Sierra Club v. West Virginia DEP

64 F.4th 487
Court of Appeals for the Fourth Circuit·Decided April 3, 2023·No. 22-1008·Published·Cited by 5 cases

Opinion

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 22-1008

SIERRA CLUB; WEST VIRGINIA RIVERS COALITION; WEST VIRGINIA HIGHLANDS CONSERVANCY; INDIAN CREEK WATERSHED ASSOCIATION; APPALACHIAN VOICES; CHESAPEAKE CLIMATE ACTION NETWORK,

Petitioners,

v.

WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION; HAROLD WARD, in his official capacity as Secretary of the West Virginia Department of Environmental Protection,

Respondents,

MOUNTAIN VALLEY PIPELINE, LLC, Intervenor.

On Petition for Review of a Certification Issuance of the West Virginia Department of Environmental Protection. (FERC Docket No. WQC-2021-005)

Argued: October 25, 2022 Decided: April 3, 2023

Before GREGORY, Chief Judge, WYNN, and THACKER, Circuit Judges.

Petition for review granted and certification vacated by published opinion. Chief Judge Gregory wrote the opinion, in which Judge Wynn and Judge Thacker joined.

ARGUED: Derek Owen Teaney, APPALACHIAN MOUNTAIN ADVOCATES, INC., Lewisburg, West Virginia, for Petitioners. Lindsay Sara See, OFFICE OF THE ATTORNEY GENERAL OF WEST VIRGINIA, Charleston, West Virginia, for Respondents. George Peter Sibley, III, HUNTON ANDREWS KURTH, LLP, Richmond, Virginia, for Intervenor. ON BRIEF: Benjamin A. Luckett, Elizabeth A. Bower, APPALACHIAN MOUNTAIN ADVOCATES, INC., Lewisburg, West Virginia, for Petitioners. Patrick Morrisey, Attorney General, Michael R. Williams, Senior Deputy Solicitor General, Caleb A. Seckman, Assistant Attorney General, OFFICE OF THE ATTORNEY GENERAL OF WEST VIRGINIA, Charleston, West Virginia, for Respondents. J. Pierce Lamberson, Richmond, Virginia, Deidre G. Duncan, HUNTON ANDREWS KURTH LLP, Washington, D.C.; Robert G. McLusky, Jennifer L. Hughes, JACKSON KELLY PLLC, Charleston, West Virginia; Justin W. Curtis, AQUALAW PLC, Richmond, Virginia, for Intervenor.

GREGORY, Chief Judge:

This appeal is the latest installment in a series of challenges to Mountain Valley Pipeline, LLC’s (“MVP”) plans to build a natural gas pipeline. Because it intends to construct a portion of the pipeline in West Virginia, MVP obtained a Clean Water Act (“CWA”) certification from the West Virginia Department of Environmental Protection (the “Department”). The certification reflected the Department’s conclusion that MVP’s activities during the pipeline’s construction would not violate the state’s water quality standards. Disagreeing with that determination, landowners and members of various environmental organizations in the state (collectively, “Petitioners”) have petitioned for this Court’s review of the Department’s certification. We find the Department’s justifications for its conclusions deficient and vacate the certification.

I.

A.

In 2018, MVP began building an approximately 304-mile, forty-two-inch diameter pipeline. Spanning Virginia and West Virginia, the pipeline is intended to be an essential conduit for delivering natural gas to markets in the mid-Atlantic, Southeastern, and Appalachian regions of the United States. Approximately 197 miles of the pipeline will be constructed in West Virginia, crossing many of the state’s aquatic resources along its path.

