Appalachian Voices v. FERC

139 F.4th 903
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 6, 2025
Docket24-1094
StatusPublished
Cited by1 cases

This text of 139 F.4th 903 (Appalachian Voices v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Voices v. FERC, 139 F.4th 903 (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued February 20, 2025 Decided June 6, 2025

No. 24-1094

APPALACHIAN VOICES, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

MOUNTAIN VALLEY PIPELINE, LLC AND PUBLIC SERVICE COMPANY OF NORTH CAROLINA, INC., D/B/A DOMINION ENERGY NORTH CAROLINA, INTERVENORS

Consolidated with 24-1150

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Benjamin A. Luckett argued the cause for petitioners. With him on the briefs were Elizabeth F. Benson, Gillian Giannetti, and Caroline Reiser. 2 Jason T. Perkins, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Jeremy C. Marwell argued the cause for intervenors in support of respondent. With him on the joint brief were Charlotte Taylor, James Olson, Misha Tseytlin, James T. Dawson, Garrett T. Meisman, and William Lavarco.

Before: SRINIVASAN, Chief Judge, HENDERSON, Circuit Judge, and EDWARDS, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge EDWARDS.

Concurring opinion filed by Circuit Judge HENDERSON.

EDWARDS, Senior Circuit Judge: This case concerns a decision of the Federal Energy Regulatory Commission (“FERC” or “Commission”) finding good cause to extend a construction deadline it had previously set for Mountain Valley Pipeline, LLC (“MVP”) to complete the MVP Southgate Project (“Southgate Project” or “Southgate”). The Commission issued a certificate of public convenience and necessity authorizing the Southgate Project in June 2020. The Commission exercised its discretion to set a construction completion deadline of June 18, 2023. It recognized that Southgate functioned as an extension of the Mountain Valley Pipeline Mainline (“Mainline”), so it conditioned authorization to start Southgate construction on MVP obtaining all required federal permits and authorizations for the Mainline. However, permitting issues for the Mainline were not resolved until June 3, 2023, and the Commission did not authorize resumption of Mainline construction until June 28, 2023. By then, 3 Southgate’s initial construction deadline of June 18, 2023, had already passed.

Shortly before the deadline, MVP requested an extension of time to complete construction. The Commission granted the request, finding that MVP had adequately demonstrated good cause. Specifically, MVP had made a good faith effort to meet the Southgate construction deadline but encountered unavoidable circumstances – i.e., Mainline permitting delays – that prevented it from doing so. The Commission also explained that its prior analysis of market need and environmental impacts for the Southgate Project remained valid and, thus, declined to revisit them.

Petitioners – eight environmental organizations – seek review of the Commission’s decision. They argue that the Commission’s finding of good cause to extend the time to complete construction and its refusal to revisit its prior assessments of market need and environmental impacts were arbitrary and capricious.

We deny the petitions for review. First, we hold that the Commission reasonably found that MVP had satisfied the good cause standard in seeking an extension. As the Commission explained, permitting and litigation delays with the Mainline prevented MVP from proceeding with Southgate construction. Thus, by focusing their efforts on securing authorization for the Mainline, which had to come first, MVP made a good faith effort to meet the original Southgate deadline.

Second, we hold that the Commission’s decision not to revisit its prior findings on market need and environmental impacts was adequately explained. The Commission generally declines to reevaluate issues that were already addressed during the certification process. The Commission “has leeway, 4 however, to revisit prior market-need or environmental findings when new circumstances render such findings stale or out of date.” Sierra Club v. FERC, 97 F.4th 16, 26 (D.C. Cir. 2024). On the record before it, the Commission reasonably concluded that the information presented by petitioners did not amount to significant changes in circumstances that merited renewed economic or environmental analysis. It was also reasonable for the Commission to wait for MVP to file a certificate amendment application before addressing any potential changes to Southgate, and to conduct further economic and environmental analysis, as necessary, when reviewing that application.

I. BACKGROUND

A. Statutory and Regulatory Background

The Natural Gas Act (“NGA”), 15 U.S.C. § 717 et seq., empowers the Commission to regulate the interstate transportation and sale of natural gas. A company seeking to construct new natural gas pipeline facilities must receive authorization from the Commission by applying for a certificate of “public convenience and necessity.” 15 U.S.C. § 717f(c)(1)(A). The Commission will issue a certificate if it finds that (1) “the applicant is able and willing properly to do the acts and to perform the service proposed,” in conformance with the NGA and the Commission’s “requirements, rules, and regulations”; and (2) the proposed project “is or will be required by the present or future public convenience and necessity.” Id. § 717f(e). Prior to issuing a certificate, the Commission “undertakes an extensive analysis of market need, the public interest, and any environmental effects of the proposed project.” Sierra Club, 97 F.4th at 20; see also 15 U.S.C. § 717f(e). The project is also examined under the National Environmental Policy Act (“NEPA”) through the 5 issuance of either an environmental assessment or an environmental impact statement (“EIS”). See Sierra Club, 97 F.4th at 20; 42 U.S.C. § 4321 et seq.

The NGA does not require the Commission to set deadlines for the completion of construction projects. However, the Commission has the authority to “perform any and all acts” to “prescribe, issue, make, amend, and rescind” a certificate order, “as [the agency] may find necessary or appropriate to carry out the [NGA].” 15 U.S.C. § 717o. And under its own regulation, “[a]ny authorized construction [or] extension . . . shall be completed and made available for service . . . within [a] period of time to be specified by the Commission in each order.” 18 C.F.R. § 157.20(b) (2024) (cleaned up).

The Commission may grant extensions of time for project completion “for good cause, upon a motion made before” the operative deadline. Id. § 385.2008(a). “Good cause” is the only showing that a certificate holder is required to make if the extension request is filed “within a timeframe during which the environmental and other public interest findings underlying the Commission’s authorization [of the project] can be expected to remain valid.” Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 15 (2020). An extension of time is considered an amendment of the project-completion deadline in the certificate order and thus pursued as part of the Commission’s broad authority under § 717o of the NGA. See 15 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
139 F.4th 903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-voices-v-ferc-cadc-2025.