New York State Electric & Gas Corp. v. Federal Energy Regulatory Commission

177 F.3d 1037, 336 U.S. App. D.C. 204, 1999 U.S. App. LEXIS 11368
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 4, 1999
DocketNo. 97-1430
StatusPublished
Cited by6 cases

This text of 177 F.3d 1037 (New York State Electric & Gas Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New York State Electric & Gas Corp. v. Federal Energy Regulatory Commission, 177 F.3d 1037, 336 U.S. App. D.C. 204, 1999 U.S. App. LEXIS 11368 (D.C. Cir. 1999).

Opinion

Opinion for the Court filed by Circuit Judge ROGERS.

ROGERS, Circuit Judge:

New York State Electric & Gas Corporation (“NYSEG”), a customer of Columbia Gas Transmission Company (“Columbia”), petitions for review of two orders by the Federal Energy Regulatory Commission, allowing Columbia to build additional facilities on its pipeline system and finding that absent changed circumstances Columbia may roll-in the cost of the expansion into systemwide rates in its next rate case. See Columbia Gas Transmission Corp., 78 F.E.R.C. ¶ 61,030 (1997), reh’g denied, 79 F.E.R.C. ¶ 61,160 (1997). Although Columbia proceeded under section 7 of the Natural Gas Act (“NGA”), 15 U.S.C. § 717f (1994), NYSEG contends that because the Commission established a presumption in favor of Columbia rolling-in the cost of its new facilities at its next section 4 rate proceeding, the Commission erred by failing to proceed under section 4. See 15 U.S.C. § 717c (1994). Because this appeal is not ripe for review, we dismiss NYSEG’s petition without reaching the merits of its contentions.

I.

In February 1996, Columbia filed an application under NGA section 7 to construct and expand its pipeline operations, as well as abandon certain pipelines and lease firm capacity from Texas Eastern Transmission Corporation (“Texas Eastern”) at an estimated cost of $350 million.1 Columbia further sought an “upfront determination that it may roll the costs associated with the Expansion Project into its systemwide Part 284 rates in its next rate case,” rather than impose such charges “incrementally,” ie. solely on expansion facility customers. See Columbia Gas, 78 F.E.R.C. at 61,117. The Commission agreed, relying on its Pricing Policy Statement, which established a presumption in [1039]*1039favor of rolled-in rates where the rate impact is five percent or less and the pipeline shows specific system-wide operational and financial benefits to its customers. See id. at 61,119; see also Pricing Policy for New and Existing Facilities Constructed by Interstate Natural Gas Pipelines, 71 F.E.R.C. ¶ 61,241, at 61,916-17 (1995), reh’g denied, 75 F.E.R.C. ¶ 61,-105 (1996). Finding that Columbia’s project met these criteria, the Commission determined that Columbia could “roll-in” its costs associated with the expansion project “in Columbia’s next rate proceeding unless there has been a significant change from the facts and circumstances underlying this order.” Columbia Gas, 78 F.E.R.C. at 61,124.

In rejecting NYSEG’s arguments that Columbia’s rate impact study was flawed and that a substantial part of its operational benefits were withdrawn, the Commission concluded that Columbia had sufficiently demonstrated that the rate impact of the Expansion Project was below the five percent threshold and that Columbia had “shown ample operational and financial benefits to its system.”2 Id. at 61,119. Hence, the Commission ruled, the burden of proof shifted to the objecting customer to show that the benefits of rolled-in pricing were so “insignificant” that such rates were not justified. Id. The Commission found that NYSEG had not met this burden, because Columbia’s impact study had relied on appropriate considerations and “not all customers must benefit equally to justify rolled-in' rate treatment.” Id. It therefore preliminarily determined that Columbia could proceed with its expansion project, subject to environmental review and issuance of a final order. Id. at 61,-124.

On rehearing NYSEG challenged the Commission’s determinations on several grounds, including that the policy statement provided an insufficient basis on which the Commission could evaluate the merits of Columbia’s application, that the Commission failed to consider its precedent, that the impact determination was unsupported by record evidence and based on an inflationary scheme that encouraged uneconomic investments, that the Commission’s order lacked any reasoned analysis to support the finding of benefits to existing customers and, in any event, that the claimed benefits were illusory. The Commission found NYSEG’s challenges unpersuasive and also rejected NYSEG’s request for an evidentiary hearing because no material fact was in dispute. 79 F.E.R.C. at 61,759. The Commission then issued certificates of convenience and necessity generally authorizing Columbia to proceed with its expansion program. Id. at 61,762.

In its petition for review, NYSEG contends that the Commission’s presumption in favor of rolled-in rates will, in fact, control Columbia’s next section 4 rate case, and therefore the Commission erred by failing to follow its usual section 4 procedures with a full evidentiary hearing.3 It further maintains that the Commission acted arbitrarily and capriciously by placing the burden on customers to show that the system benefits were not sufficiently substantial to warrant rolled-in pricing and [1040]*1040by adopting five percent as a threshold for its presumption favoring rolled-in rates. Finally, it contends that the Commission failed to apply Battle Creek Gas Co. v. FPC, 281 F.2d 42, 47 (D.C.Cir.1960), and its progeny, which require the Commission when imposing rolled-in rates to identify how the new facilities are integrated into the main system and how they will benefit all the customers in the system. See also ' TransCanada PipeLines Ltd. v. FERC, 24 F.3d 305, 308 (D.C.Cir.1994). The Commission responds that the appeal is not ripe because Columbia has not yet filed a section 4 rate case, nor has the Commission actually approved rolled-in rates.

II.

A claim is unripe for review when it rests “upon contingent future events that may not occur as anticipated, or indeed may not occur at all.” Texas v. United States, 523 U.S. 296, -, 118 S.Ct. 1257, 1259, 140 L.Ed.2d 406 (1998) (quotation marks omitted).

The primary focus of the ripeness doctrine as applied to judicial review of agency action “has been a prudential attempt to time review in a way that balances the petitioner’s interest in prompt consideration of allegedly unlawful agency action against the agency’s interest in crystallizing its policy before that policy is subjected to judicial review and the court’s interests in avoiding unnecessary adjudication and in deciding issues in a concrete setting.”

Mississippi Valley Gas Co. v. FERC, 68 F.3d 503, 508 (D.C.Cir.1995) (quoting Eagle-Picher Indus, v. EPA, 759 F.2d 905, 915 (D.C.Cir.1985)). To evaluate ripeness, a court must therefore consider “both the fitness of the issues for judicial decision and the hardship to the parties of withholding court consideration.” Texas, 118 S.Ct. at 1260 (quoting Abbott Labs. v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967)); see also Tennessee Gas Pipeline Co. v. FERC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
177 F.3d 1037, 336 U.S. App. D.C. 204, 1999 U.S. App. LEXIS 11368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-york-state-electric-gas-corp-v-federal-energy-regulatory-commission-cadc-1999.