Myersville Citizens for a Rural Community, Inc. v. Federal Energy Regulatory Commission

783 F.3d 1301, 414 U.S. App. D.C. 438, 180 Oil & Gas Rep. 1093, 80 ERC (BNA) 1649, 2015 U.S. App. LEXIS 6779, 2015 WL 1873139
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 24, 2015
Docket13-1219
StatusPublished
Cited by76 cases

This text of 783 F.3d 1301 (Myersville Citizens for a Rural Community, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myersville Citizens for a Rural Community, Inc. v. Federal Energy Regulatory Commission, 783 F.3d 1301, 414 U.S. App. D.C. 438, 180 Oil & Gas Rep. 1093, 80 ERC (BNA) 1649, 2015 U.S. App. LEXIS 6779, 2015 WL 1873139 (D.C. Cir. 2015).

Opinion

Opinion for the Court filed by Circuit Judge PILLARD.

PILLARD, Circuit Judge:

Citizens of the small town of Myersville, in Frederick County, Maryland, oppose the construction of a natural gas facility called a compressor station in their town. The compressor station is a small part of a larger expansion of natural gas facilities in the northeastern United States proposed by Dominion Transmission, Inc., a regional natural gas company and Intervenor in this case. Dominion, which is in the business of storing and transporting natural gas, requested approval from the Federal Energy Regulatory Commission to move ahead with the project. The Commission, over the objections of the Myersville citizens, conditionally approved it in December 2012. Dominion then fulfilled the Commission’s conditions, including obtaining a Clean Air Act permit from the Maryland Department of the Environment. Dominion built the station, and it has been operating for approximately six months.

The Myersville citizens petition this court to vacate the Commission’s order approving the project. They attack the Commission’s decision on a number of fronts. They argue that the Commission lacked substantial evidence to conclude that there was a public need for the project Dominion proposed. They assert that the Commission unlawfully interfered with Maryland’s rights under the Clean Air Act. *1307 They challenge the Commission’s environmental review of the project, including its consideration of potential alternatives. And they claim the Commission unlawfully withheld hydraulic flow diagrams from them in violation of their due process rights. Because we conclude that each of Petitioners’ challenges lacks merit, we deny the petition for review.

I.

Dominion runs underground natural gas storage and transportation facilities in six northeastern and mid-Atlantic states. Dominion operates over 947 billion cubic feet of storage capacity and approximately 11,-000 miles of natural gas pipeline. Before it sought the Commission’s approval, Dominion conducted an “open season” in which it offered contracts for future supply of natural gas to potential customers. It entered contracts with two municipal utilities and a natural gas distribution company for firm transportation and storage services. 1 Dominion’s proposed project, called the “Allegheny Storage Project,” called for new or expanded natural gas facilities in Maryland, Ohio, West Virginia, and Pennsylvania, thereby providing to Dominion’s customers an additional 115,-000 dekatherms per day of firm transportation, 7.5 billion cubic feet of storage capacity, and 125,000 dekatherms per day of storage withdrawal at an estimated cost of over $112 million. 2

The Project required the building of two compressor stations — facilities along a pipeline that compress gas to move it through the system at high speeds — and additional pipeline to serve the compressors. One of those compressor stations is located on a twenty-one-acre plot in the town of Myersville. That compressor station is the subject of this appeal.

Congress enacted the Natural Gas Act, ch. 556, 52 Stat. 821 (1938) (codified as amended at 15 U.S.C. § 717 et seq.), with the “principal purpose” of “eneourag[ing] the orderly development of plentiful supplies of ... natural gas at reasonable prices,” NAACP v. Fed. Power Comm’n, 425 U.S. 662, 669-70, 96 S.Ct. 1806, 48 L.Ed.2d 284 (1976). “[Sjubsidiary” purposes include respecting “conservation, environmental, and antitrust” limitations. Id. at 670 & n. 6, 96 S.Ct. 1806. The Act vests the Commission with authority to regulate the transportation and sale of natural gas in interstate commerce, including authority to issue certificates permitting the construction or extension of natural gas transportation facilities, such as those Dominion operates. 15 U.S.C. § 717f(c).

