Alabama Municipal Distributors Group v. FERC

100 F.4th 207
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 30, 2024
Docket22-1101
StatusPublished
Cited by8 cases

This text of 100 F.4th 207 (Alabama Municipal Distributors Group v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alabama Municipal Distributors Group v. FERC, 100 F.4th 207 (D.C. Cir. 2024).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 5, 2023 Decided April 30, 2024

No. 22-1101

ALABAMA MUNICIPAL DISTRIBUTORS GROUP, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

SOUTHERN NATURAL GAS COMPANY, L.L.C., ET AL., INTERVENORS

Consolidated with 22-1171, 22-1256, 22-1273

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Nathan Matthews argued the cause for petitioners Sierra Club and Healthy Gulf. With him on the briefs was Rebecca McCreary. 2 Randolph Lee Elliott argued the cause for Municipal petitioners. With him on the briefs were James R. Choukas-Bradley and Joshua L. Menter.

Carol J. Banta, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, and Lona T. Perry, Deputy Solicitor. Matthew W.S. Estes, Attorney, entered an appearance.

Brian D. O’Neill argued the cause for respondent- intervenors Southern Natural Gas Company, L.L.C., et al. With him on the brief were Michael R. Pincus, Sandra Y. Snyder, Richard P. Bress, J. Patrick Nevins, and Eric J. Konopka.

Before: SRINIVASAN, Chief Judge, WALKER, Circuit Judge, and GINSBURG, Senior Circuit Judge

Opinion for the Court filed by Circuit Judge WALKER.

WALKER, Circuit Judge: Natural gas companies must obtain “a certificate of public convenience and necessity” from the Federal Energy Regulatory Commission before they construct, operate, or expand an interstate natural gas pipeline. 15 U.S.C. § 717f(c)(1)(A). In this case, FERC certified the Evangeline Pass Expansion Project — a series of expanded pipelines, compression facilities, and meter stations in the Southeastern United States. Environmental groups challenge that certification, alleging that FERC improperly applied the National Environmental Policy Act. 42 U.S.C. § 4321 et seq.

FERC’s certification was reasonable and reasonably explained. So was its decision to deny a windfall to a pipeline 3 owner’s existing customers. We therefore deny the petitions for review.

I. Background

FERC and the Department of Energy share regulatory authority over natural gas. Section 7 of the Natural Gas Act allows FERC to issue “a certificate of public convenience and necessity” to any entity that seeks to construct, operate, or expand an interstate natural gas pipeline. 15 U.S.C. § 717f(c)(1)(A).

However, Section 7 does not reach foreign commerce. See 15 U.S.C. § 717f. Foreign commerce instead falls under Section 3 of the Natural Gas Act. See 15 U.S.C. § 717b. That section grants FERC regulatory authority over the construction, operation, and expansion of export facilities. 15 U.S.C. § 717b(e).

But no section of the Natural Gas Act gives FERC authority over the exported gas itself. Instead, the “exclusive authority” over exported gas belongs to the Department of Energy. Sierra Club v. FERC, 827 F.3d 36, 40 (D.C. Cir. 2016) (“Freeport”) (citing 42 U.S.C. § 7151(b)).

Thus, we end up with the following distinct scopes of authority mandated by Congress:

Interstate Pipelines FERC Export Facilities FERC Natural Gas Exports Department of Energy

No matter which scope of authority is invoked, FERC (for interstate pipelines or export facilities) or the Department of Energy (for natural gas exports) must consider the National 4 Environmental Policy Act. 42 U.S.C. § 4321 et seq. Among other things, the Act requires the relevant government entity to consider a project’s potential environmental impact in one of two ways — either through an environmental impact statement (the more onerous analysis) or an environmental assessment (the less onerous analysis). See 42 U.S.C. § 4332(2)(C). Either way, the Act requires the relevant government entity to consider any actions that are “connected” to the proposed project. See 40 C.F.R. § 1501.9(e)(1).1

In 2020, Tennessee Gas Pipeline Company and Southern Natural Gas Company applied under Section 7 of the Natural Gas Act for approval of the Evangeline Pass Expansion Project.2 Tennessee Gas wanted to construct and replace pipelines and compression facilities. Similarly, Southern wanted to build a compression facility and meter stations. Although pipelines, compression facilities, and meter stations serve different functions, the bottom-line goal of the Evangeline Pass Project was to move more gas.

The Sierra Club protested the applications.3 Although it asserted different arguments at different stages of the

1 When certification for the Evangeline Pass Expansion Project was sought — February 2020 — the definition of “connected actions” was listed in 40 C.F.R. § 1508.25(a)(1). The definition was later moved to, and remains under, 40 C.F.R. § 1501.9(e)(1). In this opinion, we cite to the regulation as it is today. 2 Although Tennessee Gas and Southern’s projects were listed as separate projects in the FERC order, both involved the same pipeline. For simplicity, we refer to both projects as the Evangeline Pass Expansion Project. 3 Healthy Gulf joined the Sierra Club in its protest. For simplicity, we will refer to both petitioners as the Sierra Club. 5 certification process, Sierra Club ultimately said FERC violated the National Environmental Policy Act by (1) not considering the environmental effects of four other natural-gas projects it thinks are connected to the Evangeline Pass Project; (2) not considering the indirect environmental effects of gas from the Evangeline Pass Project after that gas is exported; and (3) not relying on an analytical tool known as the social cost of carbon metric.4

In addition, a municipal customer of Southern — the Alabama Municipal Distributors Group — argued that a new lease from Southern to Tennessee Gas may mean more profits for Southern, so Alabama Municipal should receive a portion of those profits.5 The new lease was made possible by the Evangeline Pass Project.

FERC unanimously issued a Certificate Order to Tennessee Gas and Southern, denying all objections. Tennessee Gas Pipeline Co., LLC, 178 FERC ¶ 61,199, at 46- 48 (Mar. 25, 2022). It reaffirmed its determination on rehearing. Tennessee Gas Pipeline Co., LLC, 180 FERC ¶ 61,205, at 43 (Sept. 29, 2022).

The Sierra Club and Alabama Municipal timely petitioned for review. We now deny those petitions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rover Pipeline, L.L.C. v. Harris
2025 Ohio 2806 (Ohio Supreme Court, 2025)
Sierra Club v. FERC
D.C. Circuit, 2025
Healthy Gulf v. FERC
107 F.4th 1033 (D.C. Circuit, 2024)
Food & Water Watch v. FERC
104 F.4th 336 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
100 F.4th 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alabama-municipal-distributors-group-v-ferc-cadc-2024.