Maryland - National Capital Park and Planning Commission a Public Body Corporate v. U. S. Postal Service

487 F.2d 1029, 159 U.S. App. D.C. 158, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20702, 5 ERC (BNA) 1719, 1973 U.S. App. LEXIS 8230, 5 ERC 1719
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 23, 1973
Docket72-2126
StatusPublished
Cited by152 cases

This text of 487 F.2d 1029 (Maryland - National Capital Park and Planning Commission a Public Body Corporate v. U. S. Postal Service) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland - National Capital Park and Planning Commission a Public Body Corporate v. U. S. Postal Service, 487 F.2d 1029, 159 U.S. App. D.C. 158, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20702, 5 ERC (BNA) 1719, 1973 U.S. App. LEXIS 8230, 5 ERC 1719 (D.C. Cir. 1973).

Opinion

LEVENTHAL, Circuit Judge:

This appeal is taken from the District Court’s denial of a preliminary injunction in a suit by the Maryland-National Capital Park and Planning Commission to stop continued construction of the Washington Bulk Mail Center now under construction on a 63-acre tract in Prince George’s County, Maryland, adjacent to the west side of the Capital Beltway, a major divided highway. The site already contained significant industrial development. On the southern border was a PEPCO power line, to the north a large Coca Cola bottling plant, and shopping center. Appellant claims that the Post Office was required to file an environmental impact statement pursuant to the requirements of the National Environmental Policy Act of 1969 (NEPA). Jurisdiction is properly taken under 28 U.S.C. § 1292(a)(1). We do not reverse the denial of the preliminary injunction that has been appealed, but believe that the case calls for a remand to consider the matters identified in our opinion.

I. STATEMENT OF FACTS

Early in 1970, the Post Office Department began formulating specific plans for site acquisition and construction of the Bulk Mail Facility. In November of the same year, the Post Office referred its plans for the building project to the National Capital Planning Commission (NCPC) for approval pursuant to the provisions of 40 U.S.C. § 71d, which generally provides for “comprehensive planning and orderly development of the National Capital”, for advance submission by a Federal Agency “of plans and programs in preliminary and successive stages which affect the plan and development of the National Capital.” The statute does not require Commission approval before action is taken, but it does contemplate consideration of the report and recommendations of the Commission. Specifically, when development plans require the acquisition of land, plans must be submitted “to the Commission for report and recommendations before final commitment to said acquisition, unless such matters shall have been specifically approved by Congress.” The Commission, in turn consults with “the appropriate planning agency having jurisdiction over the affected part of the environs”, in this case the appellant, Maryland-National Capital Park and Planning Commission (MNCPC).

Following referral from NCPC, MNCPC offered its views on the proposed project by Resolution adopted De *1033 cember 23, 1970. This Resolution based its conclusion on a review of the project by the Prince George’s County Planning Board, and disapproved the proposed location as well as the Preliminary Master Plan for the Facility. While the “overriding issue” underlying the rejection was “social and economic”, rooted in the prospective loss of real and personal property taxation, the Resolution also called attention to other undesirable effects of the plan: (1) the uncertain state of authorization for water and sewer service, (2) increased traffic in the area, (3) inadequate provision for a storm-water and oil run-off, and (4) “visual and aesthetic detriment” connected with the placement near the Beltway of exterior parking and loading facilities. The proposed facility was to be placed in 1-1 and 1-3 zoning, as part of an industrial park. Twenty-five of the 63 acres were zoned 1-3, which included a 500 foot-wide strip along the Beltway to be used by the Department, later to become the Postal Service. The NMCPC concluded that “[t]he proposed bulk mail facility is a permitted use” in both zones, since permitted uses included a “[pjublic building where owned and/or operated by a government agency.”

Despite the fact that the facility was thought to be a “permitted use” by the Board, it noted in its conclusions and recommendation :

The proposed facility is not wholly in conformance with either the intent of the 1-3 zone ordinance to encourage high-quality industrial uses, or the intent of the establishment of á 500-foot strip of 1-3 zoning along the Beltway. Good visibility, prestige location and other related factors were not indicated as necessary for this facility by the Post Office.