Before any applicant may construct or extend natural gas transportation facilities, it must obtain a “certificate of public convenience and necessity” from’the Commission pursuant to Section 7(c) of the Act. Id. § 717f(e)(l)(A). The Commission may issue a certificate to “any qualified applicant” if it finds that “the applicant is able and willing properly to do the acts and to perform the service proposed ... and that the proposed service” and “construction ... is or will be required by the present or future public convenience and necessity.” Id. § 717f(e). As part of its certificate authority, fhe Commission has the “power to attach to the issuance of the certificate and to the exercise of the rights granted *1308 thereunder such reasonable terms and conditions as the public convenience and necessity may require.” Id.

Petitioners in this case — Myersville Citizens for a Rural Community, Inc. and citizens of Myersville Franz Gerner, Ted Cady, and Tammy Mangan — protest the building of the Myersville compressor station. During the public comment process before the Commission, they raised objections, several of which form the basis of the current petition.

After preparing an Environmental Assessment of the Allegheny Storage Project, the Commission rejected the objections made by Petitioners and others and granted Dominion a conditional Section 7 certificate. Dominion Transmission, Inc., 141 FERC ¶ 61,240 (Dec. 20, 2012) (“Certificate Order”). The Commission conditioned the certificate, in part, on Dominion’s ability to secure all necessary federal authorizations, including Clean Air Act permits. Certificate Order, App. B, Envtl. Condition 8. After considering renewed objections, the Commission denied rehearing. Dominion Transmission, Inc., 143 FERC ¶ 61,148 (May 16, 2013) (“Rehearing Order ”). The Myersville compressor station was placed into service on November 1, 2014. FERC, Docket No. CP12-72, Supplemental Information Filing Replacing Previous filed In Service Notification Request of Dominion Transmission, Inc. under CP 12-72 (filed Nov. 10, 2014). Petitioners timely petitioned for review of the Commission’s orders.

We have jurisdiction pursuant to 15 U.S.C. § 717r(b). Our review of the Commission’s decision is limited to determining whether the order was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); see Minisink Residents for Envtl. Pres. & Safety v. FERC, 762 F.3d 97, 105-06 (D.C.Cir.2014). “If supported by substantial evidence, the Commission’s findings of fact are conclusive.” B & J Oil & Gas v. FERC, 353 F.3d 71, 76 (D.C.Cir.2004) (citing 15 U.S.C. §

Related

Sierra Club v. FERC
D.C. Circuit, 2025
Healthy Gulf v. Haaland
District of Columbia, 2025
Sierra Club v. DOT
125 F.4th 1170 (D.C. Circuit, 2025)
American Whitewater v. FERC
125 F.4th 1139 (D.C. Circuit, 2025)
City of Port Isabel v. FERC
111 F.4th 1198 (D.C. Circuit, 2024)
New Jersey Conservation Foundation v. FERC
111 F.4th 42 (D.C. Circuit, 2024)
Columbia Gulf Transmission, LLC v. FERC
106 F.4th 1220 (D.C. Circuit, 2024)
Earthworks v. DOI
105 F.4th 449 (D.C. Circuit, 2024)
El Puente v. United States Army Corps of Engineers
100 F.4th 236 (D.C. Circuit, 2024)
Seia v. Ferc
Ninth Circuit, 2023
Fairless Energy, LLC v. FERC
77 F.4th 1140 (D.C. Circuit, 2023)
Solenex LLC v. Bernhardt
District of Columbia, 2022

Cite This Page — Counsel Stack

Bluebook (online)
783 F.3d 1301, 414 U.S. App. D.C. 438, 180 Oil & Gas Rep. 1093, 80 ERC (BNA) 1649, 2015 U.S. App. LEXIS 6779, 2015 WL 1873139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/myersville-citizens-for-a-rural-community-inc-v-federal-energy-cadc-2015.