Rover Pipeline, L.L.C. v. Harris

2025 Ohio 2806
CourtOhio Supreme Court
DecidedAugust 13, 2025
Docket2024-0484
StatusPublished
Cited by1 cases

This text of 2025 Ohio 2806 (Rover Pipeline, L.L.C. v. Harris) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rover Pipeline, L.L.C. v. Harris, 2025 Ohio 2806 (Ohio 2025).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as Rover Pipeline, L.L.C. v. Harris, Slip Opinion No. 2025-Ohio-2806.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2025-OHIO-2806 ROVER PIPELINE, L.L.C., APPELLANT, v. HARRIS, TAX COMMR., APPELLEE. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as Rover Pipeline, L.L.C. v. Harris, Slip Opinion No. 2025-Ohio-2806.] Taxation—Public-utility property—R.C. Ch. 5727—Board of Tax Appeals has wide discretion in determining weight to be given to evidence and credibility of witnesses when faced with “battle of appraisals”—Board’s adoption of tax commissioner’s appraisal evidence was reasonable and lawful—Board’s decision affirmed. (No. 2024-0484—Submitted June 4, 2025—Decided August 13, 2025.) APPEAL from the Board of Tax Appeals, No. 2020-1540. _________________ FISCHER, J., authored the opinion of the court, which KENNEDY, C.J., and DEWINE, BRUNNER, DETERS, HAWKINS, and SHANAHAN, JJ., joined. SUPREME COURT OF OHIO

FISCHER, J. {¶ 1} Under Ohio law, the taxable property of a public utility shall be assessed at its true value in money. See R.C. 5727.10. At issue in this appeal is the true value for tax year 2019 of an interstate natural-gas pipeline owned and operated by appellant, Rover Pipeline, L.L.C. The Board of Tax Appeals (“board” or “BTA”) rejected the report proposed by Rover’s appraiser, finding that the value proposed by appellee Tax Commissioner Patricia Harris’s appraiser reflected the best evidence of the pipeline’s value. Rover appealed the board’s decision to this court. Rover’s challenge is multifaceted, but the crux of its argument is that the board vastly overvalued the pipeline. Because Rover has not shown that the board committed reversible error, we affirm. I. BACKGROUND {¶ 2} The record in this case is voluminous and is amply described in the board’s decision. See BTA No. 2020-1540 (Mar. 7, 2024). We recount only those facts that are necessary to put the case in its proper context and to frame the legal issues presented by the parties. A. Planning and building the pipeline {¶ 3} Rover’s pipeline is over 700 miles long and transports natural gas from the Marcellus and Utica shale basins located in Ohio, West Virginia, and Pennsylvania to markets across the United States and Canada. The Ohio portion of the pipeline runs from the east–central area of the State to a location in Defiance County, where it turns north and heads into Michigan. The pipeline has the capacity to transport 3.25 billion cubic feet of natural gas per day. {¶ 4} Beginning in 2013 and 2014, Rover determined that it could profit from the installation of a pipeline in the basins, which could ease a bottleneck that had emerged from insufficient infrastructure. Before commencing the pipeline’s construction and operation, however, Rover first had to apply for and receive approval from the Federal Energy Regulatory Commission (“FERC”). See

2 January Term, 2025

Alabama Mun. Distribs. Group v. Fed. Energy Regulatory Comm., 100 F.4th 207, 209 (D.C. Cir. 2024), citing 15 U.S.C. 717f(c)(1)(A). In determining whether to approve such an application, FERC will often check whether an applicant has collected precedent agreements—“long-term contracts with shippers who would use the pipeline to transport natural gas”—which demonstrate demand for the project. Oberlin v. Fed. Energy Regulatory Comm., 39 F.4th 719, 722 (D.C. Cir. 2022). {¶ 5} To facilitate FERC’s approval, Rover negotiated several precedent agreements with shippers in the region. The agreements accounted for 95 percent of the pipeline’s capacity. As a representative example, one agreement authorized a shipper to transport specified quantities of natural gas through Rover’s pipeline at a fixed price for 15 years, with an option to extend. {¶ 6} Rover’s negotiations with the shippers were informed by its understanding of the project’s construction costs and the return Rover could earn on its investment. Rover initially estimated that it would cost $4.2 billion to construct the pipeline. Based on that estimate, it structured its precedent agreements to achieve a 13 percent return on equity. {¶ 7} FERC approved Rover’s application in February 2017, but the project’s actual cost—$6.3 billion—vastly exceeded Rover’s expectations. Two factors contributed to this increase. {¶ 8} First, abnormally high levels of rainfall caused construction delays and increased costs. During periods of inactivity because of heavy rainfall, idle workers continued to be paid per the terms of their employment agreements. The same goes for leased equipment, which sat onsite while the conditions were too wet for construction. While the project area historically received 37.38 inches of rain annually, during construction, the area received 61.08 inches of rain, annualized. {¶ 9} Second, in April 2017, Rover ran into an environmental problem when one of its contractors released two million gallons of bentonite-based drilling

3 SUPREME COURT OF OHIO

fluid while drilling underneath the Tuscarawas River. The drilling fluid surfaced in a wetland near the river, covering approximately 6.5 acres. Rover notified FERC of the incident, and, in response, FERC ordered Rover to, among other things, stop drilling activities in certain locations and double the number of environmental inspectors per work area. Construction on the pipeline stalled for four to five months because of regulatory actions taken by FERC and Ohio’s Environmental Protection Agency. {¶ 10} In November 2018, the pipeline was completed and became available for commercial operation. B. The Blackstone transaction {¶ 11} In July 2017, the investment firm Blackstone acquired a 49.9 percent equity stake in ET Rover Pipeline, L.L.C., Rover’s “corporate great-grandparent,” BTA No. 2020-1540 at 7 (Mar. 7, 2024), eventually paying $1.51 billion for its ownership interest.1 Because ET Rover Pipeline owned a 65 percent interest in Rover, Blackstone thus acquired a 32.435 percent indirect ownership interest in Rover. {¶ 12} ET Rover Pipeline thus retained a controlling interest by the slimmest of margins under the terms of the deal—50.1 percent to Blackstone’s 49.9 percent. Nevertheless, Blackstone gained access to 32.435 percent of the cash flows generated by Rover’s pipeline. C. Proceedings before the tax commissioner {¶ 13} Ohio’s public-utility-property tax is set forth in R.C. Ch. 5727. It is undisputed that Rover is subject to the tax as a “pipe-line company.” See R.C. 5727.01(D)(5) (defining “pipe-line company” as a taxpayer “engaged in the

1. The actual purchaser was BCP Renaissance, L.L.C., which is held by Blackstone. For purposes of this appeal, the parties have characterized Blackstone as the purchaser; accordingly, we do the same. Blackstone paid for its interest in installments, with the bulk of the payments made during the fourth quarter of 2017.

4 January Term, 2025

business of transporting natural gas, oil, or coal or its derivatives through pipes or tubing, either wholly or partially within this state”). As a pipeline company, Rover’s taxable property subject to assessment by the tax commissioner for the 2019 tax year consisted of its tangible personal property located in Ohio on December 31 of the preceding year—here, December 31, 2018 (i.e., the tax-lien date)—but not including property otherwise exempted by law. See R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Dunn v. Delaware Cty. Bd. of Elections
2026 Ohio 1084 (Ohio Supreme Court, 2026)
In re Guardianship of Foust
2025 Ohio 5833 (Ohio Court of Appeals, 2025)
Snider Crossing L.L.C. v. Warren Cty. Bd. of Rev.
2025 Ohio 3189 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 2806, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rover-pipeline-llc-v-harris-ohio-2025.