Healthy Gulf v. FERC

107 F.4th 1033
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 16, 2024
Docket23-1069
StatusPublished
Cited by2 cases

This text of 107 F.4th 1033 (Healthy Gulf v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Healthy Gulf v. FERC, 107 F.4th 1033 (D.C. Cir. 2024).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued February 12, 2024 Decided July 16, 2024

No. 23-1069

HEALTHY GULF, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

COMMONWEALTH LNG, LLC, INTERVENOR

Consolidated with 23-1071

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Nathan Matthews argued the cause for petitioners. With him on the briefs were Rebecca McCreary, Caroline Reiser, Morgan Johnson, and Jared E. Knicley.

Susanna Y. Chu, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the 2

brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

John Longstreth argued the cause for intervenor in support of respondent. With him on the brief were David L. Wochner and Timothy J. Furdyna.

Before: HENDERSON, PAN, and GARCIA, Circuit Judges.

Opinion for the Court filed by Circuit Judge GARCIA.

GARCIA, Circuit Judge: Healthy Gulf and four other environmental groups petition for review of the Federal Energy Regulatory Commission’s decision to authorize the construction and operation of liquefied natural gas facilities in southwestern Louisiana. They argue that the Commission did not properly address certain National Environmental Policy Act and Natural Gas Act requirements. We agree, in part. The Commission inadequately explained its failure to determine the environmental significance of the project’s greenhouse gas emissions, and it failed to adequately assess the cumulative effects of the project’s nitrogen dioxide emissions. The Commission did, however, satisfy its obligation to consider alternatives to the project. We therefore grant the petitions in part, deny them in part, and remand for further consideration. I A The Commission exercises delegated authority under Section 3 of the Natural Gas Act (“NGA”) to “approve or deny an application for the siting, construction, expansion, or operation” of facilities used to export liquefied natural gas (“LNG”). 15 U.S.C. § 717b(e)(1); see EarthReports, Inc. v. 3

FERC, 828 F.3d 949, 952–53 (D.C. Cir. 2016). The Commission “shall” approve such an application unless it finds that the project “will not be consistent with the public interest.” 15 U.S.C. § 717b(a); see EarthReports, 828 F.3d at 953. “Before authorizing the construction and operation of a proposed LNG facility . . . the Commission must conduct an environmental review” under the National Environmental Policy Act (“NEPA”). Vecinos para el Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321, 1325 (D.C. Cir. 2021). If, as here, the Commission determines that approval of the facility constitutes a “major Federal action[] significantly affecting the quality of the human environment,” the Commission must prepare an Environmental Impact Statement (“EIS”). 42 U.S.C. § 4332(2)(C); see id. § 4336(b)(1). Among other things, the EIS must address the “reasonably foreseeable environmental effects” of the proposed action as well as “a reasonable range of alternatives . . . that are technically and economically feasible, and meet the purpose and need of the proposal.” Id. §§ 4332(2)(C)(i), (iii). The EIS “forces the [Commission] to take a ‘hard look’ at the environmental consequences of its actions” and “ensures that [those] consequences, and the [Commission’s] consideration of them, are disclosed to the public.” Sierra Club v. FERC (“Sabal Trail”), 867 F.3d 1357, 1367 (D.C. Cir. 2017). B On August 20, 2019, Commonwealth LNG, LLC (“Commonwealth”) applied to the Commission for authorization to build and operate a natural gas liquefaction and export facility in Cameron Parish, Louisiana (the “Project”). The Project would be located on approximately 153 acres of land on the west side of the Calcasieu Ship Channel, near the entrance to the Gulf of Mexico. As relevant here, 4

Commonwealth’s proposal included six LNG storage tanks, a marine facility consisting of an LNG carrier berth and barge dock, and utilities for electricity generation. On September 9, 2022, after taking public comments on the Project’s potential environmental impacts, the Commission issued a final EIS (“FEIS”). The FEIS found that, although the Project would have a permanent and significant impact on visual resources in the area, other impacts would not be significant or would be reduced to less-than-significant levels if certain recommended measures were incorporated into the Project. On November 17, 2022, the Commission authorized the Project as modified by the FEIS’s recommendations. See Order Granting Authorization Under Section 3 of the Natural Gas Act, Commonwealth LNG, LLC, 181 FERC ¶ 61,143 (Nov. 17, 2022) (“Authorization Order”). The Authorization Order found that the Project as modified constitutes an “environmentally acceptable action,” id. ¶ 84, and that its construction and operation are “not inconsistent with the public interest,” id. ¶ 85. On December 19, 2022, petitioners requested rehearing. Petitioners claimed that the Commission failed to reasonably assess the Project’s greenhouse gas (“GHG”) emissions, air pollution impacts, and impacts on sensitive species; rigorously explore all reasonable alternatives; and properly balance adverse effects and benefits under the NGA Section 3 public interest analysis. On January 19, 2023, after the Commission failed to timely respond, petitioners’ request was deemed denied by operation of law. On March 15, 2023, petitioners asked this court to review the Commission’s order. We granted Commonwealth leave to intervene. On June 9, 2023, while the petitions were pending, 5

the Commission issued an order addressing the rehearing request and affirming the authorization. See Order Addressing Arguments Raised on Rehearing, Commonwealth LNG, LLC, 183 FERC ¶ 61,173 (June 9, 2023) (“Rehearing Order”). II We review petitioners’ NEPA claims under the “arbitrary and capricious” standard of the Administrative Procedure Act (“APA”). Nevada v. U.S. Dep’t of Energy, 457 F.3d 78, 87 (D.C. Cir. 2006). “Our role is not to flyspeck an agency’s environmental analysis, looking for any deficiency no matter how minor, but instead simply to ensure that the agency has adequately considered and disclosed the environmental impact of its actions and that its decision is not arbitrary or capricious.” Birckhead v. FERC, 925 F.3d 510, 515 (D.C. Cir. 2019) (per curiam) (citations and quotation marks omitted). We therefore ask whether the agency “examine[d] the relevant data and articulate[d] a satisfactory explanation for its action[,] including a rational connection between the facts found and the choice made.” Motor Vehicle Mfrs. Ass’n, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (internal quotation marks omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healthy Gulf v. FERC
132 F.4th 544 (D.C. Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
107 F.4th 1033, Counsel Stack Legal Research, https://law.counselstack.com/opinion/healthy-gulf-v-ferc-cadc-2024.