Sierra Club v. U.S. Army Corps of Engineers

909 F.3d 635
Court of Appeals for the Fourth Circuit·Decided November 27, 2018·No. 18-1173; 18-1757·Published·Cited by 30 cases

Opinion

WYNN, Circuit Judge:

The Sierra Club, West Virginia Rivers Coalition, Indian Creek Watershed Association, Appalachian Voices, and Chesapeake Climate Action Network ("Petitioners") ask this Court to set aside Respondent U.S. Army Corps of Engineers' (the "Corps") December 22, 2017, verification ("Verification") and July 3, 2018, reinstated verification ("Reinstatement") that construction of the Mountain Valley Pipeline (the "Pipeline") can proceed under the terms and conditions of Clean Water Act Nationwide Permit 12 ("NWP 12"), rather than an individual permit. For the reasons that follow, we hold that the Corps lacked statutory authority to substitute its own special condition "in lieu of" a different special condition imposed by West Virginia as part of its certification of NWP 12.

We further conclude that, absent completion of the notice-and-comment procedures required by the Clean Water Act, a state cannot waive a special condition previously imposed as part of its certification of a nationwide permit. Because West Virginia did not follow its federally mandated notice-and-comment procedures in waiving another special condition the state imposed as part of its certification of NWP 12, that condition remains a required-but, in this case, unsatisfied-condition of the nationwide permit. Accordingly, we vacate, in their entirety, the Corps' December 22, 2017, Verification and July 3, 2018, Reinstatement authorizing the Pipeline's compliance with NWP 12.

I.

A.

The 42-inch diameter natural gas Pipeline proposes to run 304 miles through parts of Virginia and West Virginia, crossing the Corps' Pittsburgh, Norfolk, and Huntington Districts. In the Corps' Huntington District, the Pipeline and related access roads propose to cross 591 federal water bodies, including four major rivers (the Elk, Gauley, Greenbrier, and Meadow), three of which are navigable-in-fact rivers regulated by Section 10 of the Rivers and Harbors Act of 1899 (the Elk, Gauley, and Greenbrier). 33 U.S.C. § 403 . Following extensive administrative proceedings, Intervenor Mountain Valley Pipeline, LLC ("Mountain Valley") obtained a certificate from the Federal Energy Regulatory Commission ("FERC") to construct and operate the Pipeline. Because construction of the Pipeline will involve the discharge of fill material into federal waters, the Clean Water Act requires that Mountain Valley obtain clearance from the Corps before beginning construction. 33 U.S.C. § 1344 (a).

The Corps has established, by regulation, two methods to obtain a permit to discharge fill material into federal waters. See Crutchfield v. Cty. of Hanover, Va. , 325 F.3d 211 , 214 (4th Cir. 2003). First, the Corps "can issue individual permits on a case-by-case basis," through a "resource-intensive review" requiring "extensive site-specific research and documentation, promulgation of public notice, opportunity for public comment, consultation with other federal agencies, and a formal analysis justifying the ultimate decision to issue or refuse the permit." Id. (citing 33 C.F.R. §§ 320.4 , 325.1 - 325.3 ). Alternatively, "interested parties can try to fit their proposed activity within the scope of an existing general permit," in this case NWP 12, "which acts as a standing authorization for developers to undertake an entire category of activities deemed to create only minimal environmental impact." Id. (citing 33 U.S.C. § 1344 (e) ; 33 C.F.R. §§ 320.1 (c), 330.1(b) - (c) ). Potential permittees "must satisfy all terms and conditions of an NWP for a valid authorization to occur." 33 C.F.R. § 330.4 (a) (emphasis added). Mountain Valley elected to pursue the general permit approach to obtain the Corps' clearance to discharge fill as part of Pipeline construction.

NWP 12, reissued most recently in 2017, 82 Fed. Reg. 1860 (Jan. 6, 2017), authorizes the discharge of dredged or fill material into federal waters attributable to "the construction, maintenance, repair, and removal of utility lines and associated facilities in waters of the United States." J.A. 40. NWP 12 includes several General Conditions designed to ensure that activities falling under NWP 12 minimally impact water quality, the aquatic environment and adjacent land, and water bodies managed by the Corps. See, e.g. , J.A. 45-46 (establishing conditions related to "adverse effects from impoundments," "soil erosion and sediment controls," and "removal of temporary fills."). General Condition 7 provides that, "No activity may occur in the proximity of a public water supply intake, except where the activity is for the repair or improvement of public water supply intake structures or adjacent bank stabilization." J.A. 46.

As with any other federal Clean Water Act permit, an applicant for a Section 1344(a) permit, like Mountain Valley, "shall provide the [Corps] a certification from the State in which the discharge originates or will originate," unless the state waives, either explicitly or by inaction, its right to independently certify the project. 33 U.S.C. § 1341 (a)(1) ; see also 33 C.F.R. § 325.2 (b)(1)(ii).

Free access — add to your briefcase to read the full text and ask questions with AI

Sierra Club v. U.S. Army Corps of Engineers, 909 F.3d 635 (4th Cir. 2018).

909 F.3d 635 (Sierra Club v. U.S. Army Corps of Engineers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related