Midcoast Interstate Transmission, Inc. v. Federal Energy Regulatory Commission

198 F.3d 960, 339 U.S. App. D.C. 213, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20299, 2000 U.S. App. LEXIS 619, 2000 WL 4986
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 18, 2000
Docket98-1603, 98-1604, 99-1047 and 99-1090
StatusPublished
Cited by21 cases

This text of 198 F.3d 960 (Midcoast Interstate Transmission, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midcoast Interstate Transmission, Inc. v. Federal Energy Regulatory Commission, 198 F.3d 960, 339 U.S. App. D.C. 213, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20299, 2000 U.S. App. LEXIS 619, 2000 WL 4986 (D.C. Cir. 2000).

Opinion

Opinion filed by Senior Judge BUCKLEY.

BUCKLEY, Senior Judge:

Midcoast Interstate Transmission, Inc., and two unincorporated associations have filed petitions for review of Federal Ener *964 gy Regulatory Commission orders granting Southern Natural Gas Company’s application to construct a natural gas pipeline and denying Midcoast’s alternative proposals for serving the same markets. Petitioners claim that the Commission failed to make a reasoned evaluation of the competing environmental and economic factors and that its approval of “rolled-in” rates for Southern’s project ignored the agency’s own policy and precedent. Because we conclude that the Commission neither abused its discretion nor acted contrary to law, we deny the petitions.

I. Background

A. Statutory and Regulatory Framework

Under section 7 of the Natural Gas Act (“NGA”), 15 U.S.C. §§ 717-717z (1997), a company seeking to construct and operate any portion of an interstate gas pipeline must apply to the Federal Energy Regulatory Commission (“FERC”) for a certificate of public convenience and necessity. 15 U.S.C. § 717f(c)(1)(A). Such a certificate

shall be issued to any qualified applicant therefor ... if it is found that the applicant is able and willing properly to do the acts and to perform the service proposed ... and that the proposed service ... is or will be required by the present or future public convenience and necessity.

Id. § 717f(e). In evaluating certificate applications, FERC employs “a flexible balancing process, in the course of which all the factors are weighed prior to final determination.” FPC v. Transcontinental Gas Pipe Line Corp., 365 U.S. 1, 23, 81 S.Ct. 435, 5 L.Ed.2d 377 (1961). Congress and the Commission have both stated that the promotion of competition in the natural gas industry is one of the Commission’s regulatory goals. See General Motors Corp. v. Tracy, 519 U.S. 278, 283-84, 117 S.Ct. 811, 136 L.Ed.2d 761 (1997).

Section 4 of the NGA provides that “[a]ll rates and charges” of a natural gas pipeline must be “just and reasonable.” 15 U.S.C. § 717c(a). A pipeline may not change its rates “except after thirty days’ notice to the Commission and to the public.” Id. § 717c(d). When a pipeline files a new rate, FERC may, upon receiving a complaint or on its own initiative, “enter upon a hearing concerning the lawfulness of such rate ...; and, pending such hearing and the decision thereon, the Commission ... may ... defer the use of such rate” for up to five months. Id. § 717c(e).

When an interstate pipeline proposes to expand its business through the construction of new facilities (“expansion facilities”), FERC has the authority to establish the initial rates that will be charged customers who will be served by those facilities. See United Gas Improvement Co. v. Callery Properties, Inc., 382 U.S. 223, 227, 86 S.Ct. 360, 15 L.Ed.2d 284 (1965) (holding that Commission may establish initial rates as condition to issuing certificate “pending determination of a just and reasonable rate” through a section 4 proceeding). In May 1995, the Commission issued a policy statement governing how the cost of new pipeline construction should be “priced,” i.e., reflected in the pipeline’s rate structure. See generally Pricing Policy For New and Existing Facilities Constructed By Interstate Natural Gas Pipelines, 71 FERC ¶ 61,241 (1995) (“Pricing Policy”). The cost of construction may be recovered in either of two ways: through “incremental” pricing, which imposes an additional charge payable solely by customers who are directly served by the expansion facilities (“expansion customers”); or “rolled-in” pricing, in which the cost of the new facilities are added to the pipeline’s total rate base and reflected in rates charged to all customers systemwide. See TransCanada PipeLines Ltd. v. FERC, 24 F.3d 305, 307 n. 1 (D.C.Cir.1994).

Under the Pricing Policy, when FERC grants a certificate of public convenience and necessity, it either sets an incremental rate to be paid by consumers served by *965 the new facilities or establishes a presumption that the facilities will be of sufficient benefit to existing customers to permit the pipeline to roll their cost into its system-wide rates. See Pricing Policy, 71 FERC at 61,915. If the Commission issues a certificate with a presumption of rolled-in pricing, the expansion customers will initially pay the pipeline’s existing system-wide rates. Otherwise, they will be required to pay an incremental rate fixed by the Commission at the time the certificate issues. Id. at 61,918 n. 12. Those rates will remain in place until superceded by new ones established in accordance with section 4 of the NGA.

To determine whether a pipeline qualifies for rolled-in pricing, FERC “look[s] to the extent to which the new facilities are integrated with the existing facilities and to the specific system benefits produced by the project.” Id. at 61,915-16. Where the pipeline can establish that the new facilities will provide system-wide benefits and that the rolled in rate would constitute an increase of five percent or less to existing customers, a rebuttable presumption is created in favor of rolled-in rates. Id. at 61,916-17. In such instances, the Pricing Policy requires the Commission to approve rolled in rates in the next section 4 proceeding absent evidence of a “significant change in circumstance.” Id. at 61,918.

While this case was pending, FERC issued a new policy statement on the certification of pipeline projects that arguably would have required incremental pricing for the expansion facilities that are the subject of this case. See generally Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227 (1999). The new policy, however, has no bearing on these proceedings because it does not apply retroactively. See id. at 61,750; Southeastern Michigan Gas Co. v. FERC, 133 F.3d 34, 37 n. 1 (D.C.Cir.1998) (“Because FERC issued its [new pricing] rule after this case had begun and did not rely on it in this proceeding, we do not consider what effect its application would have had.”).

B. Facts

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
198 F.3d 960, 339 U.S. App. D.C. 213, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20299, 2000 U.S. App. LEXIS 619, 2000 WL 4986, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midcoast-interstate-transmission-inc-v-federal-energy-regulatory-cadc-2000.