O'Reilly v. United States Army Corps of Engineers

477 F.3d 225, 2007 WL 173936
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 25, 2007
Docket04-31026
StatusPublished
Cited by53 cases

This text of 477 F.3d 225 (O'Reilly v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Reilly v. United States Army Corps of Engineers, 477 F.3d 225, 2007 WL 173936 (5th Cir. 2007).

Opinion

DENNIS, Circuit Judge:

Plaintiffs, residents of St. Tammany Parish, Louisiana, who allege that the environment surrounding their dwellings, businesses, and recreational areas will be unlawfully harmed by a residential subdivision developer’s dredging and filling of wetlands, challenge the United States Army Corps of Engineers’ (“the Corps”) Finding Of No Significant Impact (“FON-SI”) on the environment under the National Environmental Policy Act of 1969 (“NEPA”), 42 U.S.C. §§ 4321-4370f, which resulted in the Corps’s issuance of a permit to dredge and fill wetlands to the developer under § 404 of the Clean Water Act, 33 U.S.C. § 1344. Plaintiffs contend that the Corps acted arbitrarily in issuing the FONSI for the dredge and fill permit because its Environmental Assessment (EA), the basis for the FONSI, (1) does not articulate a rational basis for finding that the mitigation measures imposed by the Corps upon the dredging and filling operations reduce their harmful effects below the level of significant environmental impacts; (2) does not adequately consider the project’s cumulative effects; and (3) improperly segments the project by considering only the first of three possible phases of development. Consequently, plaintiffs argue, NEPA required that the Corps prepare a full-fledged environmental impact statement (“EIS”) before issuing permits affecting the wetlands.

The district court agreed with plaintiffs and held that the Corps had acted arbitrarily in violation of NEPA because it failed to: (1) articulate or demonstrate how the mitigation measures will succeed; (2) consider the cumulative effects of the project, the permits to third parties, and the growing area urbanization; (3) consider the effects of the current proposal together with the effects of additional phases of the developer’s long range residential subdivision plans.

We agree with the district court that the Corps acted arbitrarily in issuing a FONSI based on an EA that fails to articulate how the mitigation measures will render the adverse effects insignificant and to consider the cumulative effects of the project, area urbanization, and permits issued to third parties. But we disagree with the district court’s conclusion that the Corps engaged in improper segmentation of the project by failing to include full analysis of two possible future phases of development in its EA. Accordingly, we affirm the district court’s holding that the Corps acted arbitrarily in the foregoing respects, but we amend the district court’s injunc *228 tion, reverse the balance of its decision, and remand the case to the Corps for further proceedings consistent with this opinion.

I. The NEPA Framework

Before we begin our analysis, we review NEPA’s framework, terminology and objectives. “NEPA ... was intended to reduce or eliminate environmental damage and to promote' ‘the understanding of the ecological systems and natural resources important to’ the United States.” Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 756, 124 S.Ct. 2204, 159 L.Ed.2d 60 (2004) (quoting 42 U.S.C. § 4321). Instead of mandating particular environmental results, NEPA “imposes procedural requirements on federal agencies, requiring agencies to analyze the environmental impact of their proposals and actions.” Coliseum Square Ass’n, Inc. v. Jackson, 465 F.3d 215, 224 (5th Cir.2006) (quoting Pub. Citizen, 541 U.S. at 756-57, 124 S.Ct. 2204). NEPA’s central requirement is that federal agencies must, except in certain qualifying situations, complete a detailed environmental impact statement (“EIS”) for any major federal action significantly affecting the quality of the human environment. 42 U.S.C. § 4332(2). To assist these agencies in determining whether an EIS must be prepared, NEPA authorized the Council on Environmental Quality (“CEQ”) to promulgate guidelines in the form of regulations. See 40 C.F.R. § 1500.3; see also Coliseum Square, 465 F.3d at 224.

NEPA requires an agency to produce a full EIS only where the agency proposes to undertake a project that qualifies as a “major Federal action[],” and then only when that action “significantly affect[s] the quality of the human environment.” 42 U.S.C. § 4332(2)(C); see also Coliseum Square, 465 F.3d at 228. The CEQ regulations define a “[mjajor Federal action” as “actions with effects that may be major and which are potentially subject to Federal control and responsibility.” 40 C.F.R. § 1508.18; see also Coliseum Square, 465 F.3d at 228. Effects, for the purposes of the regulations, “include: (a) [djirect effects, which are caused by the action and occur at the same time and place,” and “(b) [ijndirect effects, which are caused by the action and are later in time or farther removed in distance, but are still reasonably foreseeable.” 40 C.F.R. § 1508.8; see also Coliseum Square, 465 F.3d at 228.

“The CEQ regulations allow an agency to prepare a more limited document, an Environmental Assessment (EA), if the agency’s proposed action neither is categorically excluded from the requirement to produce an EIS nor would clearly require the production of an EIS.” Pub. Citizen, 541 U.S. at 757, 124 S.Ct. 2204 (citing 40 C.F.R. §§ 1501.4(a),(b)). An EA should be a “concise public document ... that serves to ... [bjriefly provide sufficient evidence and analysis for determining whether to prepare an [EIS].” 40 C.F.R. § 1508.9(a). In some cases, an agency may find that it must complete a full EIS. Where an EA results in a determination that an EIS is not required, however, the agency must issue a Finding of No Significant Impact (“FONSI”). Coliseum Square, 465 F.3d at 224 (quoting Pub. Citizen, 541 U.S. at 757, 124 S.Ct. 2204). The FONSI must briefly state “the reasons why the proposed agency action will not have a significant impact on the human environment.” Coliseum Square, 465 F.3d at 224 (citing 40 C.F.R. §§ 1501.4(e), 1508.13).

II. Factual and Procedural Background

A. Agency Proceedings

The Planche family plans to develop its plot of land in St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TX Assn of Manufacturers v. CPSC
989 F.3d 368 (Fifth Circuit, 2021)
State v. U.S. Envtl. Prot. Agency
389 F. Supp. 3d 497 (S.D. Texas, 2019)
Atchafalaya Basinkeeper v. U.S. Army Corps of Eng'rs
310 F. Supp. 3d 707 (M.D. Louisiana, 2018)
Friends of Animals v. Phifer
238 F. Supp. 3d 119 (D. Maine, 2017)
Sierra Club, Inc. v. Bostick
787 F.3d 1043 (Tenth Circuit, 2015)
Frito-Lay, Inc. v. United States Department of Labor
20 F. Supp. 3d 548 (N.D. Texas, 2014)
Defenders of Wildlife v. United States Department of the Navy
895 F. Supp. 2d 1285 (S.D. Georgia, 2012)
Webster v. United States Department of Agriculture
685 F.3d 411 (Fourth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
477 F.3d 225, 2007 WL 173936, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oreilly-v-united-states-army-corps-of-engineers-ca5-2007.