Environmental Defense Fund v. FERC

2 F.4th 953
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 22, 2021
Docket20-1016
StatusPublished
Cited by20 cases

This text of 2 F.4th 953 (Environmental Defense Fund v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund v. FERC, 2 F.4th 953 (D.C. Cir. 2021).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 8, 2021 Decided June 22, 2021

No. 20-1016

ENVIRONMENTAL DEFENSE FUND, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

SPIRE MISSOURI INC. AND SPIRE STL PIPELINE LLC, INTERVENORS

Consolidated with 20-1017

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Natalie M. Karas argued the cause for petitioner Environmental Defense Fund. With her on the briefs were Erin Murphy, Jason T. Gray, Kathleen L. Mazure, Matthew L. Bly, and Sean H. Donahue.

Henry B. Robertson argued the cause and filed the briefs for petitioner Juli Steck. 2 Jennifer Danis and Edward Lloyd were on the brief for amicus curiae Dr. Susan Tierney in support of petitioners.

Randy M. Stutz was on the brief for amicus curiae the American Antitrust Institute in support of petitioners.

Anand R. Viswanathan, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were David L. Morenoff, Acting General Counsel, and Robert H. Solomon, Solicitor.

Jonathan S. Franklin argued the cause for intervenors Spire STL Pipeline LLC and Spire Missouri Inc. in support of respondent. With him on the brief were Christopher J. Barr, Jessica R. Rogers, Matthew J. Aplington, Thomas E. Hirsch III, David T. Kearns, Daniel Archuleta, and Sean P. Jamieson.

Paul Korman, Michael R. Pincus, and Michael Diamond were on the brief for amicus curiae Interstate Natural Gas Association of America in support of respondent.

Before: TATEL and MILLETT, Circuit Judges, and EDWARDS, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge EDWARDS.

EDWARDS, Senior Circuit Judge: In the action leading to this petition for review, the Federal Energy Regulatory Commission (the “Commission” or “FERC”) issued a certificate of public convenience and necessity (“Certificate”) under section 7(c) of the Natural Gas Act, 15 U.S.C. § 717f(c)(1)(A), to Intervenor-Respondent Spire STL Pipeline LLC (“Spire STL”) to construct a new natural gas pipeline in the St. Louis area. The Commission may issue such a 3 Certificate only if it finds that construction of the new pipeline “is or will be required by the present or future public convenience and necessity.” Id. § 717f(e).

Pursuant to the Commission’s “Certificate Policy Statement,” Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227 (Sept. 15, 1999), clarified, 90 FERC ¶ 61,128 (Feb. 9, 2000), further clarified, 92 FERC ¶ 61,094 (July 28, 2000), FERC first considers whether there is a market need for the proposed project. If there is a need for the pipeline, FERC then determines whether there will be adverse impacts on “existing customers of the pipeline proposing the project, existing pipelines in the market and their captive customers, or landowners and communities affected by the route of the new pipeline.” Id. at 61,745. If adverse impacts on these stakeholders will result, the Commission “balanc[es] the evidence of public benefits to be achieved against the residual adverse effects.” Id. In analyzing the need for a particular project, the Certificate Policy Statement makes it clear that the Commission will “consider all relevant factors.” See id. at 61,747 (emphasis added).

The issue in this case arose in 2016, when Spire STL announced its intent to build a pipeline in the St. Louis metropolitan area. In August of that year, Spire STL held an “open season” during which it invited natural gas “shippers” to enter into preconstruction contracts, also known as “precedent agreements,” for the natural gas the pipeline would transport. But no shippers committed to the project during the open season. Instead, after the open season finished without any takers, Spire STL privately entered into a precedent agreement with one of its affiliates, Laclede Gas Company – now known as Intervenor-Respondent Spire Missouri Inc. (“Spire 4 Missouri”) – for just 87.5 percent of the pipeline’s projected capacity.

