Sfpp, Lp v. Ferc

592 F.3d 189, 2010 WL 135203
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 15, 2010
Docket08-1110
StatusPublished

This text of 592 F.3d 189 (Sfpp, Lp v. Ferc) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sfpp, Lp v. Ferc, 592 F.3d 189, 2010 WL 135203 (D.C. Cir. 2010).

Opinion

592 F.3d 189 (2010)

SFPP, L.P., Petitioner
v.
FEDERAL ENERGY REGULATORY COMMISSION and United States of America, Respondents
Ultramar Inc., et al., Intervenors.

No. 08-1110.

United States Court of Appeals, District of Columbia Circuit.

Argued November 13, 2009.
Decided January 15, 2010.

Charles F. Caldwell argued the cause for petitioner. With him on the briefs *190 were Catherine O'Harra and D. Ryan Nayar.

Jennifer S. Amerkhail, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were John J. Powers III and Robert J. Wiggers, Attorneys, U.S. Department of Justice, and Cynthia A. Marlette, General Counsel, and Robert H. Solomon, Solicitor.

Steven A. Adducci argued the cause for intervenors. With him on the brief were R. Gordon Gooch, Elisabeth R. Myers, George L. Weber, Thomas J. Eastment, Gregory S. Wagner, Christina M. Vitale, Marcus W. Sisk Jr., and Frederick G. Jauss IV. Joshua B. Frank entered an appearance.

Before ROGERS and GRIFFITH, Circuit Judges, and SILBERMAN, Senior Circuit Judge.

Opinion for the Court by Circuit Judge ROGERS.

ROGERS, Circuit Judge.

Following the remand in BP West Coast Products, L.L.C. v. FERC, 374 F.3d 1263, 1270-71 (D.C.Cir.2004), the Federal Energy Regulatory Commission ("FERC") ordered petitioner SFPP, L.P. ("SFPP") to pay reparations to the complaining shippers using its Watson Station drain-dry facilities. SFPP, L.P., 122 FERC ¶ 61,126 (2008) ("Order on Initial Decision"). SFPP contends that notwithstanding its failure to file the Watson Contract rates, FERC's decision was arbitrary and capricious for failing to explain why it rejected its previous findings that special circumstances justified enforcement of the unfiled rate contracts. The circumstances surrounding the shippers' agreement to the Watson Contract rates, SFPP maintains, "allay any reasonableness or discrimination concerns" and "manifestly present good cause." Pet'r's Br. 12. FERC responds that the unfiled contract rates could not supplant its authority to ensure rates are just and reasonable and that it reasonably determined the payment of reparations was an appropriate remedy. Concluding that FERC's determination of the rates was not arbitrary or capricious and that the remedy was within its discretion, we deny the petition for review.

I.

The background to this appeal appears in BP West Coast Products, 374 F.3d at 1273-74. Between 1989 and 1991, SFPP and its shippers negotiated a set of contracts for the construction of "drain-dry" facilities at Watson Station, which speeded switching between different types of petroleum products stored in SFPP's tanks. As part of the contracts, the shippers agreed to pay an additional charge per barrel of 3.2 cents to cover construction costs and provide SFPP a return on its investment in the drain-dry facilities. SFPP did not file the Watson Contract rates with FERC, concluding its drain-dry services were not jurisdictional.

Responding to complaints filed in the mid-1990s by various shippers, FERC ruled in Opinion No. 435 that although SFPP should have filed its Watson Contract rates, SFPP would not be ordered to pay reparations and the Watson Contract rates would be deemed reasonable. SFPP, L.P., 86 FERC ¶ 61,022 at 61,074-76 (1999) ("Opinion No. 435"). FERC relied on section 1803 of the Energy Policy Act of 1992 ("EPAct"), Pub.L. No. 102-486, 106 Stat. 2776, 3011, reprinted in 42 U.S.C. § 7172 note, which limited the ability of shippers to challenge pipeline rates "in effect" for a full year as of October 24, 1992 and deemed such rates, with exceptions not applicable here, just and reasonable. FERC concluded that although the Watson Contract rates were not on file, the charges for the Watson Station drain-dry facilities were the equivalent of lawful *191 rates because the rates were in effect prior to the EPAct's enactment on October 24, 1992 and the shippers had failed to establish "substantially changed circumstances," EPAct § 1803(b), 106 Stat. at 3011. See Opinion No. 435 at 61,075-76. FERC noted that the complaining shippers were sophisticated parties that negotiated sophisticated contracts, and that it would be inequitable to change the negotiated rates years after the contracts were signed. Id. at 61,075. FERC denied rehearing. SFPP, L.P., 91 FERC ¶ 61,135 at 61,502 (2000) ("Opinion No. 435-A"). FERC reasoned that "if [the rates] had been filed. . ., it is clear that they would have been grandfathered" under the EPAct, Opinion 435-A at 61,502.

