National Trust for Historic Preservation in the United States v. Elizabeth H. Dole

819 F.2d 1164, 17 Envtl. L. Rep. (Envtl. Law Inst.) 21
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 2, 1987
Docket85-6182
StatusPublished
Cited by3 cases

This text of 819 F.2d 1164 (National Trust for Historic Preservation in the United States v. Elizabeth H. Dole) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Trust for Historic Preservation in the United States v. Elizabeth H. Dole, 819 F.2d 1164, 17 Envtl. L. Rep. (Envtl. Law Inst.) 21 (D.C. Cir. 1987).

Opinions

Opinion for the Court PER CURIAM.

Opinion concurring in part and dissenting in part filed by Circuit Judge BUCKLEY.

PER CURIAM:

This appeal arises from a dispute over the federally-funded construction of suicide prevention barriers on the Duke Ellington Bridge, an historic landmark in Washington, D.C. Appellants, distressed by the barriers’ effect on the appearance of the bridge, seek to require the Federal Highway Administration (FHWA) to evaluate alternatives to and the environmental con[1166]*1166sequences of the barriers.1 The District Court found that the FHWA’s determination that it was not statutorily bound to conduct such evaluations was not arbitrary and capricious, and granted summary judgment. We affirm.

I

The Duke Ellington Bridge, which spans Rock Creek Park (a national park), is an historic landmark eligible for inclusion in the National Register of Historic Places. The bridge has, unfortunately, become a popular place for suicide; according to the District of Columbia Medical Examiner’s Office, 37 suicides occurred from D.C. bridges between January 1979 and June 1985, 21 of which occurred from the Duke Ellington Bridge. Appendix at 124. In an effort to prevent, or at least deter, such suicides, the District of Columbia Department of Public Works decided to erect high, picket-like metal safety barriers along the sides of the bridge.2

In September 1984, the Department of Public Works sought and received federal funding for approximately 80 percent of the project from the United States Department of Transportation (the Department) through the FHWA. Due to the FHWA’s substantial involvement, it had to contend with the potential applicability of procedural protections contained in two provisions of law: first, section 4(f) of the Department of Transportation Act of 1966, 49 U.S.C. § 303(c) (1982), which authorizes the Secretary of the Department to approve a transportation project requiring the use of an historic site only if no prudent and feasible alternative exists and harm to the site is minimized; and second, section 102(2)(c) of the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. § 4332(2)(C) (1982), which requires federal agencies to prepare an environmental impact statement on “proposals for ... major Federal actions significantly affecting the quality of the human environment.” In conjunction with its funding decision, however, the FHWA determined that construction of the barriers was exempt from the procedural requirements of both statutes.

Preliminary installation work on the bridge thus began on August 20, 1985. Concerned about what they considered the damage to the bridge's appearance, appellants promptly filed suit, claiming that the FHWA’s determination that erection of the barriers was not protected by the procedural mandate of NEPA or the Department of Transportation Act was arbitrary and capricious under the Administrative Procedure Act (APA), 5 U.S.C. § 706 (1982).3 Appellants sought declaratory relief and preliminary and permanent injunctions to halt the erection of the barriers and force the FHWA to evaluate the project under [1167]*1167the environmental statutes. On August 29, 1985, the District Court denied appellants’ application for a temporary restraining order. Work on the project thus continued until September 20, 1985, when it was voluntarily suspended. Following a bench trial,4 the District Court issued an opinion and order on October 3, 1985 granting summary judgment in favor of the FHWA, the Department of Transportation, and the Department of Public Works. Construction resumed in December, 1985, and the barriers are now fully in place.5

Before us, appellants argue that summary judgment was improperly granted. In reviewing their contentions, we turn first to the Department of Transportation Act, and then to NEPA.6

II. The 4(f) Issue

In their complaint, appellants allege that appellees are in violation of section 4(f) of the Department of Transportation Act “because construction of the proposed barriers would require the use of historic sites, because there are prudent or feasible alternatives to erecting barriers on these bridges and because the proposed barriers do not include all possible planning to minimize harm to the bridges.” Complaint at 2-3, Appendix at 94-95. Appellees claim that the installation of suicide prevention barriers do not represent a “use” of bridges within the meaning of section 4(f). We agree with the District Court’s conclusion that section 4(f) is not applicable to this case, but for different reasons than those given by the court.

A. The Statutory Language

Section 4(f) of the Department of Transportation Act reads in pertinent part as follows:

The Secretary may approve a transportation program or project requiring the use of publicly owned land of a public park ... or land of an historic site ... only if—
(1) there is no prudent and feasible alternative to using that land; and
(2) the program or project includes all possible planning to minimize harm to the park ... or historic site resulting from the use.

49 U.S.C. § 303(c) (1982) (emphasis added). Thus two requirements must be met before the provisions of section 4(f) may be invoked. First, the program or project to be approved must serve a transportation purpose; that is to say, it must deal with the movement of goods or persons from one place to another. Second, that program or project must require the use of land. Only if these conditions are shown to exist do we need to determine whether the requirements of subsections (1) (a finding that no prudent or feasible alternative exists) and (2) (planning to minimize harm) have been met.

This construction is dictated by the plain meaning of the statutory language, and is [1168]*1168required by the Supreme Court’s most recent guidance on statutory interpretation:

If the statute is clear and unambiguous “that is the end of the matter, for the Court, as well as the agency, must give effect to the unambiguously expressed intent of Congress.” Chevron U.S.A., Inc. v. National [sic] Resources Defense Council, Inc., 467 U.S. 837, 842-43 [104 S.Ct. 2778, 2781, 81 L.Ed.2d 694] (1984). The traditional deference courts pay to agency interpretation is not to be applied to alter the clearly expressed intent of Congress.

Board of Governors v. Dimension Fin. Corp., 474 U.S. 361, 106 S.Ct. 681, 686, 88 L.Ed.2d 691 (1986).

Appellants have failed to meet this threshold test.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
819 F.2d 1164, 17 Envtl. L. Rep. (Envtl. Law Inst.) 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-trust-for-historic-preservation-in-the-united-states-v-elizabeth-cadc-1987.