Exxon Mobil Corp. v. Federal Energy Regulatory Commission

571 F.3d 1208, 387 U.S. App. D.C. 125, 2009 U.S. App. LEXIS 14947, 2009 WL 1930170
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 7, 2009
Docket07-1306, 07-1309, 07-1310, 07-1335, 07-1351
StatusPublished
Cited by21 cases

This text of 571 F.3d 1208 (Exxon Mobil Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exxon Mobil Corp. v. Federal Energy Regulatory Commission, 571 F.3d 1208, 387 U.S. App. D.C. 125, 2009 U.S. App. LEXIS 14947, 2009 WL 1930170 (D.C. Cir. 2009).

Opinion

Opinion for the Court filed by Circuit Judge GRIFFITH.

GRIFFITH, Circuit Judge:

Here we review the competing claims of six independent electric power generators and three public utility companies, each dissatisfied with the manner in which the Federal Energy Regulatory Commission resolved an unusual problem involving an application of its interconnection pricing policies. The Generators filed complaints with FERC, seeking to recover from several utilities funds paid to cover the cost to interconnect to the utilities’ transmission systems. Arguing that these funds were a loan to improve the utilities’ systems, the Generators sought a credit against charges for future transmission service. FERC agreed in part and awarded the Generators a partial refund in the form of credits. But the amount awarded was not enough, in the Generators’ view, and they now ask us to review FERC’s decision. Three of the utility companies that would be required to issue the transmission credits are also dissatisfied with the outcome and likewise seek review, arguing FERC was without authority to award any credits. Because we find FERC’s decision reasonable, we deny the Generators’ petitions. We dismiss the Utilities’ petitions because they lack standing.

I.

We begin with a description of the context in which the parties’ competing claims arise: a complex web of statutory provisions, regulations, agency and judicial precedent, and economic principles that is typical of federal energy law.

Statutory Background

Section 201 of the Federal Power Act (FPA), 16 U.S.C. § 824(b) (2006), grants FERC exclusive jurisdiction over the transmission and sale of electric energy in interstate commerce. Section 205 requires every public utility to file with FERC a schedule that includes the rates charged to customers for the transmission or sale of energy. Id. § 824d(e). FERC must ensure the rates are “just and reasonable.” Id. § 824d(a).

Once approved, there is only one way for FERC to revisit its determination that a rate is reasonable. Section 206(a) of the FPA requires FERC, upon its own motion or the filing of a complaint, to determine whether “any rate, charge, or classification ... observed [or] charged ... by any public utility for any transmission or sale ... is unjust, unreasonable, unduly discriminatory or preferential.” Id. § 824e(a). FERC must remedy such a rate by “determining] the just and reasonable rate, charge, [or] classification ... to be thereafter observed and in force, and shall fix the same by order.” Id. FERC may not retroactively alter a filed rate to compensate for prior over-or underpayments. See Towns of Concord v. FERC, 955 F.2d 67, 71 & n. 2 (D.C.Cir.1992). A corollary to this rule against retroactive ratemaking, the filed rate doctrine, “forbids a regulated entity to charge rates for its services other than those properly filed with the appropriate federal regulatory authority.” Ark. La. Gas Co. v. Hall, 453 U.S. 571, 577, 101 S.Ct. 2925, 69 L.Ed.2d 856 (1981). Together, these rules generally limit the relief FERC may order to prospective remedies. See id. at 578, 101 S.Ct. 2925.

The FPA provides a narrow exception to the limitations imposed by these rules, under which FERC can order the refund of some past rate payments. Section 206(b) *1192 of the FPA permits FERC, when ordering prospective relief under section 206(a), to order “refunds of any amounts paid” in excess of the just and reasonable rate during a statutorily defined period. 16 U.S.C. § 824e(b). Today, this refund period begins at the latest five months after the filing of a complaint, and ends fifteen months later. Id. In short, FERC can order a refund of overcharges paid during a limited time period that begins after the filing of a complaint.

Interconnection Pricing

In what we have referred to as “the bad old days,” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1363 (D.C.Cir.2004), public utilities owned most of the nation’s electricity grid and there was little competition within wholesale electric energy markets, id. In exercising their monopoly power, these utilities refused independent electricity generators access to their transmission lines on competitive terms and conditions. See Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 681-82 (D.C.Cir. 2000).

In its landmark Order No. 888, FERC did away with the old arrangement and sought to establish competitive wholesale power markets to increase consumer welfare. See id. at 680-81; see also Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities (Order No. 888), 61 Fed.Reg. 21,540 (May 10, 1996). To achieve this goal, Order No. 888 requires that public utilities provide open access to their transmission lines on nondiscriminatory terms to any independent entity that generates or purchases electricity. Transmission Access, 225 F.3d at 681.

To take advantage of open access, generators must be able to link their plants to the utilities’ transmission systems. The process of physically connecting a generating plant to a transmission grid is called “interconnection.” Although Order No. 888 did not address interconnection, FERC has since made clear that interconnection is an indispensable component of open access that must be offered on a nondiscriminatory basis. See Tenn. Power Co., 90 F.E.R.C. ¶ 61,238, at 61,761-62 (2000).

The rates, terms, and conditions of interconnection are set forth in “interconnection agreements” between the utility that owns the transmission system and the interconnecting generator. These agreements identify the new facilities needed and what the generator must pay to achieve interconnection. The parties file their agreements with FERC for its certification that they are just and reasonable. See Entergy Servs., Inc. v. FERC, 391 F.3d 1240, 1243 (D.C.Cir.2004). The agreement’s rate for interconnection becomes a filed rate that can only be modified under the section 206 process.

FERC originally evaluated the cost allocations laid out in interconnection agreements on a case-by-case basis but over time found this approach inadequate. See Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277, 1279 (D.C.Cir.2007). In Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hecate Energy LLC v. FERC
126 F.4th 660 (D.C. Circuit, 2025)
Industrial Energy Consumers of America v. FERC
125 F.4th 1156 (D.C. Circuit, 2025)
Ameren Illinois Company v. FERC
58 F.4th 501 (D.C. Circuit, 2023)
In re: LA Pub Svc Comm
58 F.4th 191 (Fifth Circuit, 2023)
Waterkeeper Alliance, Inc. v. Michael Regan
41 F.4th 654 (D.C. Circuit, 2022)
Utility Water Act Group v. Perciasepe
714 F.3d 1317 (D.C. Circuit, 2013)
Sfpp, Lp v. Ferc
592 F.3d 189 (D.C. Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
571 F.3d 1208, 387 U.S. App. D.C. 125, 2009 U.S. App. LEXIS 14947, 2009 WL 1930170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxon-mobil-corp-v-federal-energy-regulatory-commission-cadc-2009.