Occidental Permian Ltd. v. Federal Energy Regulatory Commission

673 F.3d 1024, 400 U.S. App. D.C. 60, 2012 WL 1003493, 2012 U.S. App. LEXIS 6184
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 27, 2012
Docket10-1381
StatusPublished
Cited by6 cases

This text of 673 F.3d 1024 (Occidental Permian Ltd. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Occidental Permian Ltd. v. Federal Energy Regulatory Commission, 673 F.3d 1024, 400 U.S. App. D.C. 60, 2012 WL 1003493, 2012 U.S. App. LEXIS 6184 (D.C. Cir. 2012).

Opinion

Opinion for the Court filed by Circuit Judge BROWN.

BROWN, Circuit Judge:

Occidental Permian (“Occidental”) and a number of its subsidiaries petition for review of final orders of the Federal Energy Regulatory Commission (“FERC”) granting negotiated rate authority to Tres Amigas, a proposed energy transmission project. Occidental argues Tres Amigas does not satisfy the criteria FERC has set out as preconditions for such authority. Because we conclude Occidental lacks standing to challenge these orders, we do not reach this question and instead dismiss the petition.

*1025 I

Tres Amigas is a multi-billion dollar energy transmission project being developed in New Mexico. Its goal is to tie together all three of the independent electrical grids in the United States. As these grids currently operate, power cannot automatically flow between them but instead must be converted at each interchange. Tres Amigas says its facility will address this problem and remove structural barriers to the movement of power across the country by providing a three-way transmission “superstation” with a transfer capability greater than all the existing interconnections combined. New technological developments will also permit Tres Amigas to move power across the grids at shorter notice and lower cost while at the same time integrating renewable sources of energy like wind and solar power. In order for any of these goals to reach fruition, though, regional utilities will themselves have to build new transmission lines connecting to Tres Amigas, at significant cost. The Tres Amigas project itself is solely an interconnection facility; like a train station without any tracks, it alone connects to nothing.

Under the Federal Power Act (“the Act”), utilities must file tariff schedules with FERC, and FERC must determine that the rates the utility' plans to charge are just, reasonable, and lawful. 16 U.S.C. §§ 824d, 824e. Traditionally, utilities and FERC rely on a cost-based pricing model when assessing the reasonableness of rates. But merchant transmission developers are unlike ordinary utilities. Transmission projects have no preexisting transmission network in which costs can be determined — they seek to create a network, not operate within one — and no captive pool of customers from which they can recoup those costs. For these reasons, FERC allows transmission developers to request permission to charge reasonable negotiated rates, rather than cost-based rates. To do so, a transmission project developer must meet a set of criteria designed to ensure that the negotiated rate authority will not lead to unjust rates: among other things, the developer must have no captive customers, must not have the ability to exercise monopoly power, and must bear the full market risk of the project failing. See Chinook Power Transmission, LLC, 126 FERC ¶ 61,134, 61,765 (2009); TransEnergie U.S., Ltd., 91 FERC ¶ 61,230, 61,838-39 (2000).

In December 2009, Tres Amigas filed an application with FERC requesting authorization to sell transmission services at negotiated rates. In its application, Tres Amigas explained that it cannot realistically use cost-based pricing because it has no captive customers and, because its beneficiaries will be in all three grid regions, it will have no regional transmission organization in which it can recover costs or determine cost-based rates. Occidental filed a motion to intervene, protest, and request summary denial of Tres Amigas’s application. It argued that Tres Amigas failed to meet the Chinook criteria because Tres Amigas has captive customers and would exercise monopoly power while bearing none of the project’s risk. FERC found that Occidental’s concerns were misplaced and approved Tres Amigas’s request over Occidental’s objections in March 2010. Tres Amigas LLC, 130 FERC ¶ 61,207 (2010). Occidental requested a rehearing, and FERC denied that request in September 2010. Tres Amigas LLC, 132 FERC ¶ 61,233 (2010). This petition for review followed.

II

Before we may reach the merits of Occidental’s objection, we must first be satisfied that Occidental has standing to challenge these orders. Pub. Util. Dist. *1026 No. 1 of Snohomish Cnty. v. FERC, 272 F.3d 607, 613 (D.C.Cir.2001). The “irreducible constitutional minimum” of standing requires a petitioner to show a concrete injury that has either transpired or is “imminent,” that is causally connected to the agency action, and that will likely be redressed by a favorable decision from this Court. Lujan v. Defenders of Wildlife, 504 U.S. 555, 560-61, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992). A “conjectural or hypothetical” injury will not do. Id. at 560, 112 S.Ct. 2130. Occidental advances three possible injuries it has suffered as a result of FERC’s orders approving negotiated rate authority for Tres Amigas. All are conjectural or hypothetical. Because none meets the constitutional standard, we lack jurisdiction and dismiss Occidental’s petition.

First, Occidental complains that neighboring utilities will themselves have to build transmission lines to connect to Tres Amigas. Those utilities will, Occidental argues, in turn recover the costs of that construction and connection from regional energy consumers like some of Occidental’s subsidiaries. These subsidiaries and other captive customers will thus face higher rates along those transmission lines. This parade of horribles is far too speculative to represent a “concrete” injury to Occidental. Lujan, 504 U.S. at 560, 112 S.Ct. 2130. Even if all of these additional events transpired, Occidental’s injury would be caused by some action other than FERC’s approval of the orders before us.

Occidental’s alleged injury necessarily relies on the premises that neighboring utilities will in fact build connecting transmission lines to Tres Amigas, and that they will recover costs from captive customers, and that doing so will mean higher rates for Occidental’s subsidiaries. None of these eventualities is about to occur. First, it remains possible that no neighboring utility will successfully build a transmission line that connects to Tres Amigas. Though some utilities have apparently “stated their willingness” to do so, Pet. Br. 16, even the most enthusiastic of plans would not give rise to Occidental’s injury since, as Occidental recognizes, those utilities’ plans are “subject to appropriate support and favorable ratemaking treatment from ... regulators,” Payton Aff. ¶ 16 (quoting an interested utility describing its support for the project). No such support has materialized. Those connecting utilities have yet to secure siting and planning approvals, and FERC has made no decision, favorable or otherwise, regarding the rates those connecting utilities would be able to charge their customers.

Even if we knew with certainty that a given utility was going to connect to Tres Amigas, the remaining links in Occidental’s chain of injury remain uncertain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LSP Transmission Holdings II, LLC v. FERC
45 F.4th 979 (D.C. Circuit, 2022)
Coalition of MISO Transmission v. FERC
45 F.4th 1004 (D.C. Circuit, 2022)
Wildearth Guardians v. Salazar
859 F. Supp. 2d 83 (District of Columbia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
673 F.3d 1024, 400 U.S. App. D.C. 60, 2012 WL 1003493, 2012 U.S. App. LEXIS 6184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/occidental-permian-ltd-v-federal-energy-regulatory-commission-cadc-2012.