B&J Oil & Gas v. Federal Energy Regulatory Commission

353 F.3d 71, 359 U.S. App. D.C. 214, 158 Oil & Gas Rep. 155, 2004 U.S. App. LEXIS 349, 2004 WL 51111
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 13, 2004
Docket02-1306
StatusPublished
Cited by30 cases

This text of 353 F.3d 71 (B&J Oil & Gas v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B&J Oil & Gas v. Federal Energy Regulatory Commission, 353 F.3d 71, 359 U.S. App. D.C. 214, 158 Oil & Gas Rep. 155, 2004 U.S. App. LEXIS 349, 2004 WL 51111 (D.C. Cir. 2004).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

*73 TATEL, Circuit Judge:

In this case, we consider an energy producer’s challenge to the Federal Energy Regulatory Commission’s decision to permit a neighboring natural gas pipeline operator to expand an underground gas storage facility onto the producer’s property. Although we reject FERC’s argument that the producer lacks standing to pursue this challenge, because FERC’s orders are supported by substantial evidence and are neither arbitrary nor capricious, we deny the petition for review.

I.

Under section 7(c) of the Natural Gas Act (NGA), natural gas companies seeking to construct new gas transportation or storage facilities, or to expand existing ones, must obtain a certificate of “public convenience and necessity” from the Federal Energy Regulatory Commission. See 15 U.S.C. § 717f(e)(l)(A) (2000) (“No natural-gas company ... shall engage in the transportation or sale of natural gas ..., or undertake the construction or extension of any facilities therefor ..., unless there is in force ... a certifícate of public convenience and necessity issued by the Commission authorizing such acts or operations .... ”); Schneidewind v. ANR Pipeline Co., 485 U.S. 293, 295 n. 1, 108 S.Ct. 1145, 1148 n.1, 99 L.Ed.2d 316 (1988) (stating that “transportation” within the meaning of the NGA includes storage). Such certificates enable gas companies unable to purchase the property rights needed to construct or operate their certificated facilities to acquire the property from unwilling owners through eminent domain. 15 U.S.C. § 717f(h).

Dominion Transmission, Inc., intervenor in this case, owns and operates an interstate gas transmission system that transports and stores natural gas for customers in several east coast states. As part of this system, Dominion runs an underground storage facility in central West Virginia called the Fink-Kennedy/Lost Creek Storage Reservoir. FERC’s predecessor, the Federal Power Commission, certificated the Fink Reservoir in 1956. See Dominion Transmission, Inc., 97 F.E.R.C. ¶ 61,344, 62,598, 2001 WL 1638754 (2001) (relying on Hope Natural Gas Co., 16 F.P.C. ¶ 955, 1956 WL 4364 (1956)). The Fink Reservoir spans nearly 50,000 acres within the Gantz Formation, a geologic formation located approximately 1600 to 2600 feet underground. According to Dominion, the Fink Reservoir is one of the country’s largest natural gas storage facilities.

Petitioner B&J Oil and Gas operates fourteen oil and gas wells, ten of which are located within the Gantz Formation adjacent to the current boundary of Dominion’s Fink storage field. In these proceedings, B&J acts “on behalf of the working interest owners and royalty interest owners that it represents as the operator of [these] fourteen wells.” Pet’r’s Br. at 2.

In February 2001, Dominion asked FERC to revise the Fink Reservoir’s certificated boundary. In its application filed pursuant to NGA section 7(c), Dominion asserted that data acquired and analyses performed after the field’s initial certification indicated that gas could easily migrate out of the reservoir area and that third-party wells located outside the current boundary likely were “producing,” i.e., extracting, gas from Dominion’s storage field. To prevent this loss, Dominion asked FERC to amend the Fink Reservoir’s certificated boundary to encompass an additional 3063 acres, which would enlarge the storage area to the reservoir’s actual geologic border. This proposed expansion would incorporate neighboring private property, including B&J’s.

