Sierra Club v. West Virginia DEP

64 F.4th 487
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 3, 2023
Docket22-1008
StatusPublished
Cited by5 cases

This text of 64 F.4th 487 (Sierra Club v. West Virginia DEP) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. West Virginia DEP, 64 F.4th 487 (4th Cir. 2023).

Opinion

USCA4 Appeal: 22-1008 Doc: 92 Filed: 04/03/2023 Pg: 1 of 34

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 22-1008

SIERRA CLUB; WEST VIRGINIA RIVERS COALITION; WEST VIRGINIA HIGHLANDS CONSERVANCY; INDIAN CREEK WATERSHED ASSOCIATION; APPALACHIAN VOICES; CHESAPEAKE CLIMATE ACTION NETWORK,

Petitioners,

v.

WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION; HAROLD WARD, in his official capacity as Secretary of the West Virginia Department of Environmental Protection,

Respondents,

MOUNTAIN VALLEY PIPELINE, LLC,

Intervenor.

On Petition for Review of a Certification Issuance of the West Virginia Department of Environmental Protection. (FERC Docket No. WQC-2021-005)

Argued: October 25, 2022 Decided: April 3, 2023

Before GREGORY, Chief Judge, WYNN, and THACKER, Circuit Judges.

Petition for review granted and certification vacated by published opinion. Chief Judge Gregory wrote the opinion, in which Judge Wynn and Judge Thacker joined. USCA4 Appeal: 22-1008 Doc: 92 Filed: 04/03/2023 Pg: 2 of 34

ARGUED: Derek Owen Teaney, APPALACHIAN MOUNTAIN ADVOCATES, INC., Lewisburg, West Virginia, for Petitioners. Lindsay Sara See, OFFICE OF THE ATTORNEY GENERAL OF WEST VIRGINIA, Charleston, West Virginia, for Respondents. George Peter Sibley, III, HUNTON ANDREWS KURTH, LLP, Richmond, Virginia, for Intervenor. ON BRIEF: Benjamin A. Luckett, Elizabeth A. Bower, APPALACHIAN MOUNTAIN ADVOCATES, INC., Lewisburg, West Virginia, for Petitioners. Patrick Morrisey, Attorney General, Michael R. Williams, Senior Deputy Solicitor General, Caleb A. Seckman, Assistant Attorney General, OFFICE OF THE ATTORNEY GENERAL OF WEST VIRGINIA, Charleston, West Virginia, for Respondents. J. Pierce Lamberson, Richmond, Virginia, Deidre G. Duncan, HUNTON ANDREWS KURTH LLP, Washington, D.C.; Robert G. McLusky, Jennifer L. Hughes, JACKSON KELLY PLLC, Charleston, West Virginia; Justin W. Curtis, AQUALAW PLC, Richmond, Virginia, for Intervenor.

2 USCA4 Appeal: 22-1008 Doc: 92 Filed: 04/03/2023 Pg: 3 of 34

GREGORY, Chief Judge:

This appeal is the latest installment in a series of challenges to Mountain Valley

Pipeline, LLC’s (“MVP”) plans to build a natural gas pipeline. Because it intends to

construct a portion of the pipeline in West Virginia, MVP obtained a Clean Water Act

(“CWA”) certification from the West Virginia Department of Environmental Protection

(the “Department”). The certification reflected the Department’s conclusion that MVP’s

activities during the pipeline’s construction would not violate the state’s water quality

standards. Disagreeing with that determination, landowners and members of various

environmental organizations in the state (collectively, “Petitioners”) have petitioned for

this Court’s review of the Department’s certification. We find the Department’s

justifications for its conclusions deficient and vacate the certification.

I.

A.

In 2018, MVP began building an approximately 304-mile, forty-two-inch diameter

pipeline. Spanning Virginia and West Virginia, the pipeline is intended to be an essential

conduit for delivering natural gas to markets in the mid-Atlantic, Southeastern, and

Appalachian regions of the United States. Approximately 197 miles of the pipeline will be

constructed in West Virginia, crossing many of the state’s aquatic resources along its path.

Pipelines can cross waterbodies in two ways. One construction method uses

trenchless crossings to conduct conventional boring under waterbodies, which do not

require digging and excavating the soil. MVP will use this method for a portion of its

3 USCA4 Appeal: 22-1008 Doc: 92 Filed: 04/03/2023 Pg: 4 of 34

crossings. For most crossings, though, MVP has chosen to trench through waterbodies

using open-cut crossings. The open-cut crossing method allows MVP to “work in the dry.”

As the name suggests, working “in the dry” entails dewatering the streambeds to achieve

dry working conditions. Once dry conditions are established, MVP would excavate

trenches through the streambeds to bury the pipeline beneath the surface. After placing the

pipeline in the trenches, MVP would then backfill the trenches, attempt to restore the

streambeds, and allow normal streamflow to resume.

All told, MVP expects the project to have unavoidable permanent and temporary

impacts on the West Virginia ecosystem. The permanent effects would likely stem from

restoring the pipeline’s right of way, constructing permanent access roads, and installing

culverts along these roads to maintain stream connectivity. MVP represents that these

impacts will be limited to less than a mile of stream channels and less than half-an-acre of

wetland. The project will carry broader temporary impacts to almost four miles of stream

channels and more than eleven-and-a-half acres of wetland due to excavation and

backfilling of trenches as the pipeline crosses wetlands and streams.

Whether temporary or permanent, these activities threaten serious harm in the

absence of proper environmental controls. Some stream crossings require in-stream

blasting, which could “injure or kill aquatic organisms during blast-hole drilling operations,

and temporarily increase stream turbidity.” J.A. 1295. The removal of crossing-

construction infrastructure poses an additional concern that sedimentation may build up

downstream through the introduction of fill material into the water. Unmitigated in-stream

crossing activity could be quite environmentally dangerous given that “[s]edimentation is

4 USCA4 Appeal: 22-1008 Doc: 92 Filed: 04/03/2023 Pg: 5 of 34

responsible for nearly 40 percent of fish imperilment problems” by disrupting their

reproduction and feeding habits. J.A. 1061.

B.

1.

The pipeline project’s success depends on its adherence to a complex regulatory

scheme. The Natural Gas Act (“NGA”) delegates to the Federal Energy Regulatory

Commission (“FERC”) final approval authority for the construction of natural gas pipelines

by authorizing FERC to issue certificates of public convenience and necessity. 15 U.S.C.

§ 717f(c)(1)(A). FERC, in turn, will issue a certificate of public convenience and necessity

only after ensuring that a proposed natural gas pipeline complies with both the NGA and

the National Environmental Policy Act. See 42 U.S.C. §§ 4321 et seq.; 15 U.S.C. §§ 717

et seq. MVP procured a certificate of public convenience and necessity in October 2017.

The certificate of public convenience and necessity was MVP’s initial hurdle, but it was

not the only challenge.

2.

Under the NGA, MVP must also obtain “any permits, special use authorizations,

certifications, opinions, or other approvals as may be required under Federal law.” Sierra

Club v. United States Dep’t of Interior, 899 F.3d 260, 267 (4th Cir. 2018) (internal citation

and quotations omitted). Because MVP’s waterbody crossings involve the discharge of fill

material into federal waters, the CWA requires MVP to obtain approval from the Army

Corps of Engineers (“Army Corps”) before beginning construction. MVP may satisfy that

requirement in one of two ways: by complying with an existing nationwide permit, “which

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
64 F.4th 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-west-virginia-dep-ca4-2023.