NECEC Transmission LLC v. Bureau of Parks and Lands

2022 ME 48, 281 A.3d 618
CourtSupreme Judicial Court of Maine
DecidedAugust 30, 2022
StatusPublished
Cited by20 cases

This text of 2022 ME 48 (NECEC Transmission LLC v. Bureau of Parks and Lands) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NECEC Transmission LLC v. Bureau of Parks and Lands, 2022 ME 48, 281 A.3d 618 (Me. 2022).

Opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions Decision: 2022 ME 48 Docket: BCD-21-416 Argued: May 10, 2022 Decided: August 30, 2022

Panel: STANFILL, C.J., JABAR and HORTON, JJ., CLIFFORD, A.R.J., and HUMPHREY, A.R.J.*

NECEC TRANSMISSION LLC et al.

v.

BUREAU OF PARKS AND LANDS et al.

STANFILL, C.J.

[¶1] The New England Clean Energy Connect project (the Project) is

designed to transmit power generated in Québec through Maine and into

Massachusetts. The Project includes a new 145.3-mile, high-voltage direct

current (HVDC) transmission line, proposed to run from the Maine-Québec

border in Beattie Township to a new converter station in Lewiston and from

there to an existing substation by a new 1.2-mile, high-voltage alternating

current transmission line. Of the Project’s five segments, segment 1—a

53.1 mile-long HVDC transmission line running along a corridor from

Beattie Township to the Forks Plantation—is the most controversial because it

* Justice Humphrey sat at oral argument and participated in the initial conference while he was an Associate Justice and, as directed and assigned by the Chief Justice, is now participating in this appeal as an Active Retired Justice. 2

must be cut through commercial timberland and will cross hundreds of

wetlands, waterways, and other wildlife habitats, as well as public land.

[¶2] On November 2, 2021, fifty-nine percent of Maine voters approved

the following ballot question through a public referendum:

Do you want to ban the construction of high-impact electric transmission lines in the Upper Kennebec Region and to require the Legislature to approve all other such projects anywhere in Maine, both retroactively to 2020, and to require the Legislature, retroactively to 2014, to approve by a two-thirds vote such projects using public land?[1]

Though the question did not mention the Project, the legislation enacted by the

voters (the Initiative) effectively precludes the Project.2

[¶3] On November 3, 2021, NECEC Transmission LLC and Avangrid

Networks, Inc. (collectively, NECEC),3 filed a complaint for declaratory

1 Section 4 of the Initiative requires legislative approval of the construction of any high-impact

transmission line in addition to a CPCN from the PUC. I.B. 2021, ch. 1, § 4 (effective Dec. 19, 2021). Section 5 of the Initiative bans the construction of any high-impact transmission line in the “Upper Kennebec Region,” defined as “the approximately 43,300 acres of land located between the Town of Bingham and Wyman Lake, north along the Old Canada Road, Route 201, to the Canadian border, and eastward from the Town of Jackman to encompass Long Pond and westward to the Canadian border, in Somerset County and Franklin County.” I.B. 2021, ch. 1, § 5 (effective Dec. 19, 2021). Section 6 requires sections 4 and 5 to be applied retroactively to September 16, 2020. I.B. 2021, ch. 1, § 6 (effective Dec. 19, 2021).

2Consistent with the terminology used by the trial court and the parties, we use “the Initiative” throughout this opinion to refer to the legislation enacted by the passage of the citizens’ initiative question in November 2021. See I.B. 2021, ch. 1, §§ 1-6 (effective Dec. 19, 2021). The Initiative was the second attempt at a citizens’ initiative to curtail the Project; we held the first proposed initiative unconstitutional in Avangrid Networks, Inc. v. Sec’y of State, 2020 ME 109, ¶¶ 35-38, 237 A.3d 882.