On March 4, 1971, the ÑCPC approved the “general location, character, extent and intensity of use for the Facility” provided, however, that the site be moved out of the 1-3 zone and located entirely within the 1-1 zone. In conditioning approval on the site change, primary concern was with the use of 500-foot wide strip of 1-3 zoning along the Beltway. The NCPC repeated the objections of the Prince George’s Planning Board that this space was intended to be reserved for “high quality industries on campus-like settings.”

A summary and over-simplified statement of 1-1 and 1-3 zoning appears in footnote *

The NCPC also requested that consideration continue to be given to oil and water run-off, landscaping of the loading and docking areas, and housing and related public facilities for new employees of the Post Office who would become residents of the area.

On or about May 6, 1971, the Post Office agreed to change the location of the Facility. As described by NCPC, in a Report of the Federal Planning and Projects Committee, “[t]he proposed site is 500 feet west of the Capital Beltway within the Hampton Industrial Park and the 1-1 zone, except approximately seven acres currently designated RR (Rural Residential). However, the proposed development is a use permitted in the RR zone under the county’s Zoning Ordinance.” This change in location satisfied the condition made part of the NCPC approval of March 4.

At this point of the factual background, the record is unclear. 1 In Octo *1034 ber 1971, the grading and foundation contract was awarded by the Post Office. However, evidently at some time between May 6 and October, the Postal Service decided to revert to its prior plan to use 1-3 zoning along the Beltway. As a matter of record, this first came to light when the Post Office, on July 12, 1972, submitted to NCPC its preliminary site and building plans. By this time work had already begun on grading and foundation. The justification for the use of the 1-3 zone was made a part of this July 12 submission, and was based on a study by consultants for the Post Service, Giffels Associates, and U. S. Corps of Engineers (the building agent of the Post Office).

Giffels concluded, contrary to the assertion of the NCPC Committee on May 6, 1971, that a move westerly to the RR zone would require a re-zoning. Giffels also concluded that such a move had design disadvantages, and would have required the destruction of several acres of natural wooded area. Their proposal was, therefore, to remedy the visual problem posed by use of the 1-3 zone by significantly increasing the landscaping plans and budget. The submission to NCPC also included an environmental assessment, taken from the Giffels study, from which the Corps of Engineers concluded that it was not necessary to prepare a full environmental impact statement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Van Antwerp
719 F. Supp. 2d 58 (District of Columbia, 2010)
Lemon v. Harvey
District of Columbia, 2009
Basel Action Network v. Maritime Administration
370 F. Supp. 2d 57 (District of Columbia, 2005)
Government of the Province of Manitoba v. Norton
398 F. Supp. 2d 41 (District of Columbia, 2005)
Pogliani v. United States Army Corps of Engineers
166 F. Supp. 2d 673 (N.D. New York, 2001)
Virgin Islands Tree Boa v. Witt
918 F. Supp. 879 (Virgin Islands, 1996)
Coalition on Sensible Transportation Inc. v. Dole
642 F. Supp. 573 (District of Columbia, 1986)
Foundation on Economic Trends v. Weinberger
610 F. Supp. 829 (District of Columbia, 1985)
State of La. v. Lee
596 F. Supp. 645 (E.D. Louisiana, 1984)
Foundation on Economic Trends v. Heckler
587 F. Supp. 753 (District of Columbia, 1984)
Town of Orangetown v. Gorsuch
718 F.2d 29 (Second Circuit, 1983)
Natural Resources Defense Council, Inc. v. Vaughn
566 F. Supp. 1472 (District of Columbia, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
487 F.2d 1029, 159 U.S. App. D.C. 158, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20702, 5 ERC (BNA) 1719, 1973 U.S. App. LEXIS 8230, 5 ERC 1719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-national-capital-park-and-planning-commission-a-public-body-cadc-1973.