Hecate Energy LLC v. FERC

126 F.4th 660
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 21, 2025
Docket23-1089
StatusPublished
Cited by6 cases

This text of 126 F.4th 660 (Hecate Energy LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hecate Energy LLC v. FERC, 126 F.4th 660 (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 6, 2024 Decided January 21, 2025

No. 23-1089

HECATE ENERGY LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

PJM INTERCONNECTION, L.L.C., INTERVENOR

Consolidated with 23-1182

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Aaron M. Streett argued the cause for petitioner. With him on the briefs were Michael A. Yuffee, J. Mark Little, and Christopher E. Tutunjian.

Angela X. Gao, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and 2 Robert H. Solomon. Susanna Y. Chu, Attorney, entered an appearance.

Wendy B. Warren argued the cause for intervenor in support of respondent. With her on the brief were Elizabeth P. Trinkle and David S. Berman.

Before: HENDERSON, PILLARD, and CHILDS, Circuit Judges.

Opinion for the Court filed by Circuit Judge PILLARD.

PILLARD, Circuit Judge: Hecate Energy, LLC, develops and operates facilities to generate and store renewable power. It petitions for our review of two Federal Energy Regulatory Commission orders that approve comprehensive reforms proposed by PJM Interconnection, LLC, a regional transmission grid operator, to the criteria PJM uses to process requests to connect new electricity sources to the electrical grid. One issue PJM faces in processing interconnection requests is whether connecting new sources will require upgrades to the grid and, if so, how upgrade costs will be allocated among generators seeking to connect. Hecate challenges a single aspect of FERC’s orders: Its approval of PJM’s proposal to help clear its backlog of pending interconnection requests by expediting requests that are projected to be assessed upgrade costs of $5 million or less. FERC defends its orders on the merits, but it first contests Hecate’s standing to challenge the orders in court. We hold that Hecate lacks Article III standing to challenge the $5 million cap, and therefore dismiss its petitions for review. Hecate’s injury is not redressable because the relief it requests from this court—vacatur of FERC’s approval of PJM’s comprehensive reform package—is unlikely to lead to the expediting of its over-$5 million project. 3 BACKGROUND

A.

Section 205 of the Federal Power Act requires electric utilities’ rates and rules for transmitting electricity to be “just and reasonable” and not “undu[ly] preferen[tial].” 16 U.S.C. § 824d(a), (b). Under Section 205 and the Federal Energy Regulatory Commission’s (FERC or Commission) implementing regulations, when a regional transmission organization like PJM seeks to change any rates or rules, it must file the proposed changes with the Commission. Id. § 824d(d); 18 C.F.R. § 35.34(j)(1)(iii). “FERC must accept proposed rate changes filed under Section 205 so long as the changes are just and reasonable” and not unduly discriminatory. NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 113 (D.C. Cir. 2017); 16 U.S.C. § 824d(a), (b).

In evaluating proposed rule changes under Section 205, FERC plays “an essentially passive and reactive role.” Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (internal quotation marks omitted). “FERC may accept or reject the proposal,” but it may not “suggest modifications that result in an entirely different rate design than the utility’s original proposal or the utility’s prior rate scheme.” NRG Power, 862 F.3d at 114-15 (internal quotation marks omitted). The Commission may not propose modifications that “und[o] the compromise that had been the basis for [the] proposal” or “eviscerate[] the terms of the bargain” underlying the original proposal. Id. at 116.

B.

PJM is a regional transmission organization—an independent, non-profit, FERC-approved entity that manages the electrical grid covering parts of 13 Mid-Atlantic and 4 Midwestern states and the District of Columbia. See Advanced Energy, 860 F.3d at 659. One of PJM’s responsibilities is to facilitate the interconnection of new power sources to the grid. See FPL Energy Marcus Hook, L.P. v. FERC, 430 F.3d 441, 443 (D.C. Cir. 2005). That process involves conducting multiple studies to determine what network upgrades (if any) are necessary to support the connection of new generators to the grid, and how the costs of those required upgrades—which “improve the network for the benefit of all users,” Exxon Mobil Corp. v. FERC, 571 F.3d 1208, 1212-13 (D.C. Cir. 2009)— should be allocated among the various generators seeking to connect. See Marcus Hook, 430 F.3d at 443.

For decades, PJM has used a serial, “first-come, first- served” model for acting on interconnection requests, in which “[t]he submission of an interconnection request triggers a review by [PJM] and holds the requestor’s place in the interconnection queue” until PJM conducts the requisite studies, allocates network upgrade costs, and provides the generator with a proposed interconnection service agreement. ESI Energy, LLC v. FERC, 892 F.3d 321, 325 (D.C. Cir. 2018). In recent years, that serial, “first-come, first-served” model has not kept up with the rising number of interconnection requests, leading to delays in connecting new generators to the grid.

The current system’s rules incentivize project developers to submit speculative and duplicative interconnection requests that they often withdraw late in the study process. For example, submitting an interconnection request is relatively cheap, there are few requirements for a project to keep its place in the queue, and projects may withdraw from the queue at any time with minimal financial penalty. In fact, the vast majority of interconnection requests are withdrawn before the requestor signs a final interconnection service agreement: Of requests submitted between January 2020 and February 2021, 80% were 5 withdrawn during the review process. In addition, PJM determines and assigns network upgrade costs based in part on a project’s queue position relative to other requests. For instance, if there is still enough excess capacity in the grid to accommodate the connection of another generator, a project submitted earlier in time might not have to pay for network upgrades necessitated by the connection of generators farther down in the queue. See Marcus Hook, 430 F.3d at 444. Because of that, almost every withdrawal requires PJM to re- study and potentially re-allocate network upgrade costs among the projects that remain in the queue behind the withdrawn project. Given large increases in the number of interconnection requests in recent years, the rules countenancing such a grossly inefficient cycle of withdrawals and restudies have hamstrung PJM’s ability to timely connect new generators to the grid and contributed to a backlog of 1,857 interconnection requests in various stages of study.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
126 F.4th 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hecate-energy-llc-v-ferc-cadc-2025.