Snakeroot Solar, LLC v. Public Utilities Commission

2025 ME 64
CourtSupreme Judicial Court of Maine
DecidedJuly 15, 2025
DocketPUC-24-322
StatusPublished

This text of 2025 ME 64 (Snakeroot Solar, LLC v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snakeroot Solar, LLC v. Public Utilities Commission, 2025 ME 64 (Me. 2025).

Opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions Decision: 2025 ME 64 Docket: PUC-24-322 Argued: March 5, 2025 Decided: July 15, 2025

Panel: STANFILL, C.J., and MEAD, HORTON, LAWRENCE, and DOUGLAS, JJ.

SNAKEROOT SOLAR, LLC

v.

PUBLIC UTILITIES COMMISSION

DOUGLAS, J.

[¶1] Snakeroot Solar, LLC, appeals from an order of the Public Utilities

Commission denying its petition for a good-cause exemption under 35-A M.R.S.

§ 3209-A(7) (2025) from the statute’s December 31, 2024, deadline—the date

by which certain electric generating facilities must have “reach[ed] commercial

operation” in order to participate in Maine’s net energy billing program.

Without the exemption, Snakeroot’s proposed photovoltaic generating facility

in Pittsfield would be ineligible for net energy billing. Snakeroot contends that

the Commission erred in its interpretation of the statute’s good-cause

exemption; the Commission’s findings are unsupported by the record evidence;

and its denial of the exemption constituted an abuse of discretion. We affirm

the Commission’s order. 2

I. BACKGROUND

A. The Net Energy Billing Program

[¶2] Since the 1980s, Maine’s net energy billing1 (NEB) program has

promoted alternative energy sources by allowing customers to offset their

electric bills using the output from renewable power generators such as

home-installed solar panels. In 2019, the Legislature significantly expanded the

NEB program to permit utility customers with an interest in an electric

generating facility with a capacity of up to five megawatts using certain

“renewable fuel or technology,” see 35-A M.R.S. § 3210(2)(B-3) (2025), to

participate in the program. P.L. 2019, ch. 478, §§ A-3, A-4 (effective

Sept. 19, 2019) (codified as amended at 35-A M.R.S. §§ 3209-A, 3209-B (2025))

(“2019 NEB Act”).2

[¶3] The 2019 NEB Act prompted a sharp spike in the development of

Maine solar projects with generating capacities between two and five

1“Net energy billing” is defined as “a billing and metering practice under which a customer is billed on the basis of the difference between the kilowatt-hours delivered by a transmission and distribution utility to the customer over a billing period and the kilowatt-hours delivered by the customer to the transmission and distribution utility over the billing period, taking into account accumulated unused kilowatt-hour credits from the previous billing period.” 35-A M.R.S. § 3209-A(1)(C) (2025).

2 In addition to amending certain provisions in 35-A M.R.S. § 3209-A, the 2019 NEB Act enacted a

new section, codified at 35-A M.R.S. § 3209-B (2025), directed at “commercial and institutional customers.” The provisions of section 3209-B are not at issue here. 3

megawatts seeking to interconnect to the electrical grid, with the result of

substantially increasing utilities’ stranded costs.3 This so-called “solar gold

rush” thus gave rise to concerns that, absent intervention, rates would increase

sharply. Legis. Rec. H-750 (1st Spec. Sess. 2021); see also infra n.4.

Consequently, in 2021 the Legislature amended the 2019 NEB Act to curb

development and contain the projected impact on electricity rates.4 See P.L.

2021, ch. 390, § 1 (effective Oct. 18, 2021) (codified as amended at 35-A M.R.S.