3NECEC Transmission LLC owns the Project; Avangrid owns NECEC Transmission LLC and is the indirect parent company of Central Maine Power Company (CMP). CMP, together with H.Q. Energy 3

judgment in the Superior Court alleging, among other things, that retroactive

application of the Initiative to the Project, as required by section 6, is

unconstitutional on a variety of grounds. The complaint named the Bureau of

Parks and Lands, the Public Utilities Commission (PUC), the Maine Senate, and

the Maine House of Representatives as defendants (collectively, the State

parties). Thirteen organizations and individuals were granted intervenor

status in the trial court.4

[¶4] NECEC moved to preliminarily enjoin the Initiative from becoming

law. After transfer to the Business and Consumer Docket, and following the

denial of NECEC’s request for a preliminary injunction, the trial court (Duddy, J.)

reported the case to us pursuant to M.R. App. P. 24(c). We accept the report and

frame the question of law raised by the court’s reported interlocutory ruling as

follows:

Services (U.S.) Inc., originally entered into transmission services agreements with several Massachusetts electricity distribution companies to transmit electricity through the Project. CMP ultimately transferred all of its rights and responsibilities in the Project to NECEC Transmission LLC.

4 The following parties intervened on the side of NECEC: H.Q. Energy Services (U.S.) Inc., Cianbro Corporation, International Brotherhood of Electrical Workers Local 104, Industrial Energy Consumer Group, and the Maine State Chamber of Commerce. The following parties intervened on the side of the State appellees: NextEra Energy Resources, LLC (NextEra); the Natural Resources Council of Maine (NRCM); and individuals Thomas B. Saviello, Christine M. Geisser, Wendy A. Huish, Jonathan T. Hall, Theresa E. York, and Robert C. Yorks (the West Forks residents). 4

Would retroactively applying sections 4 and 5 of the Initiative to the certificate of public convenience and necessity (CPCN) issued for the Project, as required by section 6, violate due process under the Maine Constitution, Me. Const. art. I, § 6-A, if NECEC undertook substantial construction consistent with and in good-faith reliance on the CPCN before the Initiative was enacted?

Answering that question, we hold that section 6 of the Initiative is

unconstitutional to the extent it requires sections 4 and 5 to be applied

retroactively to the CPCN if the appellants have acquired vested rights to

proceed with Project construction. We therefore remand to the Business and

Consumer Docket for further proceedings consistent with this opinion.

I. BACKGROUND

[¶5] The interlocutory ruling underlying this case is before us pursuant

to M.R. App. P. 24(c), on report from the Business and Consumer Docket. Given

that procedural posture, the following facts are taken from the reported ruling

and our opinion affirming the PUC’s order granting the CPCN for the Project,

NextEra Energy Res., LLC v. Me. PUC, 2020 ME 34, 227 A.3d 1117, and are limited

to those facts relevant to the question of law that we now answer.

See Littlebrook Airpark Condo. Ass’n v. Sweet Peas, LLC, 2013 ME 89, ¶ 9, 81 A.3d

348 (outlining the limited scope of review for reported interlocutory rulings). 5

A. Project Permitting and Other Governmental Approvals

[¶6] On September 27, 2017, CMP filed a petition with the PUC to obtain

a CPCN for the Project. NextEra Energy Res., LLC, 2020 ME 34, ¶ 3, 227 A.3d

1117. The PUC held many days of public and evidentiary hearings and

conferences and received well over one thousand public comments regarding

CMP’s petition. Id. ¶ 6. On May 3, 2019, the PUC concluded that the Project

meets the statutory public-need standard and unanimously voted to grant CMP

a CPCN to construct and operate the Project, all at no cost to Maine electricity

customers. Id. ¶¶ 6-10.

[¶7] Appellee-Intervenor NextEra intervened in the PUC proceeding and

appealed to us from the order granting the CPCN. Id. ¶¶ 5, 11. We affirmed the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2022 ME 48, 281 A.3d 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/necec-transmission-llc-v-bureau-of-parks-and-lands-me-2022.