Allegheny Def. Project v. Fed. Energy Regulatory Comm'n

932 F.3d 940
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 2, 2019
Docket17-1098; C/w 17-1128, 17-1263, 18-1030
StatusPublished
Cited by2 cases

This text of 932 F.3d 940 (Allegheny Def. Project v. Fed. Energy Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allegheny Def. Project v. Fed. Energy Regulatory Comm'n, 932 F.3d 940 (D.C. Cir. 2019).

Opinions

Concurring opinion filed by Circuit Judge Millett.

Per Curiam:

*943In February 2017, the Federal Energy Regulatory Commission approved a natural gas pipeline expansion called the Atlantic Sunrise Project, which stretches from northern Pennsylvania, across the Carolinas, and into Alabama. Environmental Associations whose members live and work in the areas affected by the Project and individual Homeowners whose property was used for the Project seek review of the Commission's orders permitting the Transcontinental Gas Pipe Line Company to move forward with the pipeline expansion. Because the challenges to the Commission's decision cannot surmount the deferential standards of agency review and binding circuit precedent, we deny the petitions.

I

A

Under the Natural Gas Act, 15 U.S.C. § 717 et seq ., a company wishing to construct a natural gas pipeline must first obtain a certificate of "public convenience and necessity" from the Federal Energy Regulatory Commission. See id . § 717f(c); Myersville Citizens for a Rural Community, Inc. v. FERC , 783 F.3d 1301, 1307 (D.C. Cir. 2015). The Commission "shall * * * issue[ ]" the certificate if it finds that the proposed project "is or will be required by the present or future public convenience and necessity." 15 U.S.C. § 717f(e).

When a pipeline company files a certificate application, the Commission reviews it under criteria set forth in its Certificate Policy Statement, 88 FERC ¶ 61,227 (1999), clarified , 90 FERC ¶ 61,128, further clarified , 92 FERC ¶ 61,094 (2000). The Certificate Policy Statement directs the Commission to consider whether the project meets a market need and whether the public benefits of the project outweigh the harms. See Sierra Club v. FERC , 867 F.3d 1357, 1379 (D.C. Cir. 2017). If market need and public benefit are both established, the Commission will issue a certificate authorizing the pipeline's construction. Id . Once that certificate is granted, the Natural Gas Act empowers the private certificate holder to exercise eminent domain authority if it "cannot acquire by contract, or is unable to agree with the owner of property to the compensation to be paid for, the necessary right-of-way to *944construct, operate, and maintain a pipeline[.]" 15 U.S.C. § 717f(h).

A party wishing to challenge the Commission's issuance of a certificate of public convenience and necessity must file a petition for rehearing with the Commission. 15 U.S.C. § 717r(a). Until the Commission disposes of that rehearing petition, the agency action is not final for purposes of judicial review. See id. § 717r(a) - (b) ; Clifton Power Corp. v. FERC , 294 F.3d 108, 110-111 (D.C. Cir. 2002). The filing and disposition of such a rehearing petition is thus a mandatory prerequisite to obtaining judicial review of the Commission's action. See Delaware Riverkeeper Network v. FERC , 857 F.3d 388, 399 (D.C. Cir. 2017) ; Clifton Power Corp. , 294 F.3d at 110-111. Congress directed that petitions for rehearing may be "deemed to have been denied" if the Commission has not "act[ed] upon the application for rehearing within thirty days after it is filed[.]" 15 U.S.C. § 717r(a).

The National Environmental Policy Act ("NEPA"), 42 U.S.C. § 4321 et seq. , "require[s] the Commission to consider and disclose the environmental effects of the actions it certifies." Delaware Riverkeeper Network , 857 F.3d at 394 (internal quotation marks omitted). The Commission may fulfill this requirement by compiling an Environmental Impact Statement, which must consider, among other things, the proposed project's "indirect" environmental effects. See 42 U.S.C. § 4332(C) ; 40 C.F.R. §§ 1508.8, 1508.25(c).

B

In March 2015, the Transcontinental Gas Pipe Line Company ("Transco") applied for a certificate of public convenience and necessity to build the Atlantic Sunrise Project. After notice and public comment, the Commission issued a final Environmental Impact Statement in December 2016. In that Statement, the Commission concluded that "neither construction nor operation of the Project would significantly contribute to [greenhouse-gas] cumulative effects or climate change." J.A. 323.

On February 3, 2017, the Commission granted Transco its requested certificate of public convenience and necessity. 158 FERC ¶ 61,125 (2017) ("Certificate Order"). Environmental Associations and the private Homeowners whose land would become subject to an easement for the Project both filed petitions for rehearing with the Commission, along with motions for a stay of construction pending disposition of their petitions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allegheny Defense Project v. FERC
964 F.3d 1 (D.C. Circuit, 2020)
United States v. John Kitzelman
140 F. App'x 931 (Eleventh Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
932 F.3d 940, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allegheny-def-project-v-fed-energy-regulatory-commn-cadc-2019.