Tennessee Gas Pipeline Company, a Division of Tenneco, Inc. v. Federal Energy Regulatory Commission

736 F.2d 747, 237 U.S. App. D.C. 138, 1984 U.S. App. LEXIS 21964
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 1, 1984
Docket83-1925
StatusPublished
Cited by49 cases

This text of 736 F.2d 747 (Tennessee Gas Pipeline Company, a Division of Tenneco, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Company, a Division of Tenneco, Inc. v. Federal Energy Regulatory Commission, 736 F.2d 747, 237 U.S. App. D.C. 138, 1984 U.S. App. LEXIS 21964 (D.C. Cir. 1984).

Opinion

GINSBURG, Circuit Judge:

In Middle South Energy, Inc., 23 FERC (CCH) ¶ 61,277 (May 24, 1983) (hereafter, Middle South), an adjudicatory proceeding under the Federal Power Act, 16 U.S.C. §§ 791a-825r (1982) (FPA), the Federal Energy Regulatory Commission (Commission or FERC) rendered a novel decision. Rejecting a longstanding position on which a Commission interpretative rule (18 C.F.R. § 2.4 (1983)) rested, FERC held it had authority to suspend initial rates filed under the FPA. FERC’s Middle South adjudication is now pending our decision on judicial review. 1 On the day FERC released its revised FPA interpretation in the Middle South adjudication, the Commission also amended two interpretative rules. See Interpretation of Authority to Suspend Initial Rate Schedules, III FERC Statutes & Regulations (CCH) ¶ 30,456 (May 24, 1983) (final rules); 24 FERC (CCH) ¶ 61,205 (Aug. 1, 1983) (order denying rehearing). FERC conformed its FPA interpretative rule to its holding in Middle South. See 48 Fed.Reg. 24,361 (1983) (to be codified at 18 C.F.R. § 2.4). In addition, FERC made a corresponding change in the parallel Natural Gas Act, 15 U.S.C. §§ 717-717w (1982) (NGA), interpretative rule. See 48 Fed.Reg. 24,361 (1983) (to be codified at 18 C.F.R. § 2.52). This case, pursued by Tennessee Gas Pipeline Company (Tennessee), involves a challenge to the Commission’s NGA interpretative rule change.

FERC presents a threshold objection to Tennessee’s petition for review. The Commission states that its new NGA interpretative rule has “no definitive impact on the rights of anyone” and is therefore not an independently reviewable action. Brief for the Respondent Federal Energy Regulatory Commission at 15 n. 5 (FERC Brief). 2 We conclude that the alleged “hardship” imposed on Tennessee by FERC’s action lacks the concrete quality and immediacy necessary to invoke judicial review of an agency’s bare interpretative statement on the meaning of a statutory text. See Abbott Laboratories v. Gardner, 387 U.S. 136, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967); Toilet Goods Association, Inc. v. Gardner, 387 U.S. 158, 87 S.Ct. 1520, 18 L.Ed.2d 697 (1967); Gardner v. Toilet Goods Association, Inc., 387 U.S. 167, 87 S.Ct. 1526, 18 L.Ed.2d 704 (1967); see also South Carolina Electric & Gas Co. v. ICC, 734 F.2d 1541 (D.C.Cir.1984); Baltimore Gas & Electric Co. v. ICC, 672 F.2d 146 (D.C.Cir.1982). We therefore dismiss Tennessee’s petition for want of a question ripe for review.

We recognize, however, as does the Commission, FERC Brief at 15 n. 5, that the FPA and NGA are similarly designed statutes. A court determination in an FPA adjudication may bear significantly on the appropriate construction of the NGA. See, e.g., Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, 577 n. 7, 101 S.Ct. 2925, 2930 n. 7, 69 L.Ed.2d 856 (1981). Because Tennessee has an evident interest in the latter statute’s construction and application, we will accept Tennessee’s presentation in this case as the submission of an amicus curiae in our review of FERC’s Middle South adjudication.