In January 2017, Spire STL applied to the Commission for a Certificate. It conceded that the proposed pipeline was not being built to serve new load, as natural gas demand in the St. Louis area is projected to stay relatively flat for the foreseeable future. Rather, Spire STL claimed that the pipeline would result in other benefits, such as enhancing reliability and supply security, providing access to new sources of natural gas supply, and eliminating reliance on propane “peak-shaving” during periods of high demand. As evidence of need, Spire STL principally relied on its precedent agreement with Spire Missouri. In September 2017, the Commission – pursuant to its obligations under the National Environmental Policy Act (“NEPA”) – released an Environmental Assessment (“EA”) for construction and operation of the proposed pipeline, finding that they would have no significant environmental impact.

Petitioner Environmental Defense Fund (“EDF”), along with several other parties, challenged Spire STL’s Certificate application. EDF contended, inter alia, that the precedent agreement between Spire STL and Spire Missouri should have only limited probative value in FERC’s assessment of Spire STL’s application because the two companies were corporate affiliates. In addition, Petitioner Juli Steck, then known as Juli Viel, contested the efficacy of the EA.

On August 3, 2018, in an Order Issuing Certificates (“Certificate Order”), FERC granted the authorizations for the new pipeline. See Joint Appendix (“J.A.”) 932. FERC’s decision acknowledged that the pipeline was not meant to serve new load demand. Nevertheless, FERC rejected arguments that a market study should be undertaken to establish the need for the project. Rather, the Commission’s decision principally 5 focused on the precedent agreement between Spire STL and Spire Missouri in finding that there was market need for the project. And the Commission stated that it would not “second guess” Spire Missouri’s purported “business decision” in entering into the precedent agreement with Spire STL, even though the shipper and the pipeline were affiliates. J.A. 968. In November 2019, by a 2-1 vote, FERC denied requests for rehearing filed by EDF and Steck. These two parties now seek review in this court.

EDF asserts that the Commission’s decision to award a Certificate to Spire STL was arbitrary and capricious because the Commission uncritically and exclusively relied on the affiliated precedent agreement to find need and because the Commission failed to sufficiently justify its conclusion that the new pipeline’s benefits would outweigh its adverse effects. Steck, in turn, renews many of her challenges to the Commission’s environmental analysis, including its EA.

For the reasons explained below, we find that Petitioner Steck lacks standing to pursue her claims. However, we find no jurisdictional infirmities in EDF’s petition for review. On the merits, we agree with EDF that the Commission’s refusal to seriously engage with nonfrivolous arguments challenging the probative weight of the affiliated precedent agreement under the circumstances of this case did not evince reasoned and principled decisionmaking. In addition, we find that the Commission ignored record evidence of self-dealing and failed to seriously and thoroughly conduct the interest-balancing required by its own Certificate Policy Statement. Therefore, FERC’s Certificate Order and Order on Rehearing do not survive scrutiny under the applicable arbitrary and capricious standard of review. See Minisink Residents for Env’t Pres. & Safety v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of Duke Energy Ohio, Inc.
2025 Ohio 2082 (Ohio Supreme Court, 2025)
Healthy Gulf v. FERC
132 F.4th 544 (D.C. Circuit, 2025)
American Whitewater v. FERC
125 F.4th 1139 (D.C. Circuit, 2025)
National Wildlife Federation v. Lohr
District of Columbia, 2024
City of Port Isabel v. FERC
111 F.4th 1198 (D.C. Circuit, 2024)
New Jersey Conservation Foundation v. FERC
111 F.4th 42 (D.C. Circuit, 2024)
Food & Water Watch v. FERC
104 F.4th 336 (D.C. Circuit, 2024)
Ninestar Corp. v. United States
687 F. Supp. 3d 1308 (Court of International Trade, 2024)
Alliance Hippocratic Medicine v. FDA
78 F.4th 210 (Fifth Circuit, 2023)
American Hospital Association
District of Columbia, 2022
Kentucky Municipal Energy Agency v. FERC
45 F.4th 162 (D.C. Circuit, 2022)
Delaware Riverkeeper Network v. FERC
45 F.4th 104 (D.C. Circuit, 2022)
City of Oberlin, Ohio v. FERC
39 F.4th 719 (D.C. Circuit, 2022)
Sierra Club v. FERC
38 F.4th 220 (D.C. Circuit, 2022)
Friends of the Earth v. Haaland
District of Columbia, 2022

Cite This Page — Counsel Stack

Bluebook (online)
2 F.4th 953, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-v-ferc-cadc-2021.