City Of Alexandria, Virginia v. Federal Highway Administration

756 F.2d 1014, 1985 U.S. App. LEXIS 31401
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 11, 1985
Docket84-1349
StatusPublished
Cited by9 cases

This text of 756 F.2d 1014 (City Of Alexandria, Virginia v. Federal Highway Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City Of Alexandria, Virginia v. Federal Highway Administration, 756 F.2d 1014, 1985 U.S. App. LEXIS 31401 (4th Cir. 1985).

Opinion

756 F.2d 1014

CITY OF ALEXANDRIA, VIRGINIA, A Municipal Corp., The City
Council of Alexandria, Virginia, A Body Politic, Appellants,
and
Board of Supervisors of Fairfax County, Virginia, Plaintiff,
v.
FEDERAL HIGHWAY ADMINISTRATION; Ray A. Barnhart,
Administrator, Federal Highway Administration; Commonwealth
of Virginia; Virginia Department of Highways and
Transportation; Harold C. King, Commissioner, Va. Dept. of
Highways; and Elizabeth Hanford Dole, Secretary of
Transportation, U.S., Appellees.

No. 84-1349.

United States Court of Appeals,
Fourth Circuit.

Argued Jan. 8, 1985.
Decided March 11, 1985.

Jerry K. Emrich, Arlington, Va. (Walsh, Colucci, Malinchak, Emrich & Lubeley, P.C., Arlington, Va., Cyril D. Calley, Alexandria City Atty., Alexandria, Va., on brief), for appellants.

Albert M. Ferlo, Jr., Dept. of Justice, Washington, D.C. (James F. Hayes and E. Suzanne Darling, Asst. Attys. Gen., F. Henry Habicht, II, Asst. Atty. Gen., Washington, D.C., Elsie L. Munsell, U.S. Atty., Alexandria, Va., Paula M. Potoczak, Asst. U.S. Atty., Dirk D. Snel, Dept. of Justice, Washington, D.C., on brief), for appellees.

Before WINTER, Chief Judge, and PHILLIPS and MURNAGHAN, Circuit Judges.

HARRISON L. WINTER, Chief Judge:

This appeal presents the issue of whether the Federal Highway Administration (FHWA) acted arbitrarily and capriciously in concluding that the Shirley Highway Traffic Management System was categorically excluded from the National Environmental Policy Act's requirements. We agree with the district court that FHWA's actions were not arbitrary and capricious and therefore affirm.

I.

Shirley Highway (I-395) is a limited access divided highway that links some of the northern Virginia suburbs with Washington, D.C. and a part of which runs through the City of Alexandria. The highway has three standard lanes each northbound and southbound, but it also has two reversible lanes in the center, which carry northbound traffic during the morning rush period and southbound traffic during the afternoon rush period. The two center lanes are normally open only to high occupancy vehicles (HOV's), which are vehicles with four or more occupants. The entire highway is heavily traveled, but during peak periods the HOV lanes carry over twice as many persons at substantially greater speeds than do the standard lanes.

The Traffic Management System is designed to reduce congestion and travel times on the non-HOV lanes of Shirley Highway and on portions of I-66, which does not run through Alexandria. Most of the components of the system, such as widening access ramps, restriping the highway to create an additional traffic lane, and traffic surveillance and motorist advisory signs, are not challenged on appeal. The City's only complaint is with the entrance ramp metering system, which is a computerized system of traffic sensors and control lights that is designed to adjust the rate of flow on the entrance ramps to balance the highway and entrance ramp capacity with the demand of traffic to enter the highway. The total cost of the improvements on I-66 and Shirley Highway is about $20 million, and the cost of the ramp metering system alone on Shirley Highway is about $5 million. The FHWA provided 90% of the funds to the Virginia Department of Highways and Transportation (VDH & T), which will be responsible for operation and maintenance of the system. At the time of oral argument of this appeal all of the construction on the project was complete and the ramp metering system was only awaiting final computer programming and testing before it would be fully operational.

Planning for this project began in 1976, when the VDH & T commissioned a formal study of the traffic problems on Shirley Highway. The VDH & T then requested preliminary engineering and design funding from the FHWA based on that study's recommendations, and the project was discussed at meetings of the National Capitol Region Transportation Planning Board of the Washington Metropolitan Area Council of Governments (COG). The City of Alexandria is a member of the latter group, as well as of the Shirley Highway Steering Committee that was established to monitor the progress of the project after COG's May 1978 approval of it. Additional engineering and design studies were prepared in 1978 and 1979. In April of 1981 the VDH & T submitted air quality and noise studies to the FHWA. Based on these studies, the general plans, and an on-site inspection, in August 1981 the FHWA approved VDH & T's recommendation that no further environmental studies were required because the project qualified as a categorical exclusion under 23 C.F.R. Sec. 771.115(b)(13) and (14).

The City voiced no objections to the project prior to its approval, presumably on the assumption that the system would not be operated so as to cause diversion of traffic from the highway onto local streets. By 1982 the City began to doubt representations to that effect, and city officials began making further inquiry about the actual diversionary effects and the extent to which the FHWA had considered those effects in approving the categorical exclusion. In the spring of 1983 the FHWA reviewed its previous decision approving the project as a categorical exclusion and adhered to that determination.

The City of Alexandria filed this action in district court on July 22, 1983, seeking a declaration that the FHWA violated the National Environmental Policy Act (NEPA) by not preparing an environmental impact statement or an environmental assessment for the Shirley Highway project and seeking to enjoin the defendants from operating the system until after they complied with the statute. Fairfax County brought a similar action that was consolidated with the City's suit in district court, but the County has not appealed. Since the administrative record filed with the district court was unilluminating on several important issues, the district court permitted and considered separate discovery materials.1 On February 28, 1984, upon cross-motions for summary judgment, the district court held that the FHWA had not been arbitrary or capricious in declining to prepare an environmental impact statement and therefore dismissed plaintiffs' complaints. On May 18, 1984, the district court denied a motion for an injunction pending appeal, and, on the representation that the system would not be operational until February 1, 1985 at the earliest, we did likewise on December 21, 1984.

II.

We consider first the City's argument that our standard of review of FHWA's action should be one of "reasonableness." Whenever agency action is subjected to judicial review under the Administrative Procedure Act, the standards of review specified by the statute remain precisely the same, and none of them mentions "reasonableness" other than in connection with inaction or delay. See 5 U.S.C. Sec. 706. Our precedents indicate that the provision of that statute relevant to a nonadversarial decision not to prepare an environmental impact statement (EIS),2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
756 F.2d 1014, 1985 U.S. App. LEXIS 31401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-alexandria-virginia-v-federal-highway-administration-ca4-1985.