied, 78 F.E.R.C. ¶ 61,223 (1997) (Ruling 2).

Although Domtar petitioned this court to review Rulings 1 and 2, we stayed those proceedings after Domtar filed a second petition with FERC. In that petition, Domtar asked the Commission to reverse its previous decisions and hold that the upstream facilities needed no licenses. Domtar based its request on new evidence purportedly showing that the upstream facilities did not enhance the power-generation capabilities of the downstream projects. According to Domtar, this meant that neither facility was part of any “project,” defined by FPA section 3(11) as a *307 “complete unit of improvement or development, [including] all ... dams [and] reservoirs ... the use and occupancy of which are necessary or appropriate in the maintenance and operation of such unit.” 16 U.S.C. § 796(11) (emphasis added). Based on Domtar’s new evidence, FERC agreed that the upstream facilities did not enhance downstream power generation and thus required no licenses. See Ga.-Pac. Corp., 81 F.E.R.C. ¶ 62,222 (1997) (Ruling 3).

The following month, several groups that had previously sought to intervene in the proceedings — including the U.S. Department of the Interior and the Passama-quoddy Tribe — petitioned FERC to rehear Ruling 3. In response, FERC asked Dom-tar for additional data regarding the upstream facilities, and after analyzing the data, FERC again reversed itself, concluding that the facilities in fact required licenses. See Ga.-Pac. Corp., 91 F.E.R.C. ¶ 61,047 (2000) (Ruling 4), reh’g denied, 98 F.E.R.C. ¶ 61,312 (2002) (Ruling 5). Domtar then filed a second petition for review with this court, but simultaneously asked FERC to rehear two aspects of Ruling 5— its refusal to offer the company any guidance on how to operate the facilities so as to avoid the licensing requirement, and its decision to solicit other applicants to replace Domtar as the licensee. Responding to Domtar’s request, FERC issued a final order, again declining to provide the requested advice and standing by its decision to solicit other license applicants, but ruling that it would give Domtar an incumbent’s preference in any re-licensing proceedings. See Domtar Me. Corp., 99 F.E.R.C. ¶ 61,276 (2002) (Ruling 6).

Domtar then filed a third petition for review with this court, in which it listed Ruling 6 as the ruling under review. At the time, the company’s second petition for review was still pending, but we subsequently dismissed that petition as premature, explaining that when Domtar filed the petition, the company was still pressing its case before the Commission. See Domtar Me. Corp. v. FERC, Nos. 97-1300, 02-1126, 02-1178, 2002 U.S.App. LEXIS 18,157 (D.C.Cir. Aug. 29, 2002) (unpublished order). We also consolidated Dom-tar’s first and third petitions. Id. FERC subsequently filed a motion to dismiss the third petition, which we now address along with Domtar’s first and third petitions. We also consider intervenor Passamaquoddy Tribe’s argument that we should remand the case so that FERC can determine whether the upstream facilities occupy “reservations of the United States,” and thus require a license under FPA section 23(b)(1).

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
347 F.3d 304, 358 U.S. App. D.C. 193, 2003 U.S. App. LEXIS 21973, 2003 WL 22432854, Counsel Stack Legal Research, https://law.counselstack.com/opinion/domtar-maine-corp-v-federal-energy-regulatory-commission-cadc-2003.