Sierra Club v. US Dept of the Army Corps of Engineers

997 F.3d 395
Court of Appeals for the First Circuit·Decided May 13, 2021·No. 20-2195P·Published·Cited by 5 cases

Opinion

United States Court of Appeals For the First Circuit

No. 20-2195

SIERRA CLUB; NATURAL RESOURCES COUNCIL OF MAINE; APPALACHIAN MOUNTAIN CLUB,

Plaintiffs, Appellants,

v.

UNITED STATES ARMY CORPS OF ENGINEERS; COLONEL JOHN A. ATILANO, II, Commander and District Engineer, in his official capacity;

JAY L. CLEMENT, Senior Project Manager, in his official capacity; CENTRAL MAINE POWER COMPANY,

Defendants, Appellees.

APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MAINE

[Hon. Lance E. Walker, U.S. District Judge]

Before

Lynch, Thompson, and Barron, Circuit Judges.

Kevin Cassidy, with whom Earthrise Law Center was on brief, for appellants.

Jeffrey A. Hall, with whom Jean E. Williams, Acting Assistant Attorney General, Jennifer S. Neumann, and Amelia G. Yowell were on brief, for appellees United States Army Corps of Engineers, John A. Atilano II, and Jay L. Clement.

Joshua D. Dunlap, with whom Matthew D. Manahan, Lisa Gilbreath, and Pierce Atwood LLP were on brief, for appellee Central Maine Power Company.

Kevin Poloncarz, Donald L. Ristow, Lindsay Brewer, and Covington & Burling LLP on brief for amici curiae Calpine Corporation, Nextera Energy Resources, LLC, and Vista Corp.

Shaun A. Goho and the Emmett Environmental Law & Policy Clinic on brief for amici curiae Environmental Law Clinic Directors.

Anthony W. Buxton, Jonathan G. Mermin, and Preti Flaherty on brief for amicus curiae Industrial Energy Consumer Group.

P. Andrew Hamilton, Timothy C. Woodcock, and Eaton Peadbody, P.A. on brief for amicus curiae H.Q. Energy Services (U.S.) Inc.

May 13, 2021

LYNCH, Circuit Judge. Plaintiff environmental organizations appeal from the district court's denial of preliminary injunctive relief barring construction of Segment 1 of a planned five-segment electric transmission power corridor in Maine. This was part of a larger project which would run from Quebec, Canada to Massachusetts. See Sierra Club v. U.S. Army Corps of Eng'rs, No. 2:20-CV-00396-LEW, 2020 WL 7389744, at *1 (D. Me. Dec. 16, 2020) ("CMP Decision").

The corridor would be built by Central Maine Power ("CMP"), a private company. Plaintiffs' challenge is to the Army Corps of Engineers' ("Corps") decision, after its performance of an Environmental Assessment ("EA"), to issue a permit authorizing CMP to take three actions in Segment 1: (1) temporarily fill certain wetlands, (2) permanently fill other wetlands, and (3) construct a tunnel under the Kennebec River. They allege that the Corps was required to issue not merely an EA, but a full Environmental Impact Statement ("EIS") and that the Corps acted arbitrarily or capriciously in conducting its EA and issuing a Finding of No Significant Impact ("FONSI"). They raise other secondary challenges to the Corps' EA and FONSI. We conclude that that plaintiffs have failed to show a likelihood of success on the merits. We affirm the district court's denial of a preliminary

injunction.1 We also vacate the injunction issued by this court on January 15, 2021 to allow us to consider this expedited appeal.

I. Background

A. State Agency Review of the CMP Corridor.

The parameters for the project were originally set by Massachusetts. Massachusetts selected the CMP proposal from fifty-three proposed clean energy projects in a competitive bidding process.2 State regulators and private utilities were responsible for that selection. No federal agency was involved. Massachusetts approved only the specific route outlined in CMP's proposal. "The [Massachusetts] process essentially predetermined CMP's role as applicant and limited the alternatives analysis to only those which are available and capable of being done by CMP."

