Southern Natural Gas Company and Southern Energy Company v. Federal Energy Regulatory Commission

780 F.2d 1552, 1986 U.S. App. LEXIS 21517
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 30, 1986
Docket84-7563
StatusPublished
Cited by2 cases

This text of 780 F.2d 1552 (Southern Natural Gas Company and Southern Energy Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Natural Gas Company and Southern Energy Company v. Federal Energy Regulatory Commission, 780 F.2d 1552, 1986 U.S. App. LEXIS 21517 (11th Cir. 1986).

Opinion

TJOFLAT, Circuit Judge:

Southern Natural Gas Company and Southern Energy Company have petitioned for review of a Federal Energy Regulatory Commission order requiring that they invoke the minimum bill provision of a gas tariff as of June 10, 1980. 1 We affirm the Commission’s order.

I.

In the early 1970’s, Southern Energy Company made applications to the Federal Power Commission, the predecessor to the Federal Energy Regulatory Commission, 2 for authorization to import large quantities of liquified natural gas (LNG) from Algeria and to construct a facility at Elba Island near Savannah, Georgia, to receive the LNG and regasify it. The gas would then be sold to Southern Energy’s parent, Southern Natural Gas Company, and transmitted by pipeline to Southern Natural’s interstate transmission line. The LNG was to be produced by Sonatrach, a corporation owned by the Algerian government, and sold by Sonatrach to El Paso Algeria Corporation, which would transport the LNG overseas by tanker. Southern Energy contracted with El Paso Algeria for the purchase of 350,000 Mcf per day of LNG for a twenty-five year term.

The Commission, citing gas shortage conditions in the United States, issued an opinion on June 28, 1972, authorizing Southern Energy to import annual quantities of approximately 143,718.75 billion Btu of LNG, 3 pursuant to section 3 of the Natural Gas Act, 15 U.S.C. § 717b (1982), and issued certificates of public convenience and necessity to construct and operate the facility and pipelines necessary for the project, pursuant to section 7(c) of the Natural Gas Act, 15 U.S.C. § 717f(c) (1982). Columbia LNG Corp., 47 F.P.C. 1624 (Opinion No. 622), modified, 48 F.P.C. 723 (1972) (Opinion No. 622-A) (per curiam), vacated and remanded on other grounds, 491 F.2d 651 (5th Cir.1974). The Commission simultaneously approved a similar venture to be undertaken by Columbia LNG Corporation and Consolidated System LNG Company involving a Cove Point, Maryland, LNG facility. 4 As a condition to its approval, the Commission rejected, as contrary to the public interest, a part of the rate schedule filed by Southern Energy that would have required the pipeline purchaser to pay the full cost of service regardless of whether LNG deliveries were actually made to the pipeline. Columbia LNG Corp., 47 F.P.C. at 1639-40; see Columbia LNG Corp., 48 F.P.C. at 730. The Commission noted that it was thereby requiring Southern Energy and its shareholders to bear the entire economic risk of the project. The ratepayers were absolved from sustaining the burdens of the project should it prove unsuccessful. 47 F.P.C. at 1640.

Upon applications for rehearing, the Commission affirmed its original opinion in most respects. Columbia LNG Corp., 48 F.P.C. 723 (1972) (Opinion No. 622-A) (per curiam). It did, however, in order to make the project economically feasible, modify some of the conditions it had originally imposed. Noting its earlier condition rejecting full “cost-of-service” tariffs, the Commission decided that it would now permit a minimum bill that allowed the LNG companies to recover certain fixed costs in the event of nondelivery of gas. Id. at 730. Under this provision, stockholders of the company would not be allowed a return on *1555 equity during any period of nondelivery, but the company could recover its costs. This minimum bill provision was necessary in order for Southern Energy to secure project financing. The Commission stated that “[sjueh tariff provisions are required by the public convenience and necessity as an equitable apportionment of the risk between customers and stockholders and in order to assure the financing of the project on reasonable terms to the consumer.” Id. The Commission therefore authorized inclusion of a minimum bill provision in Southern Energy’s tariff as follows: “In the event that Seller is unable to deliver gas to Buyer during any period exceeding one day, Buyer shall reimburse Seller for all out-of-pocket expenses incurred during such period____” Id. at 731. 5

LNG deliveries from Algeria commenced in March 1978. In 1979, Sonatrach sought a price increase for the LNG it was selling to El Paso Algeria. The companies reached agreement on such an increase, but the Algerian government would not approve it. As a result, LNG shipments from Algeria were stopped as of March 31, 1980. On April 9, Southern Energy received its last shipment of LNG from Algeria, leaving Southern Energy’s storage tanks nearly full. Subsequent negotiations at the governmental level and the company level were unavailing, and gas deliveries were not resumed.

Following the cut-off of its LNG supply on April 9, Southern Energy decided to husband its remaining supplies by reducing the quantity of gas it would send out on a daily basis. Gas deliveries were greatly reduced in April 1980, reduced further in May 1980,® and by June 1980, deliveries had been reduced to “boil-off” levels. 6 7

In August 1980, the Commission initiated an investigation into the rates being charged by Southern Energy. 8 In January 1981, Southern Energy and Southern Natural secured the agreement of most of their resale customers in a conservation plan, which it offered to the Commission as a settlement of the investigation. The plan called for continuing minimal deliveries of *1556 gas in order to have supplies available for emergency and winter use. Southern Energy could continue to bill the full cost of service as long as it maintained a specified quantity of gas in storage. When gas levels dropped below that specified quantity, Southern Energy would be required to invoke the minimum bill. Southern Energy operated under this procedure pending the completion of the investigation and ultimately invoked the minimum bill on April 15, 1982. 9

On March 5, 1982, the administrative law judge (ALJ) issued an initial decision finding that Southern Energy had complied with its minimum bill provision. Columbia Gas Transmission Corp., 18 F.E.R.C. ¶ 63,060 (1982). 10 The ALT found the minimum bill, which had to be invoked when the seller is “unable to deliver gas,” clear and unambiguous. Id. at 65,191. The ALT focused on the company’s ability to deliver gas. Because Southern Energy had the ability to deliver gas at all times following the embargo, it was not required to invoke the minimum bill. Moreover, Southern Energy was not only able

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
780 F.2d 1552, 1986 U.S. App. LEXIS 21517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-natural-gas-company-and-southern-energy-company-v-federal-energy-ca11-1986.