Alabama Municipal Distributors Group v. Federal Energy Regulatory Commission

312 F.3d 470, 354 U.S. App. D.C. 101, 157 Oil & Gas Rep. 875, 2002 U.S. App. LEXIS 27390
Court of Appeals for the D.C. Circuit·Decided December 17, 2002·No. No. 01-1299·Published·Cited by 12 cases

Opinion

Opinion for the Court filed By Senior Circuit Judge WILLIAMS.

STEPHEN F. WILLIAMS, Senior Circuit Judge:

Petitioners either are purchasers or represent purchasers of gas transported on Southern Natural Gas Company’s pipeline system. They protest the Federal Energy Regulatory Commission’s grant to Southern of a certificate of public convenience and necessity for construction and operation of pipeline facilities intended to provide fuel to Southern Company Services (“SCS”) for some new gas-fired power facilities planned by SCS for Alabama. See § 7(c)(1)(A) of the Natural Gas Act, 15 U.S.C. § 717f(e)(1)(A) (requiring certification for new service). Their specific objection is to FERC’s having certificated the transaction at discount rates, lower than those paid by petitioners. We dismiss the petition for want of jurisdiction.

* * *

In deciding exactly where to locate new gas-fired electric generation facilities, SCS sought to have the gas delivered as economically as possible. At least two potential carriers were available, Southern and Transcontinental Gas Pipe Line Corporation. Competition between the two carriers evidently ensued — or so FERC concluded, over objections by petitioners that the appearance of competition was illusory. Hence in seeking certification Southern claimed that it could not have won the SCS business without offering discounted rates. The Commission was persuaded, and approved Southern’s application for a certificate embodying the proposed initial rates. Southern Natural Gas Co., 94 FERC ¶ 61,297, 2001 WL 275016, order on reh’g, 95 FERC ¶ 61,220, 2001 WL 537615 (2001).

At the outset FERC and a group of intervenors (SCS, Southern and another pipeline) raise jurisdictional issues. FERC questions petitioners’ standing, specifically whether they have suffered or are in imminent peril of suffering injury in fact — “invasion of a legally protected interest which is (a) concrete and particularized ... and (b) ‘actual and imminent, not conjectural or hypothetical.’ ” Lujan v. Defenders of Wildlife, 504 U.S. 555, 560, 112 S.Ct. 2130, 2136, 119 L.Ed.2d 351 (1992) (citations omitted). And the intervenors argue that petitioners’ claims are unripe, a claim that the court could in fact raise on its own. Reno v. Catholic Soc. Servs., Inc., 509 U.S. 43, 57 n. 18, 113 S.Ct. 2485, 2495 n. 18, 125 L.Ed.2d 38 (1993). The ripeness inquiry is familiar: we must evaluate the “fitness of the issues for judicial decision [472]*472and the hardship to the parties of withholding court consideration.” Abbott Laboratories v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 1515-16, 18 L.Ed.2d 681 (1967). The two issues overlap significantly, as we shall see. The contingencies that stand between the orders here and any injury to petitioners tend both to show the injury’s lack of imminence and to render their claim unripe.

As one basis for standing, petitioners claim that FERC’s allegedly improper certification will raise demand for gas in the region, and thus the prices they will pay for gas. But they are unable to demonstrate any connection between the allegedly improper FERC action and higher prices. It is likely true that construction and operation of the SCS facility will increase the regional demand for gas. But petitioners nowhere suggest that SCS was contemplating use of any other fuel for its new facilities; indeed, the assumption that SCS had already settled on gas was the basis for petitioners’ proclaiming that the case raised fundamental issues of gas-on-gas competition. See Petitioners’ Initial Br. at 3-4. Nor do petitioners suggest that without a discount SCS might have completely abandoned any plan for new generation facilities. So the only way Southern’s transportation discount could raise demand would be if it were to cause SCS’s delivered gas costs to be lower than they would otherwise have been, and thus its electricity prices to be ever so slightly lower than they would have been, thereby driving up electricity consumption, and with it gas consumption, compared to what they would have been without the discount. But petitioners have not even mentioned this possibility, much less offered supporting empirical analysis. So we need not decide whether the possible effect is sufficiently non-speculative to support standing. See Florida Audubon Soc’y v. Bentsen, 94 F.3d 658, 667-68 (D.C.Cir.1996) (en banc).

At oral argument petitioners hinted at a related theory of standing based on direct competitive injury — specifically, that the lower electricity costs that might result from this discount could prompt consumers to choose electricity over gas for their energy needs. But petitioners never made such an argument in their briefs, and have given us no evidence of such competitive injury. Their mere invocation of the concept in response to a question from the bench is not an adequate basis for standing.

Petitioners also assert that the Commission’s action here will adversely affect them as users of Southern’s transportation services. Here an initial hurdle to their claim of injury is their acknowledgement that they will ultimately benefit from Southern’s service to SCS. Because a carrier’s unit rate is normally determined by dividing its total throughput into its “revenue requirements” (i.e., total cost), see Interstate Natural Gas Ass’n of America v. FERC, 285 F.3d 18, 56 (D.C.Cir.2002) (“INGAA”), an increase in throughput will decrease the unit rate, unless there is a more-than-offsetting rise in average costs. As there is no evidence of such a rise in average costs, it appears undisputed that once Southern adopts system rates reflecting the new service, the effect will be to reduce petitioners’ rates.

Thus petitioners’ claim is not that they will be worse off under the Commission orders than if there were no SCS-Southern transaction, but that they will be worse off than under a Commission decision by which Southern carried the SCS gas but at a lower discount or none at all. This argument draws on the Commission’s practice of making “discount adjustments.” In dividing throughput into cost to yield a unit rate, the Commission makes a down[473]*473ward adjustment to the volume of throughput expected under a discount, to reflect the reality that its contribution to revenue will be lower than that of a similar volume carried under undiscounted rates. INGAA, 285 F.3d at 56. But the Commission grants these adjustments only if it finds the discount to have been required by competitive conditions. See Williston Basin Interstate Pipeline Co., 67 FERC ¶ 61,137 at 61,378-80, 1994 WL 235474 (1994), order on reh’g, 71 FERC ¶ 61,019, 1995 WL 148310 (1995). Some critics of the Commission contend that where the only competition is from another gas pipeline — as is evidently true here — this constraint on discounts and discount adjustments is not enough.

Free access — add to your briefcase to read the full text and ask questions with AI

Alabama Municipal Distributors Group v. Federal Energy Regulatory Commission, 312 F.3d 470, 354 U.S. App. D.C. 101, 157 Oil & Gas Rep. 875, 2002 U.S. App. LEXIS 27390 (D.C. Cir. 2002).

312 F.3d 470 (Alabama Municipal Distributors Group v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related