Citizens Action Coalition of Indiana, Inc. v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 7, 2025
Docket23-1046
StatusPublished

This text of Citizens Action Coalition of Indiana, Inc. v. FERC (Citizens Action Coalition of Indiana, Inc. v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens Action Coalition of Indiana, Inc. v. FERC, (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued May 7, 2024 Decided January 7, 2025

No. 23-1046

CITIZENS ACTION COALITION OF INDIANA, INC., PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

TEXAS GAS TRANSMISSION, LLC, INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Kirti Datla argued the cause for petitioner. On the briefs were Moneen Nasmith, Ann Jaworski, Sameer Doshi, Raghu Murthy, and Aaron Stemplewicz.

Susanna Y. Chu, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. Scott R. Ediger, Attorney Advisor, entered an appearance. 2 Sean Marotta argued the cause for intervenor in support of respondent. With him on the brief were Michael E. McMahon, A. Gregory Junge, and Reedy C. Swanson.

Before: KATSAS, RAO, and WALKER, Circuit Judges.

Opinion for the Court filed by Circuit Judge RAO.

RAO, Circuit Judge: As night follows day, an environmental challenge follows the approval of a natural gas pipeline. In this case, the State of Indiana approved a plan that would retire a coal-fired facility and replace it with wind and solar energy sources. To ensure grid reliability with the move to renewable energy, the plan also included two new natural gas turbines. The Federal Energy Regulatory Commission approved a natural gas pipeline to serve those turbines. The Citizens Action Coalition of Indiana petitions for review, alleging that FERC’s environmental analysis and order were unreasonable and inconsistent with the National Environmental Policy Act and the Natural Gas Act.

Citizens Action alleges numerous errors, but its core claim is that FERC was required to analyze non-gas alternatives before approving the natural gas pipeline. We disagree. Congress gave FERC authority to promote the development of interstate natural gas pipelines, but it left the choice of energy generation to the States. The purpose of the pipeline was to support Indiana’s energy plan, and FERC has no statutory authority to consider non-gas alternatives already rejected by the State. Because FERC acted lawfully and reasonably when conducting the environmental analysis and assessing the public convenience and necessity for the pipeline, we deny the petition for review. 3 I.

A.

The Natural Gas Act (“NGA”) empowers FERC to approve the development of interstate natural gas pipelines. Pub. L. No. 75-688, 52 Stat. 821 (1938) (codified as amended at 15 U.S.C. § 717 et seq.). FERC must issue a certificate approving a pipeline if it determines the project is “required by the present or future public convenience and necessity.” 15 U.S.C. § 717f(e). When making this determination, FERC must consider “all factors bearing on the public interest,” Food & Water Watch v. FERC, 104 F.4th 336, 341 (D.C. Cir. 2024) (cleaned up), and may “approve a project only where the public benefits outweigh the project’s adverse impacts,” Minisink Residents for Env’t Preservation & Safety v. FERC, 762 F.3d 97, 102 (D.C. Cir. 2014) (cleaned up).

If FERC determines that approval of a pipeline would constitute a “major federal action significantly affecting the quality of the human environment,” FERC must prepare an environmental impact statement. National Environmental Policy Act (“NEPA”), Pub. L. No. 91-190, § 102(2)(C), 83 Stat. 852, 853 (1970) (codified as amended at 42 U.S.C. § 4332(2)(C)). NEPA requires an agency to “identify the reasonable alternatives to the contemplated action and look hard at the environmental effects of its decision.” Minisink, 762 F.3d at 102 (cleaned up). NEPA is a purely procedural statute, however, and does not require an agency “to take one type of 4 action or another.” Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 194 (D.C. Cir. 1991).

B.

Citizens Action challenges FERC’s approval of a pipeline serving two new natural gas turbines in Indiana. We begin with Indiana’s decision to approve those turbines.

CenterPoint Energy is an electric utility in southwestern Indiana. As part of the state regulatory process, CenterPoint must prepare an Integrated Resource Plan every three years. See IND. CODE § 8-1-8.5-3(e); 170 IND. ADMIN. CODE § 4-7 (requiring utilities to evaluate their total mix of generation resources and consider the tradeoffs between cost, reliability, and environmental impacts). In its 2016 Plan, CenterPoint proposed replacing coal-fired facilities at its A.B. Brown Generating Station with solar resources and natural gas. Because solar resources provide only intermittent power, the natural gas facility would “maintain constant electric supply during potentially extended periods of low output.” CenterPoint applied to the Indiana Utility Regulatory Commission for approval of an 850-megawatt natural gas unit. See IND. CODE § 8-1-8.5-2. The Indiana Commission initially denied the proposal because CenterPoint failed to adequately consider alternatives to natural gas and because the proposed unit could compromise future energy flexibility.

In response, CenterPoint modified its Plan to include wind generation, in addition to solar, and applied to build two smaller gas-fired turbines, which would produce a combined 460 megawatts of power. This time, the Indiana Commission approved the application after concluding the proposed natural gas units would be “a reasonable, least-cost resource to support [CenterPoint’s] Plan and meet consumers’ needs for electricity.” 5 C.

That brings us to the pipeline at issue here. CenterPoint contracted with Texas Gas Transmission to supply natural gas to the planned units. Texas Gas then applied to FERC for approval of a 24-mile pipeline crossing the Ohio River and connecting the A.B. Brown site to an existing pipeline system in Kentucky. Citizens Action, an environmental advocacy organization, intervened in the FERC proceeding and filed comments concerning the environmental effects of the pipeline and related infrastructure (the “Project”).

After preparing an environmental impact statement, FERC approved the Texas Gas Project. Citizens Action filed a request for rehearing, raising four challenges. It argued that FERC (1) failed to consider alternatives to building gas-fired units; (2) failed to label the Project’s emissions as “significant” or “not significant”; (3) erred by netting the reduction in emissions from the coal-fired units’ retirement against the gross emissions from the gas-fired units; and (4) failed to properly balance environmental impacts in its public convenience and necessity determination. FERC took no action on the rehearing request, so it was denied by operation of law.

Citizens Action now petitions for review of FERC’s order approving the Texas Gas Project. We have jurisdiction under 15 U.S.C. § 717r(b). We review Citizens Action’s NEPA and NGA challenges under the Administrative Procedure Act to determine whether FERC’s environmental assessment and order were “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Department of Transportation v. Public Citizen
541 U.S. 752 (Supreme Court, 2004)
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357 (D.C. Circuit, 2017)
Birckhead v. Fed. Energy Regulatory Comm'n
925 F.3d 510 (D.C. Circuit, 2019)
West Virginia v. EPA
597 U.S. 697 (Supreme Court, 2022)
Coalition of MISO Transmission v. FERC
45 F.4th 1004 (D.C. Circuit, 2022)
Citizens Against Burlington, Inc. v. Busey
938 F.2d 190 (D.C. Circuit, 1991)
Nevada v. Department of Energy
457 F.3d 78 (D.C. Circuit, 2006)
Center for Biological Diversity v. FERC
67 F.4th 1176 (D.C. Circuit, 2023)
Alabama Municipal Distributors Group v. FERC
100 F.4th 207 (D.C. Circuit, 2024)
Food & Water Watch v. FERC
104 F.4th 336 (D.C. Circuit, 2024)
Healthy Gulf v. FERC
107 F.4th 1033 (D.C. Circuit, 2024)
New Jersey Conservation Foundation v. FERC
111 F.4th 42 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Citizens Action Coalition of Indiana, Inc. v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-action-coalition-of-indiana-inc-v-ferc-cadc-2025.