National Committee for the New River, Inc. v. Federal Energy Regulatory Commission

373 F.3d 1323, 362 U.S. App. D.C. 276, 34 Envtl. L. Rep. (Envtl. Law Inst.) 20047, 58 ERC (BNA) 1839, 2004 U.S. App. LEXIS 14189, 2004 WL 1531943
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 9, 2004
Docket03-1111
StatusPublished
Cited by51 cases

This text of 373 F.3d 1323 (National Committee for the New River, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Committee for the New River, Inc. v. Federal Energy Regulatory Commission, 373 F.3d 1323, 362 U.S. App. D.C. 276, 34 Envtl. L. Rep. (Envtl. Law Inst.) 20047, 58 ERC (BNA) 1839, 2004 U.S. App. LEXIS 14189, 2004 WL 1531943 (D.C. Cir. 2004).

Opinion

Opinion for the Court filed by Circuit Judge ROGERS.

ROGERS, Circuit Judge:

At issue in this appeal are two orders of the Federal Energy Regulatory Commission approving the application of the East Tennessee Natural Gas Company (“East Tennessee”) for a certificate of public convenience and necessity to construct a pipeline extension through southwest Virginia and North Carolina known as “the Patriot Project.” The National Committee for the New River, Inc. and others (together “New River”) contend that the Commission’s environmental review of the Patriot Project was deficient in several respects: (1) the draft environmental statement was inadequate and incomplete in its disclosure and analysis of the environmental effect of the project; (2) neither the draft nor the final environmental impact statements adequately identified alternate routes for the pipeline; (3) the location of the underground taps should not have been considered in evaluating alternative routes for *1325 the pipeline, or if considered, their environmental impacts should have been considered; and (4) the draft environmental impact statement was deficient for failing to consider the impacts of two proposed generating plants.

We hold that the record demonstrates, consistent with the evolving nature of a major project, that the Commission’s process for ventilating and analyzing potential environmental impacts of the Patriot Project involved the requisite “hard look,” see Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989), and that any deficiencies in the draft environmental impact statement as may have existed were cured by the final environmental impact statement. Accordingly, because the Commission’s approval of East Tennessee’s application and the conditional issuance of a certificate of public convenience and necessity to East Tennessee was not arbitrary and capricious or an abuse of discretion, we deny the petition.

I.

On July 26, 2001, East Tennessee Natural Gas Company (“East Tennessee”) filed an application for a certificate of public convenience and necessity under § 7(c) of the Natural Gas Act (“NGA”), 15 U.S.C. § 717f(c), to expand an existing natural gas transportation pipeline in Tennessee and southwest Virginia, and to extend a new pipeline from Virginia to North Carolina (“the Patriot Project”). The purpose of the project was to help meet forecasted growth in natural gas consumption in Tennessee, Virginia, and North Carolina, to provide resources to meet the increased demand for natural gas-fired electric generation, and to stimulate industrial development in the region. The project would affect about 2,707 acres of land in three states, with a pipeline right-of-way 100 feét wide. It includes a 94 mile extension of East Tennessee’s mainline transmission facilities from near Wytheville, Virginia to an intersection with facilities of the Transcontinental Gas Pipe Line Corporation in Eden, North Carolina, a seven mile extension to service a power plant in Henry County, Virginia, and associated mainline valves and other facilities, including underground taps.

On March 27, 2002, the Commission, following its policy of evaluating non-environmental aspects of a proposed project before the environmental ones, issued a Preliminary Determination on Non-Environmental Issues, finding that the public benefits of East Tennessee’s proposal outweighed any adverse impacts. 98 FERC ¶ 61,331, 62,392, 2002 WL 471183 (2002). In making this determination, it weighed such factors as the proposal’s market support and economic, operational, and competitive benefits. See Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227, 61,743, 1999 WL 718975 (1999); Order Clarifying Statement of Policy, 90 FERC ¶ 61,128, 61,396, 2000 WL 146839 (2000); Order Further Clarifying Statement of Policy, 92 FERC ¶ 61,-094, 61,373, 2000 WL 1197827 (2000). On the benefits side, the Commission found that the “Patriot Project is in the public interest because it will provide fuel for new eleptric generation plants, provide additional gas supplies to existing local distribution companies (LDCs), and bring natural gas service to portions of southwestern Virginia for the first time.” Preliminary Determination, 98 FERC at 62,392. It also noted that there was ample market demand for the Project, with seven shippers already under contract for 87 percent of the Project’s capacity. On the impacts side, the Commission expected many potential adverse effects “will be resolved or mitigated with appropriate conditions in *1326 [the] final order” and with provisions for compensating property owners for any damage to property or the taking of property necessary for the pipeline right-of-way. Id. at 62,402. The Commission reserved issuance of the certificate pending completion of its environmental review.

The Commission’s process for evaluating the environmental impacts of the project involved six steps: a notice of intent to prepare an impact statement, a draft impact statement, public hearings, staff review and evaluation of comments, a final impact statement, and finally Commission consideration of the final statement. On October 1, 2001, the Commission issued a Notice of Intent to Prepare an Environmental Impact Statement and Request for Comments on Environmental Issues ("NOI”). The NOI described the project and included an overview map as well as a website where further information was available. It advised that public “scoping” meetings would be held to solicit and address public concerns, and that there would be a visit to the proposed route. The NOI was sent to approximately 2,460 individuals, organizations, and interested parties, including federal, state, county, and local agencies, elected officials, and property owners along the proposed route of the extended pipeline. Four public scoping meetings and two public working meetings in various cities along the proposed route were held, and several hundred comments and objections were received.

On April 26, 2002, a draft environmental impact statement (“DEIS”) was issued, assessing the environmental impacts associated with the construction and operation of the pipeline. After the time for comment on the DEIS was extended, five public comment meetings were held in Virginia and Tennessee and one in Washington, D.C. Following evaluation of the comments by Commission staff, a final environmental impact statement (“FEIS”) was issued on September 23, 2002. The Commission determined that the Patriot Project would result in limited adverse environmental impacts, and that mitigation measures detailed in the FEIS would “appropriately and reasonably” reduce and compensate for them.

In the first order on review, the Commission on November 20, 2002, issued East Tennessee a final certificate of authorization, subject to 69 conditions to mitigate environmental impacts. See Order Denying Rehearing, Authorizing Abandonment, and Issuing Certificate (“Initial Order”), 101 FERC ¶ 61,188, 61,743, 2002 WL 31973796 (2002). The Commission rejected New River’s petition for reconsideration of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healthy Gulf v. Haaland
District of Columbia, 2025
City of Port Isabel v. FERC
111 F.4th 1198 (D.C. Circuit, 2024)
Sierra Club v. FERC
97 F.4th 16 (D.C. Circuit, 2024)
Wilderness Society v. Haaland
District of Columbia, 2024
Friends of the Earth v. Haaland
District of Columbia, 2022
Stand Up For California! v. DOI
994 F.3d 616 (D.C. Circuit, 2021)
Sierra Club v. DOI
990 F.3d 898 (Fifth Circuit, 2021)
Gulf Restoration Network v. Zinke
District of Columbia, 2020
Twp. of Bordentown v. Fed. Energy Regulatory Comm'n
903 F.3d 234 (Third Circuit, 2018)
Sierra Club v. State Water Control Board
898 F.3d 383 (Fourth Circuit, 2018)
Sierra Club, Inc. v. U.S. Forest Service
897 F.3d 582 (Fourth Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
373 F.3d 1323, 362 U.S. App. D.C. 276, 34 Envtl. L. Rep. (Envtl. Law Inst.) 20047, 58 ERC (BNA) 1839, 2004 U.S. App. LEXIS 14189, 2004 WL 1531943, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-committee-for-the-new-river-inc-v-federal-energy-regulatory-cadc-2004.