1 To earn a preliminary injunction, parties must demonstrate four factors: (1) the likelihood of success on the merits; (2) the likelihood of irreparable harm absent an injunction; (3) a balancing of hardships; and (4) the public interest. Respect Maine PAC v. McKee, 622 F.3d 13, 15 (1st Cir. 2010) (citing Nken v. Holder, 556 U.S. 418, 433 (2009)). Sierra Club urges us to place less emphasis on the first prong, even though our case law has emphasized that prong's primacy in the preliminary injunction assessment. See Ryan v. ICE, 974 F.3d 9, 18 (1st Cir. 2020) ("The movant's likelihood of success on the merits weighs most heavily in the preliminary injunction calculus."). Regardless, Sierra Club would not prevail even if we adopted their view of the test. We therefore need not decide the issue.

2 Massachusetts originally selected the Northern Pass Transmission project, which would have travelled through New Hampshire. New Hampshire regulators did not approve the Northern Pass project. After that rejection, Massachusetts selected the CMP proposal through Maine.

Maine also approved the project after much more extensive review than the Corps engaged in in its EA. After CMP won the contract to construct the corridor, the Maine Department of Environmental Protection ("MDEP") accepted written and oral testimony about the project, and after a hearing approved construction. MDEP concluded that the CMP Corridor in its entirety had minimal environmental impacts, provided that CMP took mitigation measures, which it has agreed to undertake. The approved route consists of five segments, four of which track existing transmission lines. MDEP reviewed all 8,600 acres of the project, and issued a 113-page order approving the plan subject to various additional conditions, which CMP adopted. The MDEP assessed the project impact on: (1) wildlife, (2) forest and habitat fragmentation, (3) depletion of natural resources, (4) disruption during construction, (5) the visual aesthetics of the region, and (6) the feasibility of alternatives. It concluded that subject to mitigation measures to limit the visual and environmental impacts of the project, the CMP corridor did not impose unreasonable environmental risks. The Corps reviewed the project as modified by the State of Maine.

The Maine Public Utilities Commission also approved the project after holding public hearings and accepting public comment. The Maine Law Court later upheld that approval. NextEra Energy Res., LLC v. Me. Pub. Utils. Comm'n, 227 A.3d 1117, 1119

(Me. 2020). The Maine Bureau of Parks and Lands also leased to CMP a right of way over state land.

B. Federal Agency Review of the CMP Corridor.

The Corps became involved in the CMP project because construction in Segment 1 will require (1) temporary filling of wetlands; (2) permanent filling of wetlands; and (3) construction of a tunnel under the Kennebec River.3 Each of these activities requires permit approval from the Corps under either the Clean Water Act (for temporary and permanent fills) or the River and Harbors Act (for tunneling under the Kennebec River). 33 U.S.C. §§ 403, 1341, 1344(a).

Federal law requires the Corps to consider the environmental impact of permitting these activities. The National Environmental Protection Act ("NEPA") is a procedural statute. 42 U.S.C. § 4332(C). It sets out environmental policy objectives which are largely implemented through regulations promulgated by the Council on Environmental Quality ("CEQ") and individual agencies. See Sierra Club v. U.S. Army Corps of Eng'rs, 803 F.3d 31, 37 (D.C. Cir. 2015) ("Flanagan South").

Two categories of CEQ and Corps regulations are relevant to this litigation. The first concerns the appropriate scope of

3 At MDEP's request, the Corps also advised MDEP that a "zig zag" route through CMP's 300-foot-wide right of way would not significantly mitigate impacts to wetlands, and could cause other environmental consequences.

Free access — add to your briefcase to read the full text and ask questions with AI

Sierra Club v. US Dept of the Army Corps of Engineers, 997 F.3d 395 (1st Cir. 2021).

997 F.3d 395 (Sierra Club v. US Dept of the Army Corps of Engineers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stensvad v. Newman Ayers Ranch
2024 MT 246 (Montana Supreme Court, 2024)
NECEC Transmission LLC v. Bureau of Parks and Lands
2022 ME 48 (Supreme Judicial Court of Maine, 2022)