*749 Two, now black letter, criteria govern ripeness determinations: “the fitness of the issues for judicial decision and the hardship to the parties of withholding court consideration.” Abbott Laboratories v. Gardner, 387 U.S. at 149, 87 S.Ct. at 1515; see Air New Zealand, Ltd. v. CAB, 726 F.2d 832, 835-37 (D.C.Cir.1984); Arkansas Power & Light Co. v. ICC, 725 F.2d 716, 724-26 (D.C.Cir.1984). Tennessee’s petition does not focus on particular NGA applications; it addresses the agency’s attempt to locate congressional intent with regard to the NGA’s governance of initial rates generally, and thus meets the “fitness ... for judicial decision” criterion. See Abbott Laboratories v. Gardner, 387 U.S. at 149, 87 S.Ct. at 1515 (legal issues fit for review where “both sides have approached [the] case as one purely of congressional intent”); Baltimore Gas & Electric Co. v. ICC, 672 F.2d at 149 (same). But the “fitness” of an agency’s interpretative ruling for abstract review, while a commonly-met factor when administrators state their advice on what a statute means, does not serve as the critical test in cases of this kind. Mindful of the Constitution’s “case or controversy” limitation on our authority, see Regional Rail Reorganization Act Cases, 419 U.S. 102, 138, 95 S.Ct. 335, 355, 42 L.Ed.2d 320 (1974), 3 we must attentively inquire whether Tennessee has shown current “hardship” to its operations as a result of FERC’s newly-made interpretation. See South Carolina Electric & Gas Co., supra, at 1544-1547.

Tennessee argues that the Commission’s officially-announced view — that, under section 4 of the NGA, it can suspend initial rate schedules, set interim rates during the suspension period, and subject once-suspended or interim rates to contingent refund obligations — has a significant immediate impact on Tennessee’s planning “because of the uncertainties which the new interpretation adds to the regulatory process in general and to the acceptability of certificates of public convenience and ne-' cessity issued to Tennessee, in particular.” Brief of Petitioner Tennessee Gas Pipeline Company at 13. Tennessee describes elaborately the uncertainties it urges in support of judicial review in advance of any Commission attempt to apply the new rule to Tennessee. See id. at 33-37; Reply Brief of Petitioner Tennessee Gas Pipeline Company at 3-10.

Prior to offering a new gas transmission service, a pipeline company is generally required to apply for a certificate of public convenience and necessity authorizing the new service. As Tennessee points out, under section 7(e) of the NGA, 15 U.S.C. § 717f(e) (1982), the Commission has discretionary authority to condition the grant of certificates on initial prices that are “in keeping with the public convenience and necessity.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eternal Word Television Network, Inc. v. Sebelius
935 F. Supp. 2d 1196 (N.D. Alabama, 2013)
Roman Catholic Diocese v. Sebelius
927 F. Supp. 2d 406 (N.D. Texas, 2013)
Persico v. Sebelius
919 F. Supp. 2d 622 (W.D. Pennsylvania, 2013)
Zubik v. Sebelius
911 F. Supp. 2d 314 (W.D. Pennsylvania, 2012)
Wheaton College v. Sebelius
887 F. Supp. 2d 102 (District of Columbia, 2012)
Belmont Abbey College v. Sebelius
878 F. Supp. 2d 25 (District of Columbia, 2012)
National Ass'n of Home Builders v. U.S. Army Corps of Engineers
311 F. Supp. 2d 91 (District of Columbia, 2004)
NY St Elec & Gas v. FERC
177 F.3d 1037 (D.C. Circuit, 1999)
Chamber of Commerce of US v. Reich
886 F. Supp. 66 (District of Columbia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
736 F.2d 747, 237 U.S. App. D.C. 138, 1984 U.S. App. LEXIS 21964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-company-a-division-of-tenneco-inc-v-federal-cadc-1984.