Pipelines can cross waterbodies in two ways. One construction method uses trenchless crossings to conduct conventional boring under waterbodies, which do not require digging and excavating the soil. MVP will use this method for a portion of its

crossings. For most crossings, though, MVP has chosen to trench through waterbodies using open-cut crossings. The open-cut crossing method allows MVP to “work in the dry.” As the name suggests, working “in the dry” entails dewatering the streambeds to achieve dry working conditions. Once dry conditions are established, MVP would excavate trenches through the streambeds to bury the pipeline beneath the surface. After placing the pipeline in the trenches, MVP would then backfill the trenches, attempt to restore the streambeds, and allow normal streamflow to resume.

All told, MVP expects the project to have unavoidable permanent and temporary impacts on the West Virginia ecosystem. The permanent effects would likely stem from restoring the pipeline’s right of way, constructing permanent access roads, and installing culverts along these roads to maintain stream connectivity. MVP represents that these impacts will be limited to less than a mile of stream channels and less than half-an-acre of wetland. The project will carry broader temporary impacts to almost four miles of stream channels and more than eleven-and-a-half acres of wetland due to excavation and backfilling of trenches as the pipeline crosses wetlands and streams.

Whether temporary or permanent, these activities threaten serious harm in the absence of proper environmental controls. Some stream crossings require in-stream blasting, which could “injure or kill aquatic organisms during blast-hole drilling operations, and temporarily increase stream turbidity.” J.A. 1295. The removal of crossing- construction infrastructure poses an additional concern that sedimentation may build up downstream through the introduction of fill material into the water. Unmitigated in-stream crossing activity could be quite environmentally dangerous given that “[s]edimentation is

responsible for nearly 40 percent of fish imperilment problems” by disrupting their reproduction and feeding habits. J.A. 1061.

B.

1.

The pipeline project’s success depends on its adherence to a complex regulatory scheme. The Natural Gas Act (“NGA”) delegates to the Federal Energy Regulatory Commission (“FERC”) final approval authority for the construction of natural gas pipelines by authorizing FERC to issue certificates of public convenience and necessity. 15 U.S.C. § 717f(c)(1)(A). FERC, in turn, will issue a certificate of public convenience and necessity only after ensuring that a proposed natural gas pipeline complies with both the NGA and the National Environmental Policy Act. See 42 U.S.C. §§ 4321 et seq.; 15 U.S.C. §§ 717 et seq. MVP procured a certificate of public convenience and necessity in October 2017. The certificate of public convenience and necessity was MVP’s initial hurdle, but it was not the only challenge.

2.

Under the NGA, MVP must also obtain “any permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law.” Sierra Club v. United States Dep’t of Interior, 899 F.3d 260, 267 (4th Cir. 2018) (internal citation and quotations omitted). Because MVP’s waterbody crossings involve the discharge of fill material into federal waters, the CWA requires MVP to obtain approval from the Army Corps of Engineers (“Army Corps”) before beginning construction. MVP may satisfy that requirement in one of two ways: by complying with an existing nationwide permit, “which

acts as a standing authorization for developers to undertake an entire category of activities deemed to create only minimal environmental impact,” or by acquiring an individual permit issued on a “case-by-case basis” after a “resource-intensive review.” Crutchfield v. Cnty. of Hanover, Va., 325 F.3d 211, 214 (4th Cir. 2003).

MVP initially attempted to gain approval to build its pipeline under the scope of the more generalized Nationwide Permit (“NWP”) 12. Sierra Club v. United States Army Corps of Eng’rs, 909 F.3d 635, 639–43 (4th Cir. 2018) (“Sierra Club I”). Those who wish to use NWP 12 for a potential project must submit pre-construction notifications to the Army Corps and apply for “verifications” that the project would meet the criteria for operation imposed by NWP 12. Id. at 641. A successful verification under NWP 12 would excuse a project from the more arduous individual CWA permitting process tailored to specific projects. See 33 C.F.R. §§ 330.1(b)–(d).

Free access — add to your briefcase to read the full text and ask questions with AI

Sierra Club v. West Virginia DEP, 64 F.4th 487 (4th Cir. 2023).

64 F.4th 487 (Sierra Club v. West Virginia DEP) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related