Pogliani v. United States Army Corps of Engineers

166 F. Supp. 2d 673, 2001 U.S. Dist. LEXIS 11513, 2001 WL 958802
CourtDistrict Court, N.D. New York
DecidedAugust 10, 2001
Docket1:01-CV-0951
StatusPublished
Cited by11 cases

This text of 166 F. Supp. 2d 673 (Pogliani v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pogliani v. United States Army Corps of Engineers, 166 F. Supp. 2d 673, 2001 U.S. Dist. LEXIS 11513, 2001 WL 958802 (N.D.N.Y. 2001).

Opinion

MEMORANDUM-DECISION AND ORDER

MORDUE, District Judge.

I. INTRODUCTION

On June 13, 2001, plaintiffs, concerned citizens and/or property owners in or near the Town of Athens, New York, filed a complaint seeking to permanently enjoin defendant, the United States Army Corps of Engineers (“the Army Corps”), from issuing a permit to proposed intervenor, Athens Generating Company (“Athens Generating”), for construction of a 1080 megawatt gas-fired power plant in Athens, *676 New York located in scenic Hudson River Valley. On the same date, plaintiff also filed an Order to Show Cause seeking a Temporary Restraining Order (“TRO”), pending a motion to enjoin defendant from issuing the aforementioned permit. By way of the TRO, plaintiffs sought an Order suspending both the permit (which was issued to Athens Generating on May 25, 2001) as well as pre-construction work on the power plant project which began on or about May 29, 2001.

Also on June 13, 2001, Athens Generating filed a motion to intervene in this action as a defendant via Order to Show Cause. On June 18, 2001, the Court conducted a hearing via telephone in connection with the parties’ arguments on the TRO and deferred argument on the issue of intervention by Athens Generating pending receipt of papers by plaintiffs in opposition to said relief. The Court denied plaintiffs’ TRO application orally at the conclusion of said telephone conference and by written Order dated June 28, 2001, but set the return date for plaintiffs’ motion for a preliminary injunction for July 5, 2001.

II. FACTUAL AND PROCEDURAL BACKGROUND

On September 9, 1997, Athens Generating, an indirect wholly owned subsidiary of Pacific Gas & Electric Corporation (“PG&E”), commenced a state administrative proceeding by submitting a “pre-ap-plication” report, required to obtain a Certificate of Environmental Compatibility and Public Need (“certificate”) for construction of a major electric generation facility, 1 to the New York State Board on Electric Generation Siting and the Environment (“Siting Board”) under Article X of the New York Public Service Law (“Article X”). See N.Y. Pub. Serv. Law § 160 et seq. 2 The Siting Board and Athens Generating thereafter received public input concerning the report by way of public hearings, mail, telephone and the internet. The Siting Board and Athens Generating simultaneously engaged in a formal stipulation process which defined *677 the appropriate “pre-application” environmental studies, which were completed by Athens Generating and its consultants. On August 28, 1998, Athens Generating filed its formal application for a certificate and the Siting Board Chair determined that the application was complete on October 22, 1998.

Administrative Law Judges from the New York State Department of Environmental Conservation (“DEC”) and the New York State Department of Public Service (“DPS”) were appointed to serve as Hearing Examiners. The Hearing Examiners conducted a prehearing conference and public statement hearings in November 1998 and following pre-filed testimony on all issues, held evidentiary hearings in March, April and June 1999. After a round of initial and reply briefs from various parties including some voluntary citizens’ groups, the Hearing Examiners issued a 339-page recommended decision on September 3, 1999, suggesting that the Siting Board grant a certificate, subject to a number of specified terms and conditions.

Interested parties filed exceptions to the recommended decision to the Siting Board in addition to further briefs opposing the exceptions, in September and October 1999. On November 30, 1999, the Siting Board Chair requested supplemental information from Athens Generating concerning the plant’s cooling technology, visual impacts, and related issues. On remand, the Hearing Examiners considered a number of issues, including the facility’s proposed configuration if dry cooling technology were to be utilized. Responsive and rebuttal testimony was filed in December 1999 and January 2000. Additional hearings were held on January 26 and 27, 2000, and supplemental initial briefs and reply briefs were filed by the parties in February 2000.

The application for Article X certification filed by Athens Generating also included an application to DEC for a State Pollutant Discharge Elimination System (hereinafter “SPDES”) permit for the withdrawal of water from the Hudson River for cooling purposes and the subsequent discharge of the unevaporated remainder. Based upon the determination by the Commissioner of DEC that water intake should be limited to 0.18 million gallons per day in order to satisfy “best technology available” requirements and avoid adverse impacts on Hudson River fish populations, the SPDES permit issued by DEC on June 12, 2000, effectively required that the plant utilize “dry” cooling technology as opposed to the “wet” or hybrid evaporative cooling system which was originally proposed and which would have required considerably more water.

In a 123-page opinion and order issued June 15, 2000, the Siting Board granted Athens Generating a certificate to construct the plant subject to certain conditions. As required by Article X, the Siting Board made several findings including: (1) a determination that the plant was selected pursuant to an approved procurement process and would serve the public interest (see, N.Y. Pub. Serv. Law §§ 168(2)(a)(ii); (e)); (2) adverse impacts upon the environment would be minimized and the facility would be compatible with public health and safety by virtue of the certificate terms set forth in the Siting Board approval order and the terms of permits issued by other agencies, including the DEC requirement concerning the use of dry cooling technology (see, N.Y. Pub. Serv. Law §§ 168(2)(c)(i), (ii)); (3) the plant’s effect on the area’s visual resources would be mitigated by lowering the height of the emission stack and cooling tower from 225 to 213 and ultimately to 180 feet, and using dry cooling to eliminate steam plumes (see, N.Y. Pub. Serv. Law § 168(2)(b)); and (4) certain waivers from the Town’s zoning *678 ordinances deemed “unreasonably restrictive” in relation to Article X’s goal of promoting development of additional major power sources while at the same time balancing environmental concerns were required (see, N.Y. Pub. Serv. Law § 168(2)(d)).

By petition dated July 14, 2000, Citizens for the Hudson Valley, Inc. (an organization in which plaintiff Sevastopoulo is a founder and a principal) along with other interested parties sought rehearing, which petition was denied by the Siting Board on August 10, 2000. On September 8, 2000, the aforementioned petitioners commenced an action pursuant to Article 78 of New York Civil Practice Law and Rules and Article X seeking nullification of the certificate arguing that the Siting Board’s decision granting the Certificate was arbitrary and capricious and not supported by substantial evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nat'l Parks Conservation Ass'n v. Semonite
311 F. Supp. 3d 350 (D.C. Circuit, 2018)
Defend H20 v. Town Board of East Hampton
147 F. Supp. 3d 80 (E.D. New York, 2015)
Pogliani v. U.S. Army Corps of Engineers
146 F. App'x 528 (Second Circuit, 2005)
Pogliani v. United States Army Corps Of Engineers
306 F.3d 1235 (Second Circuit, 2002)
Stewart Park & Reserve Coalition, Inc. v. Slater
225 F. Supp. 2d 219 (N.D. New York, 2002)
STEWART PARK AND RESERVE CO-ALITION, INC. v. Slater
225 F. Supp. 2d 219 (N.D. New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
166 F. Supp. 2d 673, 2001 U.S. Dist. LEXIS 11513, 2001 WL 958802, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pogliani-v-united-states-army-corps-of-engineers-nynd-2001.