Delaware Riverkeeper Network v. FERC

45 F.4th 104
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 2, 2022
Docket20-1206
StatusPublished
Cited by9 cases

This text of 45 F.4th 104 (Delaware Riverkeeper Network v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware Riverkeeper Network v. FERC, 45 F.4th 104 (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 24, 2021 Decided August 2, 2022

No. 20-1206

DELAWARE RIVERKEEPER NETWORK AND MAYA VAN ROSSUM, THE DELAWARE RIVERKEEPER, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

ADELPHIA GATEWAY, LLC, INTERVENOR

Consolidated with 20-1338

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Kacy C. Manahan argued the causes for petitioners Delaware Riverkeeper Network, et al. Douglas R. Blazey argued the causes for petitioner West Rockhill Township. With them on the joint briefs was John R. Embick.

Jared B. Fish, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on 2 the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Jeremy C. Marwell argued the cause for intervenor. With him on the brief were James D. Seegers, Suzanne E. Clevenger, Matthew X. Etchemendy, and James T. Dawson.

Before: ROGERS and JACKSON*, Circuit Judges, and SILBERMAN, Senior Circuit Judge.

Opinion for the Court by Circuit Judge ROGERS.

ROGERS, Circuit Judge: Adelphia Gateway, LLC, applied to the Federal Energy Regulatory Commission for a certificate of public convenience and necessity to acquire an existing pipeline system in Pennsylvania and Delaware. It also sought authorization to construct two short lateral pipeline segments extending from the existing pipeline infrastructure it would acquire. One of these, the “Parkway Lateral,” would consist of a 0.3-mile lateral to an existing meter station that provides natural gas service to several transmission companies and power plants. Adelphia also sought approval to construct facilities necessary to operate the pipeline, including the Quakertown Compressor Station in Bucks County, Pennsylvania. Together, these acquisitions and improvements would comprise the Adelphia Gateway Project (“the Project”).

The Commission conducted an Environmental Assessment analyzing the Project’s safety and its effects on air quality, noise, and residential lands near the pipeline. The Commission acknowledged that the Project “would contribute

* Circuit Judge Jackson, now Justice Jackson, was a member of the panel at the time the case was argued but did not participate in the preparation of this opinion. 3 to global increases in [greenhouse-gas] levels,” but did not calculate “the downstream [greenhouse-gas] emissions of the southern portion of the Project,” because “the downstream emissions from the remainder of the southern portion of the Project are not designated to a specific user, and the end use of the natural gas is not identified by Adelphia.” Environmental Assessment at 132. The Commission also declined to consider the upstream impacts of the Project on demand for natural gas, which it found to be “outside the scope of this [Environmental Assessment].” Id. The Commission considered and rejected several alternatives to the Project, and specifically to the location of the Quakertown Compressor Station. Id. at 183–84. The Environmental Assessment concluded that “if Adelphia constructs and operates the proposed facilities in accordance with its application and supplements and [the Commission’s] recommended mitigation measures,” the project would have “no significant impact” on the environment. Id. at 194. Petitioners filed comments with the Commission challenging the adequacy of the Environmental Assessment and Adelphia’s application for a certificate.

The Commission issued a certificate of public convenience and necessity for the Project, finding that Adelphia had demonstrated market need for the Project. It relied largely on four precedent agreements Adelphia had entered for the majority of the Project’s capacity. It rejected commenters’ arguments that there was insufficient demand in the region to support the Project, concluding that commenters had provided “no compelling evidence of overbuilding in the face of compelling evidence of need in the form of substantial customer support.” Certificate Order at 15. The Commission concluded that “the benefits that the Adelphia Gateway Project will provide to the market outweigh any adverse effects on existing shippers, other pipelines and their captive customers, and on landowners and surrounding communities.” Id. at 17. 4 One member of the Commission dissented. Requests for rehearing and a stay of the Certificate Order were denied, and the Commission reaffirmed its finding of market need, its balancing of adverse impacts and public benefits, and its environmental analysis.

I.

In their joint brief, petitioners challenge: (1) the Commission’s finding of market need for the Project under the Natural Gas Act; (2) the sufficiency of the Commission’s environmental review under the National Environmental Policy Act (“NEPA”); and (3) the constitutionality of the Commission’s purported preemption of state and local authorities’ ability to protect public health. The Court is persuaded that the Commission did not act arbitrarily and capriciously.

This court reviews the Commission’s orders, “including those approving certificate applications, under the familiar arbitrary and capricious standard” of the Administrative Procedure Act (“APA”). Minisink Residents for Env’t Pres. & Safety v. FERC, 762 F.3d 97, 105–06 (D.C. Cir. 2014); see also 5 U.S.C. § 706(2)(A). An agency’s compliance with NEPA’s requirements is also reviewed under the APA’s arbitrary and capricious standard. Sierra Club v. FERC, 867 F.3d 1357, 1367 (D.C. Cir. 2017) (“Sabal Trail”). Thus, with respect to petitioners’ challenges under both the Natural Gas Act and NEPA, the question is whether the Commission’s Certificate and Rehearing Orders were “based on a consideration of the relevant factors and whether there has been a clear error of judgment.” Minisink, 762 F.3d at 106 (quoting ExxonMobil Gas Mktg. Co. v. FERC, 297 F.3d 1071, 1083 (D.C. Cir. 2002)). The agency’s decision must “contain ‘sufficient discussion of the relevant issues and opposing viewpoints,’” 5 Sabal Trail, 867 F.3d at 1368 (quoting Nevada v. Dep’t of Energy, 457 F.3d 78, 93 (D.C. Cir. 2006)), and “demonstrate ‘reasoned decisionmaking,’” id. (quoting Del. Riverkeeper Network v. FERC, 753 F.3d 1304, 1313 (D.C. Cir. 2014)).

To the extent petitioners challenge the Commission’s factual findings, this court reviews those findings to ensure they are supported by substantial evidence in the record. Myersville Citizens for a Rural Cmty. v. FERC, 783 F.3d 1301, 1309 (D.C. Cir. 2015). Substantial evidence means “such relevant evidence as a reasonable mind might accept as adequate to support a conclusion,” id. (quoting Colo. Interstate Gas Co. v. FERC, 599 F.3d 698, 704 (D.C. Cir. 2010)), and this standard “requires more than a scintilla, but can be satisfied by something less than a preponderance of the evidence,” id. (quoting Minisink, 762 F.3d at 108).

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Port Isabel v. FERC
111 F.4th 1198 (D.C. Circuit, 2024)
Healthy Gulf v. FERC
107 F.4th 1033 (D.C. Circuit, 2024)
Food & Water Watch v. FERC
104 F.4th 336 (D.C. Circuit, 2024)
Eagle County, Colorado v. STB
82 F.4th 1152 (D.C. Circuit, 2023)
State of Missouri v. U.S. Department of Interior
73 F.4th 570 (Eighth Circuit, 2023)
Center for Biological Diversity v. FERC
67 F.4th 1176 (D.C. Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
45 F.4th 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-riverkeeper-network-v-ferc-cadc-2022.