Ohio Valley Environmental Coalition v. Aracoma Coal Co.

556 F.3d 177, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20035, 68 ERC (BNA) 1343, 2009 U.S. App. LEXIS 2904, 2009 WL 350899
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 13, 2009
Docket07-1355, 07-1479, 07-1480, 07-1964, 07-2112
StatusPublished
Cited by381 cases

This text of 556 F.3d 177 (Ohio Valley Environmental Coalition v. Aracoma Coal Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Valley Environmental Coalition v. Aracoma Coal Co., 556 F.3d 177, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20035, 68 ERC (BNA) 1343, 2009 U.S. App. LEXIS 2904, 2009 WL 350899 (4th Cir. 2009).

Opinions

Reversed, vacated and remanded by published opinion. Judge GREGORY wrote the opinion, in which Judge SHEDD joined. Judge MICHAEL wrote a separate opinion dissenting in part and concurring in part.

GREGORY, Circuit Judge:

OPINION

This appeal concerns a challenge by Plaintiffs-Appellees Ohio Valley Environmental Coalition, the Coal River Mountain Watch, and the West Virginia Highlands Conservancy (hereinafter referred to collectively as “OVEC”) to the U.S. Army Corps of Engineers (“Corps”) issuance of [186]*186four permits allowing the filling of West Virginia stream waters in conjunction with area surface coal mining operations. Granting judgment for OVEC, the district court rescinded the permits as violations of the Clean Water Act (“CWA”), 33 U.S.C. § 1251 et seq. (2000), the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq. (2000), and the Administrative Procedure Act (“APA”), 5 U.S.C. § 701 et seq. (2000). The court also enjoined all activity under those permits and remanded to the Corps for further proceedings consistent with its order.

Separately, in an order dated June 13, 2007, the district court provided declaratory relief to OVEC, holding that the stream segments linking the permitted fills to downstream sediment treatment ponds were “waters of the United States” and that the Corps lacked authority under the CWA to permit discharge from the fills into the stream segments.

The Corps now appeals these two orders. For the reasons set forth below, we reverse and vacate the district court’s opinion and order of March 23, 2007, and vacate the district court’s injunction. We also reverse the district court’s June 13, 2007, grant of declaratory relief and we remand for further proceedings consistent with this opinion.

I.

The mountaintop removal method of surface coal mining, pioneered in West Virginia, involves the blasting of the soil and rock atop a mountain to expose coal deposits below. While mining operations are ongoing, the overburden is hauled or pushed into adjacent valleys. This excavated overburden is known as “spoil.” Once the coal has been extracted, efforts are made to re-contour the mountaintop by replacing the removed overburden, but stability concerns limit the amount of spoil that can be returned to the area. In its natural state, the spoil material is heavily compacted; once excavated, however, the loosening of the rock and soil and incorporation of air causes significant swelling. As a result, large quantities of the blasted material cannot be replaced, and this excess spoil (“overburden”) remains in the valley, creating a “valley fill” that buries intermittent and perennial streams in the process.

Water that collects in the fill must be moved out to ensure the fill’s continued stability. Thus, an underdrain system is constructed by placing large boulders up to and above the ordinary high-water mark of the stream. The collected water is then channeled into a treatment pond, where sediment from the runoff is allowed to settle. Sediment ponds usually are constructed in existing streambeds, using earth and rock to create an embankment. After sediments have settled out of the fill runoff, the treated water is discharged from the sediment pond back into existing streams. When practicable, a sediment pond will be constructed in the streambed immediately adjacent to the end (or “toe”) of the fill. But, because West Virginia’s steep, mountainous topography often prevents this kind of positioning, a short stream segment is frequently used to move runoff from the fill downstream to the sediment pond. Once a valley fill is stabilized, the embankments of the sediment pond are removed, and the ponds and the stream segments are restored to their pre-project condition.

Much of the impact of a valley fill project is felt by headwater streams. Head-water streams are small streams that form the origin of larger streams or rivers, and may be intermittent or ephemeral. Intermittent streams receive their flow from both surface runoff and groundwater discharge, while ephemeral streams rely on [187]*187major rain or snow events for their flow. The precise role of headwater streams in overall watershed ecology is a matter of some debate in this litigation, as we discuss more below, but all parties agree that these streams perform important ecological functions.

OVEC initiated this challenge in September 2005 in the United States District Court for the Southern District of West Virginia, shortly after the Corps issued an individual valley fill permit and accompanying Combined Decision Document (“CDD”) to the Araeoma Coal Company for the Camp Branch Surface Mine project (“Camp Branch”) under its CWA § 404 authority.1 As the Corps issued subsequent § 404 permits to West Virginia mining operations, the district court allowed OVEC to amend its complaint several times to include the newly issued permits.

In addition to the Camp Branch permit, OVEC’s Third Supplemental Complaint raised challenges to the individual § 404 permits issued to the Elk Run Coal Company for the Black Castle Mine (“Black Castle”), and to Alex Energy, Inc., for the Republic No. 1 and Republic No. 2 Surface Mines (“Republic No. 1” and “Republic No. 2”). The Republic No. 1 challenge was ultimately dismissed on ripeness grounds, but a challenge raised in a separate complaint to the individual permit issued to Independence Coal Company for the Laxare East Surface Mine (“Laxare East”) was consolidated with this proceeding. Each of the affected companies intervened as defendants in the action, as did the West Virginia Coal Association.

All together, the four challenged permits authorize the creation of 23 valley fills and 23 sediment ponds, and they impact 68,841 linear feet of intermittent and ephemeral streams, or just over 13 miles.2 For each of the four permits, the Corps prepared Environmental Assessments that concluded that the permitted activity would not result in significant environmental impacts given planned mitigation measures. On that basis, the Corps issued a “Finding of No Significant Impact” for all four permits.

OVEC’s Third Supplemental Complaint charged that the Corps’ issuance of the § 404 fill permits for these mining projects violated both substantive and procedural provisions of the CWA and NEPA, and were “arbitrary, capricious, and an abuse of discretion” under the APA. According to OVEC, the Corps was required under [188]*188NEPA to prepare an Environmental Impact Statement for each of the projects before issuing a permit, given the significant individual and cumulative adverse effects the projects would have on water quality, aquatic and terrestrial ecosystems and habitats, species survival and diversity, crucial stream functions, forests, and the aesthetic value of the destroyed mountains. Similarly, OVEC claimed that the Corps failed to properly determine the adverse individual and cumulative impacts to the affected aquatic ecosystems in accordance with the CWA and the Corps’ CWA Guidelines.

Trial in the case was originally scheduled for June 20, 2006, but on June 16, on the Corps’ motion, the district court remanded the permits to the Corps and stayed the proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
556 F.3d 177, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20035, 68 ERC (BNA) 1343, 2009 U.S. App. LEXIS 2904, 2009 WL 350899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-valley-environmental-coalition-v-aracoma-coal-co-ca4-2009.