Center for Biological Diversity v. FERC

67 F.4th 1176
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 16, 2023
Docket20-1379
StatusPublished
Cited by20 cases

This text of 67 F.4th 1176 (Center for Biological Diversity v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Center for Biological Diversity v. FERC, 67 F.4th 1176 (D.C. Cir. 2023).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 14, 2022 Decided May 16, 2023

No. 20-1379

CENTER FOR BIOLOGICAL DIVERSITY AND SIERRA CLUB, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

ALASKA GASLINE DEVELOPMENT CORPORATION, INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Erin Colón argued the cause for petitioners. With her on the briefs were Jeremy C. Lieb, Kristen Monsell, Nathan Matthews, Sara Gersen, and Elizabeth Jones.

Matthew J. Glover, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, and Lona T. Perry, Deputy Solicitor. 2 Howard L. Nelson argued the cause for intervenor in support of respondent. With him on the brief was Kenneth M. Minesinger.

Before: RAO and WALKER, Circuit Judges, and RANDOLPH,* Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge RAO.

RAO, Circuit Judge: The Alaska Gasline Development Corporation sought authorization to build and operate a system of natural gas facilities. After the Federal Energy Regulatory Commission granted that authorization, the Center for Biological Diversity and the Sierra Club (collectively, “CBD”) petitioned this court for review. Some of the issues CBD raises were not exhausted, and we lack jurisdiction to consider them. We reject CBD’s other arguments on the merits. FERC’s decision to authorize the Alaska Liquid Natural Gas Project was lawful and reasonable. We dismiss the petition in part and deny it in part.

I.

A.

The Corporation seeks to build liquefied natural gas (“LNG”) facilities in Alaska’s northernmost region, known as the North Slope. There are many productive natural gas wells in this region, and they produce more gas than current infrastructure can liquefy, ship, and bring to market. Due to these infrastructure limitations, much of the gas coming from the North Slope is reinjected into the ground to bolster internal

* Senior Circuit Judge Randolph was a member of the panel at the time the case was argued but did not participate in the opinion. 3 pressure and make extraction easier. Reinjection is a relatively low value use for natural gas.

The proposed Project would employ North Slope natural gas for more economically beneficial uses by building facilities to uptake the gas and ready it for pipeline transportation. The gas would be transported by a 42-inch diameter pipeline over 800 miles in length, bisecting Alaska from north to south. The pipeline would partially trace the path of an existing crude oil line. The Project also includes the construction of natural gas liquefaction facilities in the south of Alaska, near the Cook Inlet. Liquefaction reduces the volume of the gas and makes it easier to export by tanker ship. The Corporation has tentative plans to reroute some of the gas, before liquefaction, for use in Alaska. Project facilities are anticipated to uptake, transport, liquefy, and export substantial volumes of natural gas for at least 30 years.

B.

The Corporation sought FERC approval for its Project. When considering an application for an LNG facility, FERC must comply with the National Environmental Policy Act (“NEPA”), Pub. L. No. 91-190, 83 Stat. 852 (1970) (codified as amended at 42 U.S.C. § 4321 et seq.). Under NEPA, FERC was required to prepare an Environmental Impact Statement (“EIS”) because the Project was a “major Federal action[] significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C). FERC also must comply with the Natural Gas Act (“NGA”), Pub. L. No. 75-688, 52 Stat. 821 (1938) (codified as amended at 15 U.S.C. § 717 et seq.). The Commission must authorize the facility unless doing so would “not be consistent with the public interest.” 15 U.S.C. § 717b(a). 4 To comply with NEPA’s procedural requirements, the Commission prepared a roughly 1,500 page EIS, which analyzed the Project along a number of dimensions, including the potential impacts on wetlands, marine mammals, fish, drinking water, carbon dioxide levels, rivers, soils, permafrost, vegetation, the aesthetics of Denali National Park, and Alaskan socioeconomics. The Commission evaluated alternatives to the Project and analyzed mitigation measures that could help reduce certain environmental impacts. The Commission concluded the Project would cause a range of temporary, long- term, and permanent environmental impacts.

The Commission authorized the Project subject to 165 environmental conditions. Order Granting Authorization Under Section 3 of the Natural Gas Act (“Authorization Order”), 171 FERC ¶ 61,134 (May 21, 2020). The Commission found that the conditions would adequately mitigate the environmental impacts and that, as modified, the Project would be consistent with the public interest. CBD petitioned for rehearing, arguing that the EIS was deficient in various ways and that FERC had not adequately determined the Project was within the public interest. FERC denied rehearing. Order Addressing Arguments Raised on Rehearing (“Rehearing Order”), 172 FERC ¶ 61,214 (Sept. 11, 2020).

CBD timely petitioned for review of the Authorization and Rehearing Orders, and we granted the Corporation’s motion to intervene on behalf of FERC. We have jurisdiction to review the petition under the NGA. See 15 U.S.C. § 717r(b).

II.

CBD challenges the Authorization and Rehearing Orders for failure to comply with NEPA and its implementing regulations. We review NEPA challenges under the familiar standards of the Administrative Procedure Act (“APA”) to 5 determine whether the agency action was arbitrary and capricious or contrary to law. City of Oberlin v. FERC, 39 F.4th 719, 725 (D.C. Cir. 2022); 5 U.S.C. § 706(2)(A). NEPA requires agencies to “take a hard look at the environmental consequences before taking a major action.” Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87, 97 (1983) (cleaned up). Agencies evaluate these consequences in an EIS, which must consider:

(i) the environmental impact of the proposed action, (ii) any adverse environmental effects which cannot be avoided should the proposal be implemented, (iii) alternatives to the proposed action, (iv) the relationship between local short- term uses of man’s environment and the maintenance and enhancement of long-term productivity, and (v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented.

42 U.S.C. § 4332(2)(C).

NEPA is a purely procedural statute, and an agency therefore enjoys latitude when preparing an EIS. We will not set aside an agency action on NEPA grounds if the EIS “contains sufficient discussion of the relevant issues and opposing viewpoints and the agency’s decision is fully- informed and well-considered.” Gulf Restoration Network v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healthy Gulf v. DOI
D.C. Circuit, 2025
Sierra Club v. FERC
D.C. Circuit, 2025
Sierra Club v. DOE
D.C. Circuit, 2025
Healthy Gulf v. Haaland
District of Columbia, 2025
American Whitewater v. FERC
125 F.4th 1139 (D.C. Circuit, 2025)
City of Port Isabel v. FERC
111 F.4th 1198 (D.C. Circuit, 2024)
New Jersey Conservation Foundation v. FERC
111 F.4th 42 (D.C. Circuit, 2024)
Healthy Gulf v. FERC
107 F.4th 1033 (D.C. Circuit, 2024)
Food & Water Watch v. FERC
104 F.4th 336 (D.C. Circuit, 2024)
El Puente v. United States Army Corps of Engineers
100 F.4th 236 (D.C. Circuit, 2024)
Alabama Municipal Distributors Group v. FERC
100 F.4th 207 (D.C. Circuit, 2024)
Eagle County, Colorado v. STB
82 F.4th 1152 (D.C. Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
67 F.4th 1176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/center-for-biological-diversity-v-ferc-cadc-2023.