*74 To protect its property interests, B&J intervened and objected to Dominion’s application. Claiming that Dominion had failed to present sufficient engineering and geologic information to justify boundary expansion, B&J submitted its own expert report challenging the accuracy of some of Dominion’s data. Staff from FERC’s Office of Energy Projects subsequently sent “deficiency letters” to both Dominion and B&J requesting more information about their filings. In response, Dominion submitted additional materials, requesting confidential treatment for five documents on the ground that they contained sensitive or proprietary information. B&J promptly filed a Freedom of Information Act request to obtain one of the five as-sertedly privileged documents, explaining that the other four appeared on a publicly accessible FERC information management system. After determining that it had mistakenly posted Dominion’s confidential documents, FERC removed the materials from its information system, ordered parties who had downloaded them to destroy the documents and not to use them in any way, and denied B&J’s FOIA application. See Dominion Transmission, Inc., 96 F.E.R.C. ¶ 61,238, 61,955, 2001 WL 995379 (2001) (document destruction order); Dominion Transmission, Inc., 97 F.E.R.C. ¶ 61,120, 61,584, 2001 WL 1326470 (2001) (denying rehearing of the document destruction order and noting that the Commission’s Office of External Affairs had denied B&J’s FOIA request). Concluding that the public record contained sufficient information for it to decide Dominion’s boundary revision application, FERC also rejected B&J’s request to stay the Dominion certificate proceedings until after the agency resolved B&J’s FOIA appeal, see Dominion, 97 F.E.R.C. at 61,584, and later affirmed the denial of B&J’s FOIA application, see Dominion Transmission, Inc., 100 F.E.R.C. ¶ 61,168, 61,601 n. 3, 2002 WL 31975331 (2002).

In December 2001, FERC approved Dominion’s application to expand the Fink Reservoir. Dominion, 97 F.E.R.C. at 62,-598. Relying only on publicly available information, FERC found that the Gantz Formation was larger than the Fink Reservoir’s currently certificated boundary and that Dominion storage gas was in fact migrating toward B&J’s wells. Id. at 62,-601. FERC thus found it “in the public convenience and necessity to expand the storage boundary for the Fink Reservoir as proposed, in order to maintain the operational integrity of the storage field and to enable Dominion to continue to provide reliable natural gas storage service.” Id. Balancing the need to ensure the storage field’s integrity against B&J’s interests, FERC concluded that preventing gas migration outweighed B&J’s property interests because B&J would be compensated for the loss of its oil and gas wells through eminent domain proceedings. Id. In addition, the Commission rejected B&J’s proposal to allow the company to continue producing oil and return any Dominion storage gas that it extracted. According to the Commission, permitting third-party drilling in the area could interfere with storage operations and encourage other producers to poach Dominion gas. Id. at 62,601-02. In a second order, FERC denied B&J’s petition for rehearing. Dominion, 100 F.E.R.C. at 61,603.

B&J now petitions for review, challenging both FERC orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healthy Gulf v. FERC
132 F.4th 544 (D.C. Circuit, 2025)
Stingray Pipeline Company, L.L.C. v. FERC
124 F.4th 19 (D.C. Circuit, 2024)
Childrens Health Defense v. FCC
25 F.4th 1045 (D.C. Circuit, 2022)
Environmental Defense Fund v. FERC
2 F.4th 953 (D.C. Circuit, 2021)
City of Oberlin, Ohio v. FERC
937 F.3d 599 (D.C. Circuit, 2019)
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357 (D.C. Circuit, 2017)
Standing Rock Sioux Tribe v. United States Army Corps of Engineers
255 F. Supp. 3d 101 (District of Columbia, 2017)
Colorado Interstate Gas Co. v. Wright
707 F. Supp. 2d 1169 (D. Kansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
353 F.3d 71, 359 U.S. App. D.C. 214, 158 Oil & Gas Rep. 155, 2004 U.S. App. LEXIS 349, 2004 WL 51111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bj-oil-gas-v-federal-energy-regulatory-commission-cadc-2004.