Transcontinental Gas Pipe Line Company, LLC v. Gail Brandon Cochran

910 F.3d 1130
CourtCourt of Appeals for the Eleventh Circuit
DecidedDecember 6, 2018
Docket16-17503
StatusPublished
Cited by74 cases

This text of 910 F.3d 1130 (Transcontinental Gas Pipe Line Company, LLC v. Gail Brandon Cochran) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Company, LLC v. Gail Brandon Cochran, 910 F.3d 1130 (11th Cir. 2018).

Opinion

JULIE CARNES, Circuit Judge:

*1141 Transcontinental Gas Pipe Line Company, LLC ("Transcontinental") brought these consolidated condemnation proceedings against several property owners in Northwest Georgia (collectively, "Defendants") in order to obtain an easement for the construction of a natural-gas pipeline. The district court granted summary judgment in favor of Transcontinental on the issue of whether it had a right to condemn certain portions of Defendants' properties under Section 7(h) of the Natural Gas Act, 15 U.S.C. § 717f(h). The district court also issued a preliminary injunction allowing Transcontinental to immediately enter Defendants' properties and begin construction. As a condition of such access, the district court required Transcontinental to post a surety bond in an amount equal to twice the appraised value of Defendants' properties. Defendants challenge each of those rulings on appeal. After careful review, and with the benefit of oral argument, we affirm.

BACKGROUND

I. Factual Background

Transcontinental is a natural-gas company that transports natural gas back and forth between the Gulf Coast and the New York City metropolitan area via pipeline. 1 Along the route, Transcontinental provides natural gas to customers throughout the East Coast.

On March 19, 2015, Transcontinental applied to the Federal Energy Regulatory Commission ("FERC") for a certificate of public convenience and necessity authorizing it to construct a new natural-gas pipeline in Northwest Georgia, as well as related facilities in Georgia, North Carolina, and Virginia. The new 115-mile lateral pipeline would run from a compressor station on Transcontinental's mainline in Coweta County, Georgia, to meter stations in Murray County, near the city of Dalton. The purpose of the project was to enable Transcontinental to transport natural gas extracted from the Marcellus shale and other supply basins in the northeastern United States to customers in the Southeast and Gulf Coast. Transcontinental would receive the gas at a point on its mainline in Mercer County, New Jersey, and deliver it to an interconnection with another company's pipeline in Mississippi. Along the way, Transcontinental would provide natural gas to its customers, including, through the new lateral pipeline, *1142 communities in Northwest Georgia. This project, which included both the new lateral pipeline and the related facilities on Transcontinental's mainline, was called the Dalton Expansion Project.

A. Pre-application Preparations for the Dalton Expansion Project

Prior to its March 2015 application, Transcontinental held an "open season" in May and June of 2012, through which it solicited bids for the natural-gas transportation services it planned to provide if the Dalton Expansion Project were ultimately approved by FERC. 2 As a result of those solicitations, Transcontinental executed binding precedent agreements with Atlanta Gas Light Company and Oglethorpe Power Corporation for all of the natural-gas capacity associated with the Dalton Expansion Project. A precedent agreement is "a long-term contract subscribing to expanded natural gas capacity." Myersville Citizens for a Rural Cmty., Inc. v. FERC , 783 F.3d 1301 , 1310 (D.C. Cir. 2015).

As early as April of 2013, Transcontinental began contacting landowners in the general area where it planned to place the pipeline, and requested those owners' permission to access their properties for the purpose of surveying the land. These surveys were obviously necessary to help Transcontinental and FERC decide on the most appropriate route for the pipeline.

In the spring of 2014, through written communications, personal contacts, and by other means, Transcontinental began notifying those landowners who were likely to be affected by construction of the pipeline. In addition, from June through September of 2014, as part of FERC's pre-filing environmental review of the proposed project, FERC staff participated in open houses sponsored by Transcontinental in several cities along the pipeline's proposed route.

In October 2014, FERC published a notice in the Federal Register announcing that FERC environmental staff would conduct "scoping" meetings in three Georgia cities in November 2014, where members of the public could voice any concerns about the environmental impact of the project. 3 Notice of Intent to Prepare an Environmental Assessment for the Planned Dalton Expansion Project, 79 Fed. Reg. 64,186 (Oct. 28, 2014). This notice was also mailed to landowners affected by the proposed pipeline. Id. at 64 ,187 -88. Shortly after those scoping meetings, FERC published a second notice in the Federal Register, which, like the first notice, was also mailed to landowners affected by the project. Supplemental Notice of Intent to Prepare an Environmental Assessment for the Planned Dalton Expansion Project, 79 Fed. Reg. 69,455 (Nov. 21, 2014). Both notices informed the landowners that, if the project was approved, Transcontinental *1143 would have the right of eminent domain and, if an agreement could not be reached to purchase an easement on their properties, Transcontinental could initiate condemnation proceedings. Supplemental Notice of Intent, 79 Fed. Reg. at 69,455 ; Notice of Intent, 79 Fed. Reg. at 64,187.

The landowners were also informed that they could intervene in Transcontinental's FERC proceedings once Transcontinental filed its application. Supplemental Notice of Intent, 79 Fed. Reg. at 69,457 ; Notice of Intent, 79 Fed. Reg. at 64,188. In fact, after Transcontinental filed its application in March 2015, several landowners-including some of the appellants here-filed motions to intervene in Transcontinental's FERC proceedings, which FERC granted.

B. Transcontinental's Application

As noted, Transcontinental filed its application for a certificate of public convenience and necessity on March 19, 2015. As part of its application, Transcontinental was required to submit alignment sheets detailing the pipeline's proposed route. See 18 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cross v. State
2024 MT 303 (Montana Supreme Court, 2024)
State of Georgia v. President of the United States
46 F.4th 1283 (Eleventh Circuit, 2022)
Valentin Belevich v. Klavdia Thomas
17 F.4th 1048 (Eleventh Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
910 F.3d 1130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-company-llc-v-gail-brandon-cochran-ca11-2018.