City of Oberlin, Ohio v. FERC

39 F.4th 719
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 8, 2022
Docket20-1492
StatusPublished
Cited by3 cases

This text of 39 F.4th 719 (City of Oberlin, Ohio v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Oberlin, Ohio v. FERC, 39 F.4th 719 (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued January 21, 2022 Decided July 8, 2022

No. 20-1492

CITY OF OBERLIN, OHIO, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

NEXUS GAS TRANSMISSION, LLC, INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Carolyn Elefant argued the cause and filed the briefs for petitioner.

David Bookbinder, Megan C. Gibson, and Ciara Malone were on the brief for amici curiae Landowners in support of petitioner.

Carol J. Banta, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. 2 With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

David A. Super argued the cause for intervenor NEXUS Gas Transmission, LLC. With him on the brief was Britt Cass Steckman.

Before: ROGERS and RAO, Circuit Judges, and SENTELLE, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge RAO.*

RAO, Circuit Judge: This case concerns whether the Federal Energy Regulatory Commission (“FERC” or “the Commission”) properly granted NEXUS Gas Transmission, LLC (“Nexus”) a certificate of public convenience and necessity to construct and operate a natural gas pipeline from Ohio to Michigan. After FERC granted Nexus the certificate, the City of Oberlin (“City”) petitioned for review claiming, among other things, that FERC did not adequately justify its reliance on agreements to transport gas ultimately bound for export to Canada as evidence of need for the pipeline. See City of Oberlin v. FERC (“Oberlin I”), 937 F.3d 599, 606 (D.C. Cir. 2019). We agreed that FERC had not explained why considering these agreements was lawful and remanded without vacatur for FERC to justify its decision. See id. at 606– 07, 611.

On remand, FERC explained its decision. FERC also clarified that it would have granted the certificate even without considering the export agreements. The City again petitions for review, contending that FERC’s explanations were arbitrary

* Senior Circuit Judge SENTELLE concurs in the judgment and joins the opinion only to the extent that it expresses the alternative explanation set forth in Section IV. 3 and capricious or contrary to law and that its decision violates the Takings Clause. We disagree. FERC’s justification for considering the agreements to transport gas bound for export is well reasoned and comports with both the Natural Gas Act and the Takings Clause. FERC’s alternative explanation that it would have granted Nexus a certificate even without considering the export agreements also passes muster. We deny the petition.

I.

A.

The Natural Gas Act authorizes FERC “to regulate the transportation and sale of natural gas in interstate commerce.” Oberlin I, 937 F.3d at 602. Section 7, the provision directly at issue in this case, governs the construction and operation of facilities used to transport or sell gas interstate. See 15 U.S.C. § 717f. Section 7 requires natural gas companies to receive a certificate from FERC before constructing or operating such a facility. Id. § 717f(c)(1)(A). Applications for a certificate are granted or denied according to the standard laid out in Section 7(e). Id. § 717f(c)(1)(B). FERC grants a certificate only if the proposed facility “is or will be required by the present or future public convenience and necessity.” Id. § 717f(e). Determining whether the proposed facility is or will be in the public convenience and necessity “requires the Commission to evaluate all factors bearing on the public interest.” Atl. Refining Co. v. Pub. Serv. Comm’n of N.Y., 360 U.S. 378, 391 (1959). Once a natural gas company has been issued a certificate, it can exercise eminent domain as needed to secure property for completing the project. 15 U.S.C. § 717f(h).

FERC has issued a policy statement outlining how it determines whether a proposed pipeline is or will be in the public convenience and necessity. See Certification of New 4 Interstate Nat. Gas Pipeline Facilities (“Certificate Policy Statement”), 88 FERC ¶ 61,227 (Sept. 15, 1999), clarified, 90 FERC ¶ 61,128 (Feb. 9, 2000), further clarified, 92 FERC ¶ 61,094 (July 28, 2000). First, FERC determines “whether the project can proceed without subsidies from [the company’s] existing customers.” Certificate Policy Statement, 88 FERC at 61,745. If that threshold has been met, FERC balances adverse effects that cannot be eliminated against the public benefits of the project, an exercise that “is essentially an economic test.” Id. “Adverse effects may include increased rates for preexisting customers, degradation in service, unfair competition, or negative impact on the environment or landowners’ property,” and “[p]ublic benefits may include ‘meeting unserved demand, eliminating bottlenecks, access to new supplies, lower costs to consumers, providing new interconnects that improve the interstate grid, providing competitive alternatives, increasing electric reliability, or advancing clean air objectives.’” Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301, 1309 (D.C. Cir. 2015) (quoting Certificate Policy Statement, 88 FERC at 61,748). A common method for applicants to demonstrate a public benefit is by showing demand for the project with precedent agreements, long-term contracts with shippers who would use the pipeline to transport natural gas. See Env’t Def. Fund v. FERC, 2 F.4th 953, 962 (D.C. Cir. 2021) (citing Certificate Policy Statement, 88 FERC at 61,748–49), cert. denied, 142 S. Ct. 1668 (2022).

Section 7 applies only to “natural gas companies,” defined as persons “engaged in the transportation [or sale] of natural gas in interstate commerce,” which is in turn defined as “commerce between any point in a State and any point outside thereof … but only insofar as such commerce takes place within the United States.” 15 U.S.C. § 717a(6)–(7). By defining interstate commerce to exclude foreign commerce, the Natural Gas Act excludes companies that import and export 5 gas, but otherwise operate entirely intrastate, from the definition of “natural gas company.” See Border Pipe Line Co. v. Fed. Power Comm’n, 171 F.2d 149, 151 (D.C. Cir. 1948). Import/export facilities are instead governed by Section 3 of the Natural Gas Act, 15 U.S.C. § 717b.1 Section 3, unlike Section 7, does not authorize the use of eminent domain to construct approved facilities.

In addition to governing facilities used to import or export natural gas, Section 3 governs the imports and exports. All persons must get the Secretary of Energy’s approval before importing or exporting any natural gas.2 15 U.S.C. § 717b(a).

1 Most import/export facilities meet the statutory definition of liquefied natural gas (“LNG”) terminals and are thus directly governed by Section 3. See 15 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rover Pipeline, L.L.C. v. Harris
2025 Ohio 2806 (Ohio Supreme Court, 2025)
Alabama Municipal Distributors Group v. FERC
100 F.4th 207 (D.C. Circuit, 2024)
Center for Biological Diversity v. FERC
67 F.4th 1176 (D.C. Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
39 F.4th 719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-oberlin-ohio-v-ferc-cadc-2022.