This court vacated Opinion Nos. 435 and 435-A. BP West Coast Prods., 374 F.3d at 1270-71. As relevant, the court concluded that FERC's reasoning on the significance of not filing the Watson Contract rates was "fundamentally flawed" and "vacated this portion of [FERC's] order." Id. at 1274. Observing that if FERC correctly interpreted section 1803 of the EPAct only to apply to filed rates, then FERC could not grandfather unfiled rates on the assumption no challenge would have been brought. Id. Moreover, the court found FERC's reasoning afforded no assurance that all the Watson Contract rates had been in effect 365 days as of October 24, 1992. Id. The court therefore granted the petition and remanded regarding whether the rates were grandfathered. Id. at 1312.

On remand, FERC ruled that SFPP's Watson Contract rates could not be grandfathered. SFPP, L.P., 111 FERC ¶ 61,334 at 62,457 ("Order on Remand and Rehearing"). FERC found that regardless of whether the rates were filed, the Watson Contract rates became effective on November 1, 1991, less than 365 days before October 24, 1992, and thus could not be grandfathered under the EPAct. Id. at 62,458. Thereafter, SFPP and the complaining shippers settled all outstanding issues, except two legal issues, and stipulated that any reparations amount would be based on a shipping rate of between 0.48 and 0.28 cents per barrel (subtracted from the 3.2 or 3.5 cents per barrel actually charged by SFPP), plus interest, with a specific shipping rate stipulated for each year between 1991 and 2005. The two reserved legal issues were: (1) whether the Watson Contract rates established the rate level or limited reparations before April 1999, and (2) the calculation of the period for which any reparations payments would be due. FERC approved this settlement, SFPP, L.P., 116 FERC ¶ 61,116 (2006), and referred the two reserved legal issues to an Administrative Law Judge ("ALJ"), who ruled that the Watson Contract rates did not establish the rate for service because they had not been filed and that the reparation payment period for each shipper would be limited to two years before the shipper's complaint was filed, and awarded reparations to the complaining shippers in the amounts stipulated, see SFPP, L.P., 118 FERC ¶ 63,033 at 66,171-72 (2007).

Upon exceptions filed by SFPP, FERC affirmed that SFPP had violated sections 6(1) and 6(7) of the Interstate Commerce Act ("ICA") by failing to file the Watson Contract rates. See Order on Initial Decision, 122 FERC at 61,649-50. FERC noted that ICA section 6(1) requires that common carriers such as SFPP "shall file" their rates, and that ICA section 6(7) prohibits carriers from transporting property "unless the rates . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parsons v. Chicago & Northwestern Railway Co.
167 U.S. 447 (Supreme Court, 1897)
Mobil Oil Corp. v. Federal Power Commission
417 U.S. 283 (Supreme Court, 1974)
Alpharma Inc v. Leavitt, Michael
460 F.3d 1 (D.C. Circuit, 2006)
Concord Industries, Inc. v. K.T.I. Holdings, Inc.
711 F. Supp. 728 (E.D. New York, 1989)
Dan Barclay, Inc. v. Stewart & Stevenson Services, Inc.
761 F. Supp. 194 (D. Massachusetts, 1991)
Land Ocean Logistics, Inc. v. Aqua Gulf Corp.
68 F. Supp. 2d 263 (W.D. New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
592 F.3d 189, 2010 WL 135203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sfpp-lp-v-ferc-cadc-2010.