Idaho Power Co. v. Federal Energy Regulatory Commission

312 F.3d 454, 354 U.S. App. D.C. 85, 2002 U.S. App. LEXIS 25724
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 13, 2002
Docket01-1314
StatusPublished
Cited by27 cases

This text of 312 F.3d 454 (Idaho Power Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Power Co. v. Federal Energy Regulatory Commission, 312 F.3d 454, 354 U.S. App. D.C. 85, 2002 U.S. App. LEXIS 25724 (D.C. Cir. 2002).

Opinion

Opinion for the Court filed by Circuit Judge EDWARDS. '

HARRY T. EDWARDS, Circuit Judge:

Petitioner, Idaho Power Company, challenges two FERC orders barring Idaho Power from entering into a 10-year contract to provide electricity to the IP Merchant Group (“IP Merchant”) from December 2000 through December 2010. See Idaho Power Co., Order Denying Petition for Declaratory Order, 94 F.E.R.C. ¶ 61,311, 2001 WL 275044 (2001) (“Order Denying Petition”); Idaho Power Co., Order Denying Rehearing and Clarifying Prior Order, 95 F.E.R.C. ¶ 61,224 (2001) (“Order Denying Rehearing”). Before receiving the ill-fated bid from IP Merchant, Idaho Power had been furnishing electric transmission service to the Arizona Public Service Company (“APS”). APS had a “right of first refusal” to match the IP Merchant bid for service from Idaho Power. In order to exercise its right of first refusal, APS had to “agree to accept a contract term at least equal to [the] competing request” offered by IP Merchant in its bid for transmission service from Idaho *456 Power. Idaho Power Company Open Access Transmission Tariff § 2.2 (“Idaho Power OATT”), Joint Appendix (“J.A.”) 230. However, because it could only seek service from Idaho Power in 18-month increments, APS was unable to match IP Merchant’s 10-year contract bid. FERC nonetheless ruled that Idaho Power was obliged to continue providing service to APS, because the “transmission service requests were not substantially the same in all respects [due to] the dissimilarity in available terms of service.” Order Denying Rehearing, 95 F.E.R.C. at 61,759. In other words, FERC reasoned that the offers by APS and IP Merchant were not “substantially the same in all respects,” and thus not competing bids, because IP Merchant offered a 10-year term while APS offered only an 18-month term. Order Denying Petition, 94 F.E.R.C. at 62,145; Order Denying Rehearing, 95 F.E.R.C. at 61,759.

FERC’s interpretation of the right of first refusal provision defies reason. Idaho Power’s Open Access Transmission Tariff (“OATT”) and FERC’s orders creating the applicable pro forma tariff provide that, in order to exercise a right of first refusal, “the existing firm service customer must agree to accept a contract term at least equal to a competing request by any new Eligible Customer.” Idaho Power OATT § 2.2, J.A. 230; Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities', Recovery of Standard Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, F.E.R.C. Stats. & Regs. ¶ 31,048 (1997) (“Order No. 888-A”). FERC has turned the Tariff and orders on their heads by suggesting that the competitor must put forward an offer identical to the incumbent’s in order for the competing bids to be “substantially the same in all respects.” Under this reasoning, the competitor is not allowed to make a better offer, which of course ensures that the incumbent never loses. This is a nonsensical construction of the “right of first refusal,” which we reject as arbitrary and capricious. Accordingly, we grant Idaho Power’s petition for review.

I. Background

A. The Pro Forma Tariff

In 1996, FERC promulgated a set of rules designed to create a more competitive environment in the electric utility industry. Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, F.E.R.C. Stats. & Regs. 31,036 (1996) (“Order No. 888”), order on reh’g, Order No. 888-A, order on reh’g, Order No. 888-B, 81 F.E.R.C. ¶ 61,248, 1997 WL 833250 (1997), order on reh’g, Order No. 888-C, 82 F.E.R.C. ¶ 61,046, 1998 WL 18148 (1998), aff'd in part and remanded in part sub nom. Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (D.C.Cir.2000), aff'd jurisdictional ruling sub nom. New York v. FERC, 535 U.S. 1, 122 S.Ct. 1012, 152 L.Ed.2d 47 (2002). These rules required each utility to separate its transmission function from its wholesale merchant function (i.e., the selling of electric power at wholesale rates). They also required each utility to file and take transmission under an OATT designed to assure access to transmission service on a non-discriminatory basis. FERC’s rules specified the terms of a pro forma tariff designed to achieve the competitive goals of Order No. 888. Order No. 888 at 31,926-64. With limited exceptions, each utility’s OATT must conform to the non-rate *457 terms and conditions specified in the pro forma tariff. Report of the Committee on Electric Utility Regulation, 18 Energy L.J. 197, 200 (1997) (“The FERC will allow deviations from the pro-forma’s terms and conditions to reflect regional practices, but these deviations are limited primarily to scheduling deadlines. With very limited exceptions, the FERC has rejected all other deviations....”). FERC revised the pro forma tariff in Order No. 888-A.

The pro forma tariff required each utility to create an Open Access Same Time Information System (“OASIS”), an electronic system for accepting transmission requests that would make them known simultaneously to all potential customers. While § 18.2 of the pro forma tariff specified that requests for long-term firm service would generally be accepted in the order in which they are received, Order No. 888-A at 30,51516, it also noted a special provision in § 2.2 for determining priority where an incumbent customer seeks to renew service. Id. at 30,516.

Section 2.2 of the tariff provided the incumbent customer with a right of first refusal to match the duration offered by a new customer at the full OATT rate. Section 2.2 provides, in relevant part:

If at the end of the contract term, the Transmission Provider’s Transmission System cannot accommodate all of the requests for transmission service the existing firm service customer must agree to accept a contract term at least equal to a competing request by any new Eligible Customer and to pay the current just and reasonable rate, as approved by the Commission, for such service.

Id. at 30,511. FERC explained in the Preamble to the pro forma tariff in Order No. 888-A that, “[bjecause the purpose of the right of first refusal provision is to be a tie-breaker, the competing requests should be substantially the same in all respects.” Id. at 30,198.

B. The Transmission Service Requests

Idaho Power provides transmission service in accordance with the rates, terms and conditions of its OATT. Idaho Power filed its OATT pursuant to FERC Order No. 888, and FERC accepted it as the filed rate. Atlantic City Elec. Co., 77 F.E.R.C. ¶ 61,144, 1996 WL 659540 (1996) (non-rate terms and conditions);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Childrens Health Defense v. FCC
25 F.4th 1045 (D.C. Circuit, 2022)
Mario Ruiz-Del-Cid v. Eric Holder, Jr.
765 F.3d 635 (Sixth Circuit, 2014)
Urban Health Care Coalition v. Sebelius
853 F. Supp. 2d 101 (District of Columbia, 2012)
Sherley v. Sebelius
District of Columbia, 2009
Gatimi v. Holder
578 F.3d 611 (Seventh Circuit, 2009)
Canadian Lumber Trade Alliance v. United States
517 F.3d 1319 (Federal Circuit, 2008)
GasPlus, L.L.C. v. United States Department of the Interior
510 F. Supp. 2d 18 (District of Columbia, 2007)
At & T Inc. v. Federal Communications Commission
452 F.3d 830 (D.C. Circuit, 2006)
Sacramento Muni Util v. FERC
428 F.3d 294 (D.C. Circuit, 2005)
PSEG Engy Resrc Trd v. FERC
360 F.3d 200 (D.C. Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
312 F.3d 454, 354 U.S. App. D.C. 85, 2002 U.S. App. LEXIS 25724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-power-co-v-federal-energy-regulatory-commission-cadc-2002.