NextEra Energy Resources, LLC v. Maine Public Utilities Commission

2020 ME 34, 227 A.3d 1117
CourtSupreme Judicial Court of Maine
DecidedMarch 17, 2020
StatusPublished
Cited by18 cases

This text of 2020 ME 34 (NextEra Energy Resources, LLC v. Maine Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NextEra Energy Resources, LLC v. Maine Public Utilities Commission, 2020 ME 34, 227 A.3d 1117 (Me. 2020).

Opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions Decision: 2020 ME 34 Docket: PUC-19-182 Argued: December 6, 2019 Decided: March 17, 2020

Panel: SAUFLEY, C.J., and GORMAN, JABAR, HUMPHREY, and HJELM, JJ.*

NEXTERA ENERGY RESOURCES, LLC

v.

MAINE PUBLIC UTILITIES COMMISSION et al.

JABAR, J.

[¶1] NextEra Energy Resources, LLC, appeals from an order of the Maine

Public Utilities Commission granting Central Maine Power Company’s (CMP)

petition for a certificate of public convenience and necessity (CPCN) for the

construction and operation of the New England Clean Energy Connect (NECEC)

project. The NECEC project is a 145.3-mile transmission line, proposed to run

from the Maine-Qué bec border in Beattie Township to Lewiston, that will

deliver 1,200 megawatts of electricity from Qué bec to the New England Control

* Justice Hjelm sat at oral argument and participated in the initial conference while he was a Justice, and, on order of the Chief Justice, was authorized to continue his participation in his capacity as an Active Retired Justice.

Justice Mead sat at oral argument and participated in the Court’s initial conference regarding this opinion immediately following the oral argument but did not participate further in the development of the opinion. 2

Area. We discern no error in the Commission’s determination that the NECEC

project meets the applicable statutory standards for a CPCN or in its decision to

approve the stipulation. We affirm the decision of the Maine Public Utilities

Commission.

I. BACKGROUND

[¶2] Pursuant to an enactment of the Massachusetts Legislature in 2008,

every distribution company within Massachusetts was required to solicit and

enter into cost-effective long-term contracts for clean-energy generation. In

response to the Massachusetts electric distribution companies’ and

Massachusetts Department of Energy Resources’ request for proposals seeking

bids for clean energy, CMP and Hydro Renewable Energy Inc., a U.S. affiliate of

Hydro-Qué bec,1 submitted a joint bid for the NECEC project.

[¶3] On September 27, 2017, in anticipation of Massachusetts’s

January 25, 2018, deadline to select the winning bid, CMP filed a petition with

the Commission for a CPCN for the NECEC project. See 35-A M.R.S. § 3132

(2018); 65-407 C.M.R. ch. 330 (2012). The petition described the NECEC

project as “a high voltage direct current (HVDC) transmission solution capable

1 Hydro-Qué bec subsequently transferred its interest in the project to H.Q. Energy Services (U.S.) Inc. (HQUS), one of its existing U.S. affiliates. As Hydro Renewable Energy Inc.’s successor, HQUS serves as the counterparty for contractual arrangements underlying the NECEC project. 3

of delivering 1,200 [megawatts] of electricity from Qué bec to the New England

Control Area.” CMP asserted in its petition that the NECEC would “be

developed, constructed and operated by CMP in Maine at no cost to Maine

electricity customers.”

[¶4] Upon receiving the petition, the Commission’s hearing examiners2

issued a “Notice of Proceeding” to provide all interested persons with the

opportunity to file petitions for intervention by October 13, 2017. The

examiners granted seven timely-filed petitions to intervene, including those

filed by the appellees in this matter, the Office of the Public Advocate and the

Industrial Energy Consumer Group.3

[¶5] In February 2018, after the Commission proceeding was a few

months underway, CMP was notified that the NECEC project had been selected

as the winning bid.4 Shortly thereafter, the Commission received many

2 Hearing examiners are Commission staff assigned to oversee a case. Two examiners were assigned to this proceeding. 3 The Conservation Law Foundation, Dorothy Kelly, the Maine Renewable Energy Association, the

Natural Resources Council of Maine, and Western Mountains and Rivers Corporation also timely filed petitions to intervene. 4 The NECEC was originally selected as the alternate winning bid, but became the winning bid after a necessary siting permit for the original winning bid, an all-hydroelectric bid, was denied in New Hampshire. 4

late-filed petitions to intervene.5 NextEra filed its petition to intervene in

March 2018, asserting that it may be substantially and directly affected by the

proceeding because it indirectly owns three existing energy stations in Maine,

as well as a number of wind, solar, and storage projects under development in

the state. Notwithstanding NextEra’s late filing, the examiners agreed that

NextEra would be substantially and directly affected by the outcome of the

proceeding and therefore granted NextEra discretionary intervenor status.

