An opinion was released in case 23-1094, NextEra Energy Resources, LLC v. FERC

118 F.4th 361
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 4, 2024
Docket23-1094
StatusPublished
Cited by4 cases

This text of 118 F.4th 361 (An opinion was released in case 23-1094, NextEra Energy Resources, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
An opinion was released in case 23-1094, NextEra Energy Resources, LLC v. FERC, 118 F.4th 361 (D.C. Cir. 2024).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued February 6, 2024 Decided October 4, 2024

No. 23-1094

NEXTERA ENERGY RESOURCES, LLC AND NEXTERA ENERGY SEABROOK, LLC, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

AVANGRID, INC. AND NECEC TRANSMISSION LLC, INTERVENORS

Consolidated with No. 23-1215

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

John N. Estes III argued the cause for petitioners. With him on the briefs were Matthew E. Price, Arjun Ramamurti, and Anand Viswanathan.

Robert M. Kennedy, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. 2 With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Eric J. Konopka argued the cause for intervenors NECEC Transmission LLC and Avangrid, Inc. in support of respondent. With him on the brief were Richard P. Bress, David L. Schwartz, and James B. Blackburn IV.

Before: MILLETT, KATSAS, and RAO, Circuit Judges.

Opinion for the Court filed by Circuit Judge KATSAS.

Dissenting opinion filed by Circuit Judge RAO.

KATSAS, Circuit Judge: The Federal Energy Regulatory Commission may regulate the transmission, but not the generation, of electricity. In this case, FERC required a generator to upgrade its circuit breaker so that another power source could safely connect to the regional transmission grid. The Commission ordered the new power source to compensate the generator for the direct costs of the upgrade, but not for its indirect costs. We hold that the agency had statutory authority to require the upgrade, correctly interpreted the governing tariff and contract to require the upgrade, and permissibly denied compensation for its indirect costs.

I

A

Supplying electricity to consumers requires three principal kinds of facilities—generators produce the electricity, transmission facilities move it over long distances, and distribution facilities move it over short distances to individual customers. Detroit Edison Co. v. FERC, 334 F.3d 48, 49 (D.C. Cir. 2003). The transmission market has high barriers to entry, 3 so transmission owners typically “enjoy a natural monopoly.” Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667, 683 (D.C. Cir. 2000) (Transmission Access).

The Federal Power Act allows FERC to regulate some, but not all, types of these facilities. Section 201(b) empowers the Commission to regulate the “transmission” and wholesale “sale” of electricity in interstate commerce, as well as “facilities” for such transmission or sale. 16 U.S.C. § 824(b)(1). But it also states that the agency, except as specifically provided, does not have jurisdiction over facilities used for the “generation,” intrastate transmission, or local distribution of electricity. Id.

The modern structure of the electricity market reflects decades of changing technology and regulations. “In the bad old days,” power grids were run by “vertically integrated monopolies” that owned generation, transmission, and distribution facilities. Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1363 (D.C. Cir. 2004). Utilities sold these services in bundled packages to customers in limited geographic areas. Pub. Util. Dist. No. 1 v. FERC, 272 F.3d 607, 610 (D.C. Cir. 2001). Eventually, technological advances made it easier to generate electricity and transmit it over long distances. See Transmission Access, 225 F.3d at 681. But transmission owners exploited their monopoly power to deny competing sellers access to their facilities. See id. at 682–84. This practice resulted in artificially high electricity prices for consumers. Id. at 682.

In 1996, FERC responded with a regulation known as Order No. 888, which required transmission owners to give other generators equal access to interstate transmission facilities. Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public 4 Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, 61 Fed. Reg. 21,540 (May 10, 1996). Among other things, the Commission required transmission owners to “file open access nondiscriminatory tariffs” for wholesale transmission service, thus effectively “unbundling” sale of the power itself from sale of the transmission service. See Detroit Edison, 334 F.3d at 50. In Transmission Access, this Court upheld Order No. 888 “in nearly all respects.” 225 F.3d at 681.

Implementation of Order No. 888 proved challenging. “[E]very time a new generator of electricity asked to use a transmission network owned by another—to interconnect the two entities—disputes between the generator and the owner of the transmission grid would arise,” thus consistently delaying market entry by new generators. ESI Energy, LLC v. FERC, 892 F.3d 321, 324 (D.C. Cir. 2018). FERC responded with Order No. 2003, Standardization of Generator Interconnection Agreements and Procedures, 68 Fed. Reg. 49,846 (Aug. 19, 2003), which “require[d] all transmission facilities to adopt a standard agreement for interconnecting with generators larger than 20 megawatts.” Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277, 1279 (D.C. Cir. 2007) (Utility Commissioners). These agreements are known as Large Generator Interconnection Agreements (LGIAs). Order No. 2003 prescribed a standard LGIA. See Pac. Gas & Elec. Co. v. FERC, 533 F.3d 820, 823 (D.C. Cir. 2008). In Utility Commissioners, this Court upheld Order No. 2003—including its imposition of the standard LGIA—against various facial challenges under section 201(b). See 475 F.3d at 1279–80.

One final feature of the grid bears mention. To facilitate coordination among different transmission owners, FERC has encouraged them to establish Independent System Operators, which operate transmission facilities on behalf of the individual 5 owners. See Morgan Stanley Cap. Grp. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 536–37 (2008). In the six New England states, ISO New England operates the regional power grid. As required by section 205(c) of the Federal Power Act, 16 U.S.C. § 824d(c), it has filed a systemwide tariff setting rates and other terms of service. See Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1036 (D.C. Cir. 2022).

B

This case involves a dispute between NextEra Energy Resources, LLC, which transmits electricity through the New England grid, and Avangrid, Inc., which wishes to do so. It turns on various provisions in the governing tariff and LGIA.

NextEra owns Seabrook Station, a nuclear power-plant located in Seabrook, New Hampshire. Electricity flows from the plant through a circuit breaker, which serves to interrupt fault currents—abnormally high currents caused, for example, by short circuits. When a fault occurs, the circuit breaker temporarily cuts Seabrook off from the grid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reif v. U.S. Department of Labor
District of Columbia, 2026
L.G.M.L v. Noem
District of Columbia, 2025
Energy Harbor, LLC v. FERC
D.C. Circuit, 2025
Michigan Electric Transmission Company, LLC v. FERC
141 F.4th 1296 (D.C. Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
118 F.4th 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/an-opinion-was-released-in-case-23-1094-nextera-energy-resources-llc-v-cadc-2024.