South Georgia Natural Gas Company v. Federal Energy Regulatory Commission

699 F.2d 1088, 1983 U.S. App. LEXIS 29914
CourtCourt of Appeals for the Eleventh Circuit
DecidedMarch 7, 1983
Docket81-7784
StatusPublished
Cited by8 cases

This text of 699 F.2d 1088 (South Georgia Natural Gas Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Georgia Natural Gas Company v. Federal Energy Regulatory Commission, 699 F.2d 1088, 1983 U.S. App. LEXIS 29914 (11th Cir. 1983).

Opinion

*1089 RONEY, Circuit Judge:

This appeal involves an interpretation of a regulation of the Federal Energy Regulatory Commission (FERC) concerning the filing of certain tariff information. The ultimate issue is whether a three-year period for filing the information began on August 1, 1980 or on July 2,1981. Concluding that FERC’s interpretation of its own regulation is not unreasonable, arbitrary, capricious, or an abuse of discretion, we affirm the agency’s decision that the period began on August 1, 1980.

Briefly, FERC has provided natural gas pipelines a procedure to recover their cost of purchased gas without having to file a general rate increase application. The procedure requires a pipeline to obtain approval of a Base Tariff Rate which includes all authorized costs including the cost of purchased gas. Through inclusion of a purchase gas agreement (PGA) in its base tariff, a pipeline can thereafter adjust its rates every six months to reflect changes in the cost of purchased gas. 18 C.F.R. § 154.-38(d)(4)(iv) (1982). See Panhandle Eastern Pipe Line Co. v. FERC, 613 F.2d 1120, 1143 (D.C.Cir.1979) (Wright, C.J., concurring in part), cert. denied, 449 U.S. 889, 101 S.Ct. 247, 66 L.Ed.2d 115 (1980). The regulation goes on to provide that a pipeline using a PGA clause must file a new base tariff rate, for Commission Review, every 36 months along with a cost of service study that includes both purchased gas and non-gas costs. 18 C.F.R. § 154.38(d)(4Xvi)(a) (1982). It is the commencement date for this 36-month period that is the issue here.

Although the period normally runs from when the most recent base tariff is filed, it is postponed if the pipeline subsequently files for a general rate increase under section 4 of the Natural Gas Act, 15 U.S.C.A. § 717c. In such a case, the date on which the 36-month period begins to run is controlled by 18 C.F.R. § 154.38(d)(4)(vi)(b) (1982), which provides that the period starts “when the proposed rates go into effect”, as follows:

If a section 4(e) case is filed before the expiration of the 36-month period, a new 36-month period will start running when the proposed rates go into effect. Rates determined by the Commission in a section 4(e) or a 5(a) proceeding or rates in a settlement agreement approved by the Commission shall establish the new Base Tariff Rate when they become effective pursuant to a final order, and a new 36-month period will start running (Emphasis added).

South Georgia maintains that the quoted language is clear: when the Commission suspends the effectiveness of a section 4 filing and then proceeds under the authority of section 5 of the Natural Gas Act to find that the rate being charged is not just and reasonable, it enters an order determining the just and reasonable rate “to be thereafter observed.” 15 U.S.C.A. § 717d(a). It argues that the Commission’s regulation ties the start of a new 36-month period to the action taken by the Commission under section 5, which action operates prospectively. The rationale of the Commission’s orders, on the other hand, is that the phrase “when [the settlement rates] become effective” relates back to the date when the pipeline’s filed rates became effective subject to refund.

The parties generally agree on the pertinent facts. On February 1, 1977 South Georgia operating under a tariff with a purchase gas agreement filed a section 4 application for proposed changes in its tariff starting one month later. Acting pursuant to section 4(e), 15 U.S.C.A. § 717c(e), FERC suspended the proposed increase for five months until August 1st. At that time, South Georgia could lawfully collect the tariff, subject to refund if a subsequent proceeding or settlement should determine the proposed tariff to be excessive. On May 5, 1978 the Commission approved a settlement that provided for rates lower than those proposed which, when filed in a substitute tariff, went into effect July 2, 1978, with refunds from August 1, 1977.

Following informal correspondence between the parties, South Georgia in December 1980 asked FERC to clarify when it had to file a new base tariff pursuant to the *1090 purchase gas regulation. In one of the orders that are the subject of this appeal, the Commission responded that South Georgia should have filed on August 1, 1980, 36 months after August 1, 1977, and directed the pipeline to do so immediately with the restated rates to be effective from August first. The Commission subsequently denied a rehearing in the second order from which South Georgia appeals.

In considering FERC’s construction of the controlling regulation it is important to remember our narrow standard of review. “An agency’s interpretation of its own regulation is entitled to great deference.” Pennzoil Co. v. FERC, 645 F.2d 360, 383 (5th Cir.1981), cert. denied, 454 U.S. 1142, 102 S.Ct. 1000, 71 L.Ed.2d 293 (1982). See Udall v. Tallman, 380 U.S. 1, 16, 85 S.Ct. 792, 801, 13 L.Ed.2d 616 (1965) (noting that this deference is even greater than that afforded an agency’s construction of a statute it administers). The agency’s view must be upheld unless it is so plainly erroneous or so inconsistent with either the regulation or the statute authorizing the regulation that its decision is arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law. See 5 U.S.C.A. § 706; United States v. Larionoff, 431 U.S. 864, 872-73, 97 S.Ct. 2150, 2155-2156, 53 L.Ed.2d 48 (1977); Bowles v. Seminole Rock & Sand Co., 325 U.S. 410, 414, 65 S.Ct. 1215, 1217, 89 L.Ed. 1700 (1945). As long as the agency’s interpretation is reasonable, a reviewing court cannot overrule it even though other interpretations might strike the court as more reasonable. Homan & Crimen, Inc. v. Harris, 626 F.2d 1201, 1208-09 (5th Cir.1980), motion to direct clerk to accept and docket cert. petition denied, 450 U.S. 975, 101 S.Ct. 1506, 67 L.Ed.2d 809 (1981); Expedient Services, Inc. v. Weaver, 614 F.2d 56, 57 n.1 (5th Cir.1980); Kinnett Dairies, Inc. v. Farrow, 580 F.2d 1260, 1270 (5th Cir.1978); Gillring Oil Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
699 F.2d 1088, 1983 U.S. App. LEXIS 29914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-georgia-natural-gas-company-v-federal-energy-regulatory-commission-ca11-1983.