Washington Gas Light Co. v. Federal Energy Regulatory Commission

532 F.3d 928, 382 U.S. App. D.C. 327, 2008 U.S. App. LEXIS 15292, 2008 WL 2777765
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 18, 2008
Docket07-1015
StatusPublished
Cited by11 cases

This text of 532 F.3d 928 (Washington Gas Light Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Gas Light Co. v. Federal Energy Regulatory Commission, 532 F.3d 928, 382 U.S. App. D.C. 327, 2008 U.S. App. LEXIS 15292, 2008 WL 2777765 (D.C. Cir. 2008).

Opinion

Opinion for the Court filed by Circuit Judge BROWN.

BROWN, Circuit Judge:

The Federal Energy Regulatory Commission (“FERC”) approved a project that will expand the liquefied natural gas (“LNG”) capacity of the Cove Point LNG Terminal (“Cove Point”). Washington Gas Light Company (“WGL”), a local distribution company that receives natural gas from Cove Point, brought a petition for review arguing the expansion project will cause severe leakage throughout its distribution system. We find that substantial evidence supports FERC’s conclusion that any threat of increased leakage is due to defects in WGL’s system, but we grant WGL’s petition because substantial evidence does not support FERC’s conclusion that WGL can address safety concerns before the project’s in-service date.

I

Dominion Cove Point LNG, LP and Dominion Transmission, Inc. (collectively “Dominion”) applied to FERC for authorization to build the Cove Point Expansion Project (“Expansion”). Slated for completion in November 2008, the Expansion will significantly increase Cove Point’s LNG output and cause LNG that has not been blended with traditional natural gas to flow to local distribution companies. 1 WGL ob *930 jected to the Expansion, arguing that the influx of LNG would cause its distribution system in the Mid-Atlantic region to suffer severe leakage. It pointed out that in the two-year period after it began receiving a limited amount of unblended LNG from Cove Point in its Prince George’s County, Maryland (“PG County”) facilities, starting in August 2003, those facilities experienced a sixteen-fold increase in leakage. WGL also submitted a report finding the low heavy-hydrocarbon content of LNG caused the seals inside of the couplings connecting its pipes to leak.

To address WGL’s concerns, FERC permitted the parties to submit written evidence and held a “procedural conference” to hear witness testimony. It then issued several orders approving the Expansion. See Dominion Cove Point LNG, 115 F.E.R.C. ¶ 61,337 (2006) (“Certificate Order”); Dominion Cove Point LNG, LP, 118 F.E.R.C. ¶ 61,007 (2007) (“Rehearing Order ”). These orders found factors such as damaged couplings, colder temperatures, and changes in pressure played a larger role in creating the leaks in PG County than the LNG. Certificate Order at 62,268. Specifically, FERC found LNG “would not have adversely affected WGL’s system if a subset of the compression couplings had not been compromised during the installation process.” Rehearing Order at 61,029. It also concluded the Expansion could proceed consistent with the public interest because “there is time for WGL to complete any remaining corrective measures that are needed on its system so that it can safely accommodate regasified LNG.” Rehearing Order at 61,-023-24. Finally, it rejected WGL’s claim that the procedural conference was inadequate. Id. at 61,024-28. WGL petitions this court for review of the orders approving the Expansion, with intervenor Maryland People’s Counsel 2 filing a brief in support of WGL’s petition, and intervenor Dominion filing a brief in support of FERC’s opposition.

II

Under section 3 of the National Gas Act (“NGA”), FERC “shall” approve any application to import natural gas from abroad “unless, after opportunity for hearing, it finds that the proposed exportation or importation will not be consistent with the public interest.” 15 U.S.C. § 717b(a). Under section 7, FERC “shall” approve construction of facilities for transportation or sale of natural gas if the project “is or will be required by the present or future public convenience and necessity.” Id. § 717f(e). Here, FERC approved different portions of the Expansion under sections 3 and 7. We review FERC’s orders under “the arbitrary and capricious standard and uphold FERC’s factual findings if supported by substantial evidence.” Fla. Mun. Power Agency v. FERC, 315 F.3d 362, 365 (D.C.Cir.2003); 15 U.S.C. § 717r(b). When considering FERC’s evaluation of “scientific data within its technical expertise,” we afford FERC “an extreme degree of deference.” Nat'l Comm. for the New River, Inc. v. FERC, 373 F.3d 1323, 1327 (D.C.Cir.2004).

WGL argues the Expansion will be inconsistent with the public-interest requirements of the NGA because the influx of unblended LNG will cause leakage *931 throughout its system. While WGL disagrees with much of FERC’s analysis, this case boils down to the validity of two of FERC’s ultimate findings: (A) the LNG “would not have adversely affected WGL’s system [in PG County] if a subset of the compression couplings had not been compromised during the installation process”; and (B) “there is time for WGL to complete any remaining corrective measures that are needed on its system so that it can safely accommodate regasified LNG.” Rehearing Order at 61,023-24, 61,029. We conclude substantial evidence supports FERC’s finding that defects in WGL’s system caused the PG County leaks, but does not support its finding that WGL will be able to address safety concerns before the Expansion’s in-service date.

A

FERC found the influx of unblend-ed LNG “would not have adversely affected WGL’s system [in PG County] if a subset of the compression couplings had not been compromised during the installation process.” Id. at 61,029. WGL disputes this conclusion by noting its system functioned properly for decades after it installed the couplings, and the increased leak rates only began after August 2003, when Cove Point started sending LNG to its PG County facilities. In the two-year period that followed, these facilities experienced a sixteen-fold increase in leaks, from 62 repairs per year to 1,041 repairs per year, while the rest of WGL’s system experienced only typical seasonal leakage. WGL also points to a report by the ENVIRON International Corporation, which found the low heavy-hydrocarbon content of LNG caused the seals inside of WGL’s couplings to shrink and thus contributed to leakage.

FERC rejected WGL’s argument and concluded the leaks in PG County occurred because WGL applied hot tar to its couplings during the installation process decades ago. FERC explained the hot tar damaged the seals inside of these couplings to such an extent that any comparatively minor leak-inducing change, like low heavy-hydrocarbon LNG or cold temperatures, could cause leakage. Id. In support, FERC pointed to testimony by the President of Normac, the manufacturer of 25% of WGL’s couplings, explaining the hot tar process exposed the couplings’ seals to temperatures of up to 400 degrees Fahrenheit. FERC also cited a study by Neave &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
532 F.3d 928, 382 U.S. App. D.C. 327, 2008 U.S. App. LEXIS 15292, 2008 WL 2777765, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-gas-light-co-v-federal-energy-regulatory-commission-cadc-2008.