Pngts Shippers' Group v. Federal Energy Regulatory Commission

592 F.3d 132, 389 U.S. App. D.C. 79, 2010 U.S. App. LEXIS 1644
Court of Appeals for the D.C. Circuit·Decided January 26, 2010·No. 09-1029·Published·Cited by 7 cases

Opinion

Opinion for the Court by Circuit Judge ROGERS.

ROGERS, Circuit Judge:

Shippers with long-term (twenty-year) firm contracts on the Portland Natural Gas Transmission System (“PNGTS”) petition for review of two orders of the Federal Energy Regulatory Commission (“FERC”) certifying PNGTS’s capacity. The Shippers’ Group contends FERC’s determination was arbitrary and capricious because FERC failed to take into account the potential economic impact of a reduction in capacity. Noting the pipeline’s historical capacity and an “at-risk” condition imposed by FERC on PNGTS, the shippers fear that their rates will increase as a result of the reduction. In the challenged orders, however, FERC concluded that any potential impact on rates would be better addressed in PNGTS’s subsequent rate case. Portland Natural Gas Transmission Sys., 123 F.E.R.C. ¶ 61,275, 2008 WL 2468823 (June 19, 2008) (“Declaratory Order”), reh’g denied, 125 F.E.R.C. ¶61,-198, 2008 WL 4938325 (Nov. 18, 2008) (“Rehearing Order”). Because the shippers cannot show an actual or imminent injury as a result of the challenged orders, they are not aggrieved pursuant to section 19(b) of the Natural Gas Act, 15 U.S.C. § 717r(b). Accordingly, the court lacks jurisdiction and the petition for review must be dismissed.

I.

The Natural Gas Act provides that pipelines must obtain a certificate of public convenience and necessity before they can construct, acquire, or operate interstate natural gas pipeline facilities. 15 U.S.C. § 717f(c). Facilities subject to FERC’s jurisdiction or services rendered by such facilities may not be abandoned without FERC’s prior approval, based on a finding that the available supply of natural gas is depleted or that the present or future public convenience and necessity permit abandonment. § 717f(b); see 18 C.F.R. §§ 157.1-.22 (Part 157, Subpart A). A pipeline, however, may file a petition for a declaratory order “to terminate a controversy or remove uncertainty.” 18 C.F.R. § 385.207(a)(2). PNGTS filed such a petition in 2008 in view of several orders by FERC addressing the construction of two pipelines.

In the Declaratory Order now challenged by the Shippers’ Group, FERC summarized the background to its decision. In July 1996 FERC issued preliminary determinations in two proceedings in which PNGTS and Maritimes & Northeastern Pipeline, LLC (“Maritimes”) sought authorization to construct pipeline facilities in the Northeastern United States. Declaratory Order ¶ 3. Because the southern portion of each proposed pipeline “would run along essentially the same route, [FERC] urged the pipelines to consider jointly owning pipeline where their proposed routes converged.” Id. They did and subsequently they filed an additional application to construct jointly a 101-mile long, thirty-inch diameter pipeline extending from Westbrook, Maine, to Dracut, Massachusetts, as well as various laterals (“joint facilities”).

In July 1997 FERC made a preliminary determination, pending favorable environmental review, authorizing PNGTS to con *134 struct and operate an individually owned 142-mile long, 24-inch diameter pipeline from the Canadian border near Pittsburg, New Hampshire to Westbrook, Maine, as well as facilities jointly owned with Mari-times from Westbrook, Maine to Wells, Maine. At the border, PNGTS’s facilities would interconnect with facilities of Trans-Quebec & Maritimes Pipeline, Inc. (“TQM”). FERC also made a preliminary determination to authorize PNGTS to provide service using its capacity on the joint facilities from Wells, Maine and Dracut, Massachusetts, and to construct and operate the remaining joint facilities from Wells, Maine to Westbrook, Maine. FERC found:

In the first year of service, PNGTS will have a capacity of 178,000 Mcf [one thousand cubic feet] per day on its 24-inch mainline and ... 169,400 Mcf per day on the joint facilities. In subsequent years, the upstream mainline and PNGTS’ share of the joint facilities’ capacity will increase to 210,000 Mcf per day. Therefore, PNGTS must revise its initial rates to reflect billing determinants based on [these capacities].

Id. ¶ 5 (quoting Portland Natural Gas Transmission Sys., 80 F.E.R.C. ¶ 61,134 at 61,448, 1997 WL 465621 (1997)). The preliminary determination “also noted that PNGTS had not entered into contracts for the full capacity of its system and placed PNGTS at risk for the recovery of the costs for the unsubscribed capacity.” Declaratory Order ¶ 5. The increased capacity after the first year of service would result from installation of additional compression by TQM on its Canadian facilities to accommodate Maritimes’s proposal to construct upstream facilities to be placed in service after a year. FERC conditioned PNGTS’s certificate authorization on TQM receiving the necessary approvals.

In September 1997 FERC issued final certificates to PNGTS authorizing construction and operation of the individually-owned pipeline facilities between Pitts-burg, New Hampshire and Westbrook, Maine, as well as construction and operation of the joint facilities between West-brook and Wells, and the operation of the joint facilities between Wells and Dracut. The 1997 final certificate order also addressed PNGTS’s petition for rehearing on the issue of the increase in capacity and the at-risk condition after the first year. Because it was uncertain exactly when the Maritimes upstream facilities would go on line and when TQM would install its new planned compression, FERC concluded it was “premature to require PNGTS to revise its rates or to be placed at risk for higher capacity after its first year of operation,” Declaratory Order ¶ 8 (quoting Portland Natural Gas Transmission Sys., 80 F.E.R.C. ¶ 61,345 at 62,146, 1997 WL 698333 (1997)), and stated it would “review this matter when PNGTS makes its section 4 [rate] filing,” id. In December 2006 PNGTS and Maritimes filed a settlement resolving various issues involving the joint facilities, which FERC approved in part in March 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Pngts Shippers' Group v. Federal Energy Regulatory Commission, 592 F.3d 132, 389 U.S. App. D.C. 79, 2010 U.S. App. LEXIS 1644 (D.C. Cir. 2010).

592 F.3d 132 (Pngts Shippers' Group v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related