Friends of Back Bay v. United States Army Corps of Engineers

681 F.3d 581, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20129, 2012 WL 2249259, 74 ERC (BNA) 1961, 2012 U.S. App. LEXIS 12291
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 18, 2012
Docket11-1184
StatusPublished
Cited by49 cases

This text of 681 F.3d 581 (Friends of Back Bay v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friends of Back Bay v. United States Army Corps of Engineers, 681 F.3d 581, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20129, 2012 WL 2249259, 74 ERC (BNA) 1961, 2012 U.S. App. LEXIS 12291 (4th Cir. 2012).

Opinion

Vacated and remanded by published opinion. Judge KING wrote the opinion, in which Judge GREGORY and Judge FLOYD joined.

OPINION

KING, Circuit Judge:

Friends of Back Bay, together with Back Bay Restoration Foundation, Ltd., the plaintiffs below, appeal the district court’s award of summary judgment to defendants United States Army Corps of Engineers (the “Corps”), Secretary of the Army John McHugh, the Commanding *583 General of the Corps, Robert L. Van Antwerp, and Colonel Andrew W. Backus, the District Engineer for the Corps in its Norfolk District. The plaintiffs’ Complaint challenged the Corps’s decision to approve a permit under section 404 of the Clean Water Act (“CWA”), 33 U.S.C. § 1344, and section 10 of the Rivers and Harbors Act of 1899 (“RHA”), 33 U.S.C. § 403, to build a mooring facility and concrete boat ramp about 3,000 feet from the Back Bay National Wildlife Refuge (the “Refuge”) in Virginia Beach, Virginia. As set forth below, we vacate the district court’s judgment and remand.

I.

A.

Proposed by developer Kenneth Douglas Wilkins, the permitted project (the “Project” or the “Wilkins Project”) in a man-made cove off North and Shipps Bays, tributaries to Back Bay, would expand to 76 from 12 the number of existing slips at the same site, the additional 64 being dedicated for watercraft use primarily by residents of nearby condominiums. The approved permit directly authorizes channel dredging, as well as the excavation and relocation within the Project area of silt and other material. See 33 U.S.C. § 1344(a) (empowering Secretary of the Army to “issue permits ... for the discharge of dredged or fill material into the navigable waters [of the United States]”). In addition, the permit provides for the construction of bulkheads, piers, mooring piles, and a walkway in conjunction with the slips and ramp. See 33 U.S.C. § 403 (requiring approval of Secretary for, inter alia, “creation of any obstruction not affirmatively authorized by Congress[ ] to the navigable capacity of any of the waters of the United. States”).

In mitigation of vegetated wetlands cleared to make way for the facility, the permit specifies the creation of equivalent wetlands nearby, and it requires the relocation-there of the plants being displaced by the new construction. The permit also attaches a number of operational conditions to the completed Project, including horsepower limitations on boat motors, restrictions on who may use the facility, and the installation of signs informing the public of the establishment of a no-wake zone (the “NWZ”) for watercraft within the Refuge. See J.A. 232-33. 1

Prior to issuing the permit, the Corps solicited public comment on the underlying application; it received over 350 responses, “the overwhelming majority of which were in opposition to the project.” J.A. 194. The mayor of Virginia Beach recounted that various state and federal government agencies had “expended countless millions of dollars to conserve Back Bay,” and she expressed concern that “detrimental environmental impacts” would result from “greatly increase[d] access for jet skis and powerboats” to the ecologically sensitive area. J.A. 152-53.

In considerably more detail, the Gloucester, Virginia, field office of the United States Fish and Wildlife Service (the “FWS”) documented the historical efforts to preserve and restore submerged aquatic vegetation (“SAV”) in the area. The FWS surmised that “well documented” adverse effects of motorized watercraft, such as “sediment resuspension, water pollution, shoreline erosion, destruction of SAV and other wetlands, and disturbance to fish and wildlife,” would increase if the Wilkins Project were fully realized, and predicted *584 that “because Back Bay is a shallow water system, these effects are likely to be amplified.” Id. at 159. 2 The Regional Director of the FWS followed up with a separate comment, in which he maintained that the § 404 discharges occasioned by the Project “will have a substantial and unacceptable impact on aquatic resources of national importance,” and that, consequently, “the subject permit must be modified, conditioned, or denied.” Id. at 166.

Similar sentiments were echoed by the Virginia Department of Game and Inland Fisheries (warning that “restoration efforts will face even more challenges in this unique system and may ultimately be rendered unsuccessful”), J.A. 168, and the federal Environmental Protection Agency (professing its belief that “the proposed project is contradictory to the environmental goals of several federal, state, [and] local resource agencies and the public interests,” and thus “strongly recommends that the Corps deny the applicant’s request for permits”), id. at 165. The FWS likewise supported “denial of this project as proposed,” id. at 161, but suggested that if the Corps were inclined to proceed, it should prepare an Environmental Impact Statement (“EIS”) to address “impacts to Federal trust resources ... due to project construction and operation, habitat loss, and disruption/elimination of migratory pathways and feeding and resting areas.” Id. at 160-61.

An EIS is “a detailed statement” that ascertains, among other things, the effect of the proposed action on the environment, including “any adverse environmental effects which cannot be avoided should the proposal be implemented,” and evaluates alternatives. 42 U.S.C. § 4332(2)(C). As an integral underpinning of the National Environmental Protection Act (“NEPA”), an EIS must be devised in connection with “every recommendation or report on proposals for ... major Federal actions significantly affecting the quality of the human environment.” Id.; see State ex rel. Campbell v. O’Leary, 64 F.3d 892, 896 (4th Cir.1995). To determine whether a particular action meets the threshold of “significantly affecting” environmental quality, federal agencies are required to draft an Environmental Assessment (“EA”), which is “a concise public document” designed to “provide sufficient evidence and analysis for determining whether to prepare an [EIS] or a finding of no significant impact [‘FONSI’].” 40 C.F.R. § 1508.9(a)(1); see Campbell, 64 F.3d at 896.

In its March 1, 2005 Public Notice of the permit application, the Corps announced its preliminary determination “that ... no [EIS] will be required.” J.A. 150.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
681 F.3d 581, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20129, 2012 WL 2249259, 74 ERC (BNA) 1961, 2012 U.S. App. LEXIS 12291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-back-bay-v-united-states-army-corps-of-engineers-ca4-2012.