[¶6] The volume of data requests and testimony filed by over twenty

intervenors was substantial, leading the examiners to schedule additional

conferences and rebuttal phases to the proceeding. Technical conferences

continued through the summer of 2018 into the fall. CMP and NextEra both

presented expert testimony. Throughout the course of the proceeding, the

Commission held three public witness hearings and received over 1,350 public

comments.6

5In addition to NextEra, the following parties submitted late-filed petitions to intervene: the Governor’s Energy Office; RENEW Northeast, Inc.; Calpine Corporation, Vistra Energy Corporation, and Bucksport Generation, LLC (collectively, the generator intervenors); the Acadia Center; Friends of Maine Mountains; ReEnergy Biomass Operations LLC; International Brotherhood of Electrical Workers Local Union 104; City of Lewiston; Town of Caratunk; Maine Chamber of Commerce; Town of Farmington; Greater Franklin Development Council; Trout Unlimited; Former Senator Thomas Saviello; Darryl Wood; Town of Alna; Town of Wilton; Town of New Sharon; Old Canada Road National Scenic Byway, Inc.; Town of Jackman; and Terry Brann. All petitions were granted on either a mandatory or discretionary basis.

Public witness hearings were held in Farmington and the Forks Plantation in September 2018. 6

An additional public witness hearing was held in the Commission’s Hallowell hearing room in 5

[¶7] Six evidentiary hearings were held in October 2018 and

January 2019,7 following which the parties briefed specific questions posed by

the examiners.

[¶8] As the proceeding progressed, a number of the parties—including

CMP—engaged in negotiations and ultimately reached a stipulation.8 See

65-407 C.M.R. ch. 110, § 8(D) (2012). The stipulation was joined by eleven

parties, including CMP, the Office of the Public Advocate, and the Industrial

Energy Consumer Group. See infra ¶ 39. The thirty-eight-page stipulation

required the project to provide myriad benefits to ratepayers and the State as

conditions to the recommended Commission approval of the stipulated

findings and issuance of the CPCN.9 The stipulating parties agreed that a “public

October 2018. The majority of the public comments the Commission received were in opposition to the NECEC project—largely raising environmental, scenic, and tourism-related concerns. 7 On October 21, 2018, NextEra filed a motion to suspend the hearings due to CMP’s failure to produce documents as ordered. The examiners granted NextEra’s motion on October 26, thereby canceling the next three scheduled hearings. 8 In accordance with the Commission’s rules, “[t]he Commission may dispose of all or part of any

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellsworth ME Solar, LLC v. Public Utilities Comission
2026 ME 10 (Supreme Judicial Court of Maine, 2026)
Snakeroot Solar, LLC v. Public Utilities Commission
2025 ME 64 (Supreme Judicial Court of Maine, 2025)
Eastern Maine Conservation Initiative v. Board of Environmental Protection
2025 ME 35 (Supreme Judicial Court of Maine, 2025)
Industrial Energy Consumer Group v. Public Utilities Commission
2024 ME 60 (Supreme Judicial Court of Maine, 2024)
Office of the Public Advocate v. Public Utilities Commission
2024 ME 11 (Supreme Judicial Court of Maine, 2024)
NECEC Transmission LLC v. Bureau of Parks and Lands
2022 ME 48 (Supreme Judicial Court of Maine, 2022)
Maquoit Bay LLC v. Department of Marine Resources
2022 ME 19 (Supreme Judicial Court of Maine, 2022)
Avangrid Networks, Inc. v. Secretary of State
2020 ME 109 (Supreme Judicial Court of Maine, 2020)
Caiazzo v. Bellows
Maine Superior, 2020
Delbert A. Reed v. Secretary of State
2020 ME 57 (Supreme Judicial Court of Maine, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2020 ME 34, 227 A.3d 1117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nextera-energy-resources-llc-v-maine-public-utilities-commission-me-2020.