Southern Natural Gas Company and Southern Energy Company v. Federal Energy Regulatory Commission

813 F.2d 364, 1987 U.S. App. LEXIS 3977
CourtCourt of Appeals for the Eleventh Circuit
DecidedMarch 30, 1987
Docket85-7327
StatusPublished
Cited by4 cases

This text of 813 F.2d 364 (Southern Natural Gas Company and Southern Energy Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Natural Gas Company and Southern Energy Company v. Federal Energy Regulatory Commission, 813 F.2d 364, 1987 U.S. App. LEXIS 3977 (11th Cir. 1987).

Opinion

TJOFLAT, Circuit Judge:

This case concerns refunds the Federal Energy Regulatory Commission (Commission) ordered following our opinion in Southern Natural Gas Co. v. FERC, 780 F.2d 1552 (11th Cir.1986). In that case, we upheld the Commission’s determination that Southern Natural Gas Company (Southern) 1 had collected excess tariffs from its customers by failing to invoke a price limiting provision in its natural gas tariff. The Commission had also ordered Southern to provide full refunds to its customers for the excess money they paid between June 10, 1980, the date the Commission determined that Southern should have invoked the price limiting provision, and April 15, 1982, the date on which Southern actually invoked that provision. Southern now seeks review of the Commission’s decision that Southern provide full refunds to all of its customers.

I.

Early in the 1970s, Southern applied to the Federal Power Commission 2 for permission to import liquified natural gas (LNG) from Algeria, and to construct a facility near Savannah, Georgia, to regasify the LNG. Southern planned to transport the regasified LNG through a pipeline and sell it to various energy companies. The Commission, citing domestic gas shortages, approved Southern’s plan, but it rejected the part of Southern’s proposed tariff that would have required purchasers to pay for the full cost of service, including a return on Southern’s capital investment in the LNG facility, even if Southern did not deliver any gas. See generally Southern Natural Gas Co. v. FERC, 780 F.2d 1552 (11th Cir.1986). Eventually, in order to make construction of the LNG facility economically feasible, the Commission authorized Southern to include in its tariff a “minimum bill” provision that would enable Southern to recover from its customers some of its fixed costs when gas was not delivered. The minimum bill, however, precluded Southern from receiving any return on equity. 3 This arrangement, the Com *366 mission concluded, “equitably] apportioned] ... the risk [of an Algerian oil and gas embargo] between [Southern’s] customers and [its] stockholders and ... assure[d] the financing of the project on reasonable terms to the consumer.” Id. at 1555 (quoting Columbia LNG Corp., 48 F.P.C. 723, 730 (1972) (Opinion No. 622-A) (per curiam)).

Southern began receiving LNG from Algeria in 1978. Soon thereafter, a problem arose when Southern and its Algerian supplier negotiated a price increase. The Algerian government refused to approve the price increase, and the supplier stopped shipping the LNG. Southern received its last LNG shipment on April 9, 1980. To conserve its supply of stored gas, Southern greatly reduced the amount of gas it supplied to its customers; by June 1980, Southern was delivering only one to two percent of the amount of gas that it had been delivering just prior to the termination of the Algerian shipments.

In August 1980, the Commission began investigating Southern’s LNG tariff, as part of an investigation involving another company with an identical minimum bill provision in its tariff. In January 1981, most of Southern’s customers agreed to a husbanding plan, which called for Southern to continue to deliver only minimal amounts of gas and to store the remainder for winter or emergency use. Under this settlement, Southern would bill its full cost of service, including a return on Southern’s capital investment, as long as it stored a certain amount of gas. If the stored quantity of gas dropped below a certain level, Southern would invoke the minimum bill. Southern sought the Commission’s approval of the 1981 settlement. While the matter was pending before the Commission, Southern, on April 15, 1982, invoked the minimum bill.

The Commission did not approve the 1981 settlement. Instead, after several administrative hearings, the Commission ruled that Southern should have invoked its minimum bill on June 10, 1980, when it stopped delivering gas in substantial amounts. In Opinion No. 222, the Commission therefore rejected the 1981 settlement, which, as noted, allowed Southern to delay invoking the minimum bill, as being against the public interest. See Southern Natural Gas Co., 27 F.E.R.C. ¶ 61,322, at 61,605 (Opinion No. 222), modified, 28 F.E.R.C. 1161, 240 (Opinion No. 222-A) (1984). See generally Southern Natural Gas, 780 F.2d at 1556-57 & nn. 10-15.

The Commission’s decision that Southern failed timely to invoke the minimum bill provision meant that for almost two years Southern had collected a greater amount of money than its tariff authorized. To remedy this situation, the Commission ordered Southern to prepare a plan under which Southern’s customers who had not agreed to the 1981 settlement, and non-consenting consumers of those of Southern’s customers who had agreed to the plan, would receive full refunds. 4 See Southern Natural Gas Co., 27 F.E.R.C. ¶ 61,322, at 61,605-06, modified, 28 F.E.R.C. ¶ 61,240 (1984).

As Southern was preparing its refund plan, it petitioned this court to review the Commission’s decision that Southern had delayed implementing the minimum bill. While we were entertaining that petition, Southern submitted a plan to the Commission that gave full refunds to two customers, and minimal refunds to all others, whom Southern deemed to have been direct or indirect consenting parties to the 1981 *367 settlement. 5 Many of Southern’s customers objected to the company’s proposed refund plan, arguing that Southern’s consenting and non-consenting customers had received the same service under the 1981 settlement; thus, consenting customers had received no benefit that would justify their getting less than full refunds. 6 The Commission agreed with these objections, and issued an order rejecting Southern’s plan and ordering full refunds to all customers. See Southern Natural Gas Co., 30 F.E.R.C. ¶ 61,080 (1985). In that opinion, the Commission stated that opponents of Southern’s plan had convinced it that consenting and non-consenting customers had received the same benefit during the time Southern was conserving its LNG supplies, and thus should be treated equally for purposes of a refund. Furthermore, the Commission believed that denying full refunds to consenting customers would penalize them for having earlier agreed to the 1981 settlement, which would be contrary to its policy of encouraging settlements.

Southern petitioned this court to review the Commission’s order requiring full refunds. We stayed that proceeding pending our disposition of Southern’s first petition, involving the validity of the Commission’s decision that Southern did not timely invoke its minimum bill and that the 1981 settlement was contrary to the public interest. In

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
813 F.2d 364, 1987 U.S. App. LEXIS 3977, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-natural-gas-company-and-southern-energy-company-v-federal-energy-ca11-1987.