City of Bos. Delegation v. Fed. Energy Regulatory Comm'n

897 F.3d 241
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 27, 2018
DocketNo. 16-1081; C/w 16-1098; 16-1103
StatusPublished
Cited by20 cases

This text of 897 F.3d 241 (City of Bos. Delegation v. Fed. Energy Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Bos. Delegation v. Fed. Energy Regulatory Comm'n, 897 F.3d 241 (D.C. Cir. 2018).

Opinion

III.

We review the Commission's grant of a Section 7 certificate "under the familiar arbitrary and capricious standard," bearing in mind that "the grant or denial of" such a certificate "is a matter peculiarly within the discretion of the Commission." Minisink , 762 F.3d at 105-06 (brackets and citation omitted). Applying that standard, we sustain the Commission's order against the challenges brought jointly by the Town, Riverkeeper, and the coalition.

A.

In the first set of arguments raised by petitioners, they contend that the Commission failed to comply with NEPA in approving the AIM Project. NEPA generally obligates agencies to take a " 'hard look' at the environmental impacts of a proposed action." Myersville , 783 F.3d at 1324. An environmental impact statement is "deficient, and the agency action it undergirds is arbitrary and capricious, if the EIS does not contain sufficient discussion of the relevant issues and opposing viewpoints, or if it does not demonstrate reasoned decisionmaking." Sierra Club , 867 F.3d at 1368 (internal quotation marks and citations omitted). In evaluating an agency's NEPA analysis, we apply a "rule of reason," and have "refused to 'flyspeck' the agency's findings in search of 'any deficiency no matter how minor.' " Myersville , 783 F.3d at 1322-23 (quoting Nevada v. Dep't of Energy , 457 F.3d 78, 93 (D.C. Cir. 2006) ).

Petitioners present two related arguments under NEPA. First, petitioners contend that the Commission improperly segmented its environmental review by failing to examine the AIM Project and Algonquin's two other pipeline upgrade projects together in a single environmental statement. Second, petitioners submit that the Commission failed to give adequate consideration to the cumulative environmental impacts of the three upgrade projects. We find no basis to set aside the Commission's order on those grounds.

1.

Under the Council on Environmental Quality's regulations implementing NEPA, agencies must consider all "connected actions," "cumulative actions," and "similar actions" within a single environmental impact statement. 40 C.F.R. § 1508.25(a). "An agency impermissibly 'segments' NEPA review when it divides connected, cumulative, or similar federal actions into separate projects and thereby fails to address the true scope and impact of the activities that should be under consideration." Del. Riverkeeper Network v. FERC , 753 F.3d 1304, 1313 (D.C. Cir. 2014). The rule ensures that an agency considers the full environmental impact of "connected, cumulative, or similar" actions before they are undertaken, so that it can assess the true costs of an integrated project *252when it is best situated to evaluate "different courses of action" and mitigate anticipated effects. Id . at 1313-14.

This court has developed a set of factors that help clarify when "physically connected projects can be analyzed separately under NEPA." Id. at 1315. As relevant here, when an agency considers projects non-contemporaneously, see id. at 1318, and when projects have "substantial independent utility," id . at 1316, separate environmental statements can be appropriate.

Applying those considerations in Delaware Riverkeeper , we concluded that the Commission had impermissibly segmented its review of four pipeline upgrades. The projects, we explained, were "connected and interrelated" and "functionally and financially interdependent," and they also had significant "temporal overlap," id. at 1319, because they were "either under construction" or "pending before the Commission for environmental review and approval" at the same time, id. at 1308.

In Minisink and Myersville , by contrast, we sustained the Commission's conduct of separate environmental assessments. In Minisink , we noted that the projects in question lacked the temporal overlap that had characterized the projects in Delaware Riverkeeper . Rather, the application for the later-in-time project had yet to be submitted when the main project was under consideration. Minisink , 762 F.3d at 113 n.11. In Myersville , we reasoned that, unlike Delaware Riverkeeper , the projects were "unrelated" and did not depend on one another for their justification. 783 F.3d at 1326-27.

Because the case before us is more in line with Minisink and Myersville than with Delaware Riverkeeper , we conclude that the Commission did not act arbitrarily and capriciously in declining to consider Algonquin's three projects in a single environmental impact statement. With regard to temporal overlap, the Commission issued the AIM Project certificate in March 2015, Algonquin submitted the application for Atlantic Bridge in October 2015, and Algonquin has yet to file the Access Northeast application. The projects thus were not under simultaneous consideration by the agency.

Nor are the projects "financially and functionally interdependent." Del. Riverkeeper , 753 F.3d at 1319.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Port Isabel v. FERC
111 F.4th 1198 (D.C. Circuit, 2024)
Alabama Municipal Distributors Group v. FERC
100 F.4th 207 (D.C. Circuit, 2024)
Eagle County, Colorado v. STB
82 F.4th 1152 (D.C. Circuit, 2023)
Gtec Industries, Inc. v. McMahon
District of Columbia, 2022
Delaware Riverkeeper Network v. FERC
45 F.4th 104 (D.C. Circuit, 2022)
Sierra Club v. FERC
38 F.4th 220 (D.C. Circuit, 2022)
Food & Water Watch v. FERC
28 F.4th 277 (D.C. Circuit, 2022)
Environmental Health Trust v. FCC
9 F.4th 893 (D.C. Circuit, 2021)
INEOS USA LLC v. FERC
940 F.3d 1326 (D.C. Circuit, 2019)
Krukas v. Aarp
District of Columbia, 2019
Krukas v. AARP, Inc.
376 F. Supp. 3d 1 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
897 F.3d 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-bos-delegation-v-fed-energy-regulatory-commn-cadc-2018.