Board of Water, Light & Sinking Fund Commissioners v. Federal Energy Regulatory Commission

294 F.3d 1317, 2002 U.S. App. LEXIS 12211, 2002 WL 1343248
CourtCourt of Appeals for the Eleventh Circuit
DecidedJune 20, 2002
Docket01-10216
StatusPublished
Cited by1 cases

This text of 294 F.3d 1317 (Board of Water, Light & Sinking Fund Commissioners v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Water, Light & Sinking Fund Commissioners v. Federal Energy Regulatory Commission, 294 F.3d 1317, 2002 U.S. App. LEXIS 12211, 2002 WL 1343248 (11th Cir. 2002).

Opinion

*1319 ANDERSON, Circuit Judge:

Petitioner Board of Water, Light & Sinking Fund Commissioners of the City of Dalton, Georgia (“Dalton”) challenges two orders by the Federal Energy Regulatory Commission (“FERC” or the “Commission”) permitting the construction of a direct delivery connection between Southern Natural Gas Company’s (“Southern”) natural gas pipeline and one of Dalton’s current customers, the Beaulieu Plant (“Beaulieu”). The proposed connection will allow Beaulieu to bypass Dalton. Dalton contends that FERC’s orders are unlawful for several reasons, including that they violate Southern’s tariff and that they were impermissible under various sections of the Natural Gas Act (“NGA”). Dalton also challenges whether the Commission had jurisdiction under the NGA to issue the orders permitting the direct pipeline connection, arguing that by approving the bypass connection, the Commission intruded into the state’s regulatory province oyer local distribution of natural gas. We conclude that the Commission had jurisdiction to issue its orders, and that it did not act arbitrarily or capriciously in deciding that the requested bypass connection should be permitted. Furthermore, we conclude that the Commission did not abuse its discretion by denying the request for an evidentiary hearing.

I. FACTUAL AND PROCEDURAL BACKGROUND

A. Southern’s Policy Concerning Direct Delivery Connections

The issues involved in this case derive in part from a previous action in which an end-user of natural gas, Arcadian Corp. (“Arcadian”), sought to require Southern to grant it a direct delivery connection 1 to Southern’s pipeline. On May 12, 1994, the Commission approved a settlement in Arcadian’s case, pursuant to which Southern was required to construct a bypass connection for Arcadian. Furthermore, the settlement required Southern to file proposed tariff 2 provisions governing future requests by end-users of natural gas seeking direct delivery pipeline connections. See Arcadian Corp. v. Southern Natural Gas Co., 67 FERC ¶ 61,176, 1994 WL .190737 (1994). The direct delivery provision eventually approved by FERC became § 36 of Southern’s tariff. Section 36, in relevant part, states:

DIRECT DELIVERY CONNECTIONS

(a) As used herein, the term direct delivery connection shall refer to interconnection, measurement, and appurtenant facilities necessary to deliver gas directly to an end-user.
(b) A SHIPPER may request a new direct delivery connection by submitting to the attention of [Southern’s] Transportation Services Department, ... a written request to [Southern] in the format set out in Appendix A to these General Terms and Conditions. If SHIPPER is currently receiving natural gas services from the local distributor servicing the area, or if the direct delivery connection is in the authorized service area of a local distribution company, SHIPPER shall provide a. copy of its request for a direct delivery connection to such local distribution company. *1320 SHIPPER shall notify [Southern] of the date SHIPPER has complied with this notice requirement, and [Southern] shall not make the filing required by Section 157.211(a)(2) of the Commission’s Regulations until thirty (30) days after the date SHIPPER notified such local distribution company of its request for a direct delivery connection.
'(c) [Southern] will add a new direct delivery connection if-such direct delivery connection is operationally and economically feasible.
(d) A direct delivery connection is operationally feasible if, with such connection facilities, [Southern] has the existing pipeline capacity to perform the requested service through the proposed direct delivery connection and such service will not impair [Southern’s] ability to provide service to its existing firm customers.
(e) (1) A direct delivery connection is economically feasible if the proposed transportation service to be provided through the direct delivery connection will produce a net revenue gain (“revenue positive”), or is revenue neutral to [Southern].
(2) To the extent that the new direct delivery connection serves an end-user that has historically been served by a firm customer of [Southern], the proposed transportation service to be provided through the new direct delivery connection will be deemed revenue positive or revenue neutral if the costs set out in Section 26(f)(1), (3), and (4), as applicable, are paid or reimbursed in full by the SHIPPER obtaining the direct delivery connection ....
(f) The costs referenced in Sections 36(e)(2) and (3), as applicable are:
(1) All costs, including overhead and taxes, associated with construction of the required direct delivery connection facilities and with any modifications to existing facilities required to maintain service to existing firm customers ....
(g)After the SHIPPER requesting the direct delivery connection executes an interconnection agreement agreeing to pay or reimburse [Southern] in full for the costs set out in Section 36(f)(1), (2), (3), and (4), as applicable, and [Southern] has received all necessary regulatory authorizations to construct, install, and operate the direct delivery connection facilities, [Southern] shall commence , construction of the new direct delivery connection in accordance with the terms of such agreement and regulatory authorizations.

Southern’s Natural Gas Tariff, Seventh Revised, § 36. Therefore, subject to regulatory authorization by FERC, section 36 requires Southern to provide a direct delivery connection to an end-user when such a connection is requested by a shipper, if providing the connection will either result in a revenue gain, or will be revenue neutral, to the pipeline. Furthermore, section 36 indicates that a connection will be considered “revenue neutral” if the shipper agrees to pay or reimburse for all of the costs of the connection to Southern.

B. The Beaulieu Plant and Dalton

Beaulieu is a carpet manufacturer that became a natural gas customer of Dalton in 1971. 3 Initially, Dalton provided the Beaulieu Plant with “firm” gas service, meaning that Beaulieu was guaranteed a certain amount of gas and in exchange had to pay reservation or “demand” charges to Dalton, regardless of whether it actually used the gas. But in 1987 Beaulieu switched to an “interruptible” arrangement, 4 under which it purchases gas from third-party marketers, while retaining the option to purchase gas directly from Dal *1321 ton when its supply from third-party marketers is inadequate.

In 1997, Beaulieu began purchasing its natural gas from Interconn Resources, Inc. (“Intercom”), a third-party marketer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FPL Group, Inc. v. Comm'r
2005 T.C. Memo. 208 (U.S. Tax Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
294 F.3d 1317, 2002 U.S. App. LEXIS 12211, 2002 WL 1343248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-water-light-sinking-fund-commissioners-v-federal-energy-ca11-2002.