§ 3209-A(7)) (“2021 Amendment”).5

[¶4] The 2021 Amendment set a total statewide target of 750 megawatts

of generating capacity for development of commercially operational

distributed generation resources6 participating in the NEB program. Id. The

3 “Stranded costs” are defined as “a utility’s legitimate, verifiable and unmitigable costs made unrecoverable as a result of the restructuring of the electric industry.” 35-A M.R.S. § 3208(1) (2025). Stranded costs are spread out among ratepayers by the Commission in the process of rate-setting. The Commission has determined that NEB costs should generally be treated like other stranded costs. Pub. Utils. Comm'n, Investigation of Rate Treatment of NEB Program Costs, No. 2021-360, Order at 8-10 (Me. P.U.C. Mar. 11, 2022). See generally Indus. Energy Consumer Grp. v. Pub. Utils. Comm'n, 2024 ME 60, 320 A.3d 437, for a more detailed discussion of stranded costs.

4 Legis. Rec. H-750-51 (1st Spec. Sess. 2021); Legis. Rec. S-1051-52 (1st Spec. Sess. 2021); see infra

¶¶ 31-32.

5 The statute was amended again in 2023, but the later amendments have no impact on this appeal. See P.L. 2023, ch. 230, § 1 (effective Oct. 25, 2023) (codified as amended at 35-A M.R.S. § 3209-A(8)); P.L. 2023, ch. 411, § 2 (effective Oct. 25, 2023) (codified at 35-A M.R.S. § 3209-A(9)).

6 A “distributed generation resource” refers to “an electric generating facility that uses a renewable fuel or technology . . . and is located in the service territory of a transmission and distribution utility.” 35-A M.R.S. § 3209-A(1)(B). 4

legislation established milestones with mandatory deadlines applicable to

projects with a generating capacity of between two and five megawatts,

including those under development at the time. See 35 M.R.S.

§ 3209-A(7)(A)-(E). A project was required to meet each milestone to

participate in the NEB program. See id.7 The final milestone in section

3209-A(7)(E)—and the one that prompted Snakeroot’s petition for a

good-cause exemption—provides as follows:

E. In order for a distributed generation resource to be used for net energy billing, the following must be met on or before December 31, 2024:

(1) The proposed distributed generation resource must reach commercial operation by the date specified in the net energy billing agreement or by the date specified with an allowable modification to that agreement.8

Id. § 3209-A(7)(E)(1). The 2021 Amendment also included a provision

allowing a developer of a distributed generation resource that could not meet

one or more of the milestones to petition the Commission “for a good-cause

7 The milestones in the 2021 Amendment set deadlines for, among other things, executing an interconnection agreement; commencing the interconnection study process; certifying that all applicable permit applications had been submitted to and accepted by the Department of Environmental Protection and certifying receipt of all necessary nonministerial permits from local authorities; and reaching full commercial operation. See 35-A M.R.S. § 3209-A(7)(A)-(E). The parties agree that Snakeroot Solar has met all milestone deadlines except the final one, which required that it reach commercial operation by December 31, 2024. Id. § 3209-A(7)(E).

8 Snakeroot’s NEB agreement does not alter the statutory deadline of December 31, 2024. 5

exemption due to external delays outside of the entity’s control.” Id.

§ 3209-A(7).

B. Overview of the Interconnection Process

[¶5] To initiate development of a distributed generation resource to be

used for net energy billing under the 2019 NEB Act, as amended by the 2021

Amendment, a project developer and the transmission and distribution (T&D)

utility9 in whose service territory the proposed project is located enter into two

agreements: (i) an interconnection agreement, which governs the connection

of the resource to the utility’s system and its ongoing operation thereafter,

65-407 C.M.R. ch. 324, § 2(EE) (effective Nov. 20, 2023); 35-A M.R.S.

§ 3209-A(7)(A)(1), and (ii) an NEB agreement, which governs credits for excess

energy exported to the grid, see 35-A M.R.S. § 3209-A(7)(A)(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellsworth ME Solar, LLC v. Public Utilities Comission
2026 ME 10 (Supreme Judicial Court of Maine, 2026)

Cite This Page — Counsel Stack

Bluebook (online)
2025 ME 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snakeroot-solar-llc-v-public-utilities-commission-me-2025.