Sierra Club, Inc. v. U.S. Forest Service

897 F.3d 582
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 27, 2018
Docket17-2399; 18-1012; 18-1019; 18-1036
StatusPublished
Cited by25 cases

This text of 897 F.3d 582 (Sierra Club, Inc. v. U.S. Forest Service) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club, Inc. v. U.S. Forest Service, 897 F.3d 582 (4th Cir. 2018).

Opinion

THACKER, Circuit Judge:

In this case, we address petitions seeking review of two federal agency decisions. The first is the Bureau of Land Management ("BLM")'s decision granting a right of way through federal land for construction and operation of a pipeline proposed by Mountain Valley Pipeline, LLC ("MVP"). The second is the United States Forest Service ("Forest Service")'s decision to amend the Jefferson National Forest Land Resource Management Plan to accommodate the right of way and pipeline construction. Sierra Club, Inc.; Appalachian Voices; Wild Virginia, Inc.; the Wilderness Society; Preserve Craig, Inc.; and Save Monroe, Inc. (collectively, "Petitioners") claim that by these decisions, the federal agencies violated the National Environmental Policy Act ("NEPA"), the Mineral Leasing Act ("MLA"), and the National Forest Management Act ("NFMA").

After careful review, we conclude that aspects of the Forest Service's decision fail to comply with NEPA and the NFMA. As more fully explained below, we grant the petition challenging the Forest Service's decision and vacate that decision. We also conclude that the BLM failed to acknowledge its obligations under the MLA, and therefore, we also grant the petition challenging the BLM decision and vacate that decision. We remand to the respective agencies for further proceedings consistent with this opinion.

I.

A.

The Pipeline Project and FERC

MVP plans to construct, operate, and maintain approximately 303.5 miles of new underground, 42-inch diameter pipeline extending from Wetzel County, West Virginia, to Pittsylvania County, Virginia. The trench for the pipeline will be at least 54 inches wide and 5.5 to 9 feet deep. Construction will involve "remov[ing] trees, shrubs, brush, roots, and large rocks" and will initially require a 75-foot to 125-foot right of way for construction purposes, and a subsequent 50-foot right of way for at least 30 years to accommodate the pipeline's operation. J.A. 102-03, 107. 1

On October 13, 2017, the Federal Energy Regulatory Commission ("FERC") issued a Certificate of Public Convenience and Necessity for MVP's pipeline project ("Certificate"). Pursuant to the Natural Gas Act ("NGA"), a natural gas company is not permitted to undertake construction of a pipeline unless FERC first issues a Certificate authorizing such construction. See 15 U.S.C. § 717f(c)(1)(A). Before doing so, in most cases FERC "shall set the matter for hearing and shall give such reasonable notice of the hearing thereon to all interested persons as in its judgment may be necessary under [FERC's] rules and regulations." Id . § 717f(c)(1)(B). FERC also "shall have the power to attach to the issuance of the certificate and to the exercise of the rights granted thereunder such reasonable terms and conditions as the public convenience and necessity may require." Id . § 717f(e). Petitioners do not challenge FERC's issuance of the Certificate in this case.

FERC was also required to issue an Environmental Impact Statement ("EIS"). 2 Pursuant to NEPA, when a federal agency proposes to take a "major Federal action[ ] significantly affecting the quality of the human environment," the agency must prepare a detailed EIS describing the likely environmental effects, "adverse environmental effects which cannot be avoided," and potential alternatives to the proposal. 42 U.S.C. § 4332 (C). Multiple agencies may cooperate to issue an EIS, but a "lead agency" is usually designated. 7 C.F.R. § 3407.11 (a). 3 Where an interstate gas pipeline is involved, FERC acts as the lead NEPA agency. See 15 U.S.C. § 717n(b)(1) ; see also EarthReports, Inc. v. FERC , 828 F.3d 949 , 953 (D.C. Cir. 2016). Here, the BLM and the Forest Service served as cooperating agencies and ultimately adopted the EIS.

B.

The Pipeline Project and the BLM

It is not enough, however, that FERC issued a Certificate and an EIS. Because portions of the proposed pipeline route cross federally owned lands, MVP was also required to obtain rights of way and temporary use permits from the federal government to construct and operate the pipeline on those lands. The proposed right of way will cross land managed by two different agencies-the Forest Service (3.6 miles or approximately 83 acres of the Jefferson National Forest in West Virginia and Virginia) and the Army Corps of Engineers (60 feet of the Weston and Gauley Bridge Turnpike Trail in Braxton County, West Virginia)-which means the Department of the Interior is responsible for issuing rights of way and attendant permits. See 30 U.S.C. § 185 (c)(2) ("Where the surface of the Federal lands involved is administered by ... two or more Federal agencies, the Secretary [of the Interior] is authorized, after consultation with the agencies involved, to grant or renew rights-of-way or permits through the Federal lands involved."). In situations involving oil and gas pipeline rights of way, the Department of the Interior has delegated that authority to the BLM. See 36 C.F.R. § 251.54 (b)(3). Importantly, the BLM must have the concurrence of the Forest Service and the Army Corps of Engineers in order to grant the necessary rights of way or permits. See 30 U.S.C. § 185 (c)(2) ; 43 C.F.R. § 2884.26 . 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
897 F.3d 582, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-inc-v-us-forest-service-